Attach-6-Price Sheet.xlsx
XLSX spreadsheet 12 KB Posted
- Attached to
- LOWER RIO GRANDE-FENCING Federal contract opportunity
- Solicitation number
- 140F0121R0030
About this file
This document contains a price sheet and details of a related federal contract opportunity for fencing projects in Cameron and Hidalgo Counties, Texas. The price sheet includes line items for mobilization, removal of existing boundary fencing, installation of 66,570 linear feet of 4-strand barbed wire fencing, installation of corners, H-braces and gates, as well as T-posts, intermediate posts set in concrete, and clearing along the fenceline. Pricing is to be provided by line item as well as totals including direct costs, bonds and insurance, overhead, and profit. The related federal contract opportunity is solicitation number 140F0121R0030 from the Department of the Interior Fish and Wildlife Service seeking proposals for fencing projects in the Lower Rio Grande area.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attach-8-Past Performance and Clauses.pdf | ||
| Attach-5-La Puerta fence DM seg 4.pdf | ||
| Attach-4-La Puerta fence DM seg 3.pdf | ||
| Attach-7-DBA Min. Wage Rates.pdf | ||
| Attach-3-La Puerta fence DM seg 2.pdf | ||
| Attach-2-La Puerta fence DM seg 1.pdf | ||
| Attach-1-SOW.pdf | ||
| Sol_140F0121R0030.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table 1 LOWER RIO GRANDE VALLEY 2021 La Puerta barbed wire FENCE PROJECT
CAMERON & HIDALGO COUNTIES, TEXAS FENCE PROJECT
| Zip Code | 78516 | BID SCHEDULE | --- | ||
| ASSET # ITEM NO. | La Puerta 4 strand barbed Wire Fence Segments | ||||
| DESCRIPTION | 10007512 | ||||
| QUANTITY UNIT | UNIT PRICE | AMOUNT | |||
| 0001 | MOBILIZATION | 1 Lump Sum | $ | $ | |
| 0002 | REMOVE EXISTING BOUNDARY FENCE | 66,570 LF | $ | $ | |
| 0003 | INSTALL 4 -strand BARBED WIRE FENCE | 66,570 LF | $ | $ | |
| 0004 | INSTALL CORNERS | 9 EA | $ | $ | |
| 0005 | INSTALL H - BRACES | 162 EA | $ | $ | |
| 0006 | INSTALL GATES | 6 EA | $ | $ | |
| 0007 | INSTALL T-POSTS | 1900 EA | $ | $ | |
| 0008 | INSTALL INTERMEDIATE POSTS SET IN CONCRETE | 635 EA | $ | $ | |
| 0009 | CLEARING ALONG FENCELINE | 7.62 AC | $ | $ | |
| SUB-TOTAL Direct Costs | $ | ||||
| Bonds and Insurance | Percent | ||||
| $ | $ | ||||
| Overhead | $ | $ | |||
| Profit | $ |
TOTAL PRICE $