Attach-2-Price Sheet.xlsx

XLSX spreadsheet 21 KB Posted

Attached to
LACASSINE NWR ROAD REHAB
Solicitation number
140F0220R0037
Issued by

About this file

This document contains a price sheet for a shingle replacement project on four quarters buildings and a related federal contract opportunity for road rehabilitation. The price sheet provides estimated costs for shingle replacement, deck replacement, insulation replacement and removal for four quarters buildings damaged by Hurricane Dolly. It includes line items for each building and asset totals. The total estimated cost for the schedule is $63,540.95. The related federal contract opportunity is from the Department of the Interior Fish and Wildlife Service Region 2 for road rehabilitation at the Lacassine NWR. The solicitation number is 140F0220R0037 and provides the opportunity type and short description. No other details are included regarding the requirements, response dates or award information.

View the file

Other files

File Type Posted
Attach-4-Past Performance and Clauses.pdf PDF
Attach-3-DBA Min. Wage Rates.pdf PDF
Sol_140F0220R0037.pdf PDF
Attach-1-SOW.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Shingle Estimate

Project: Quarters Reroofing - Replacement Using Shingles
Prepared by: BRF 11/28/2008
Reference: Hurricane Dolly Estimates prepared by Staff
ITEM NO.DESCRIPTION OF OFFERED ITEMESTIMATED QUANTITYUNITUNIT PRICEESTIMATED AMOUNT
1Quarters 1: Shingle Replacement1700SF$ 2.00$ 3,400.00
2Quarters 1: Insulation replacement1700SF$ 1.00$ 1,700.00
3Quarters 1: Deck replacement1700SF$ 1.50$ 2,550.00
4Quarters 1: Insulation removal851CF$ 0.30$ 255.30
Subtotal$ 7,905.30
5Locality Adjustment @42%$ 3,320.23
6Mobilization and preparatory work @20%$ 1,581.06
SubTotal per Asset$ 12,806.59
7Engineering Services @10%$ 1,280.66
Asset Total$ 14,087.24
1Quarters 2: Shingle Replacement1700SF$ 2.00$ 3,400.00
2Quarters 2: Deck replacement1700SF$ 1.50$ 2,550.00
3Quarters 2: Insulation replacement1700SF$ 1.00$ 1,700.00
4Quarters 2: Insulation removal851CF$ 0.30$ 255.30
Subtotal$ 7,905.30
5Locality Adjustment @42%$ 3,320.23
6Mobilization and preparatory work @20%$ 1,581.06
SubTotal per Asset$ 12,806.59
7Engineering Services @10%$ 1,280.66
Asset Total$ 14,087.24
1Quarters 3: Shingle Replacement1700SF$ 2.00$ 3,400.00
2Quarters 3: Deck replacement1700SF$ 1.50$ 2,550.00
3Quarters 3: Insulation replacement1700SF$ 1.00$ 1,700.00
4Quarters 3: Insulation removal851CF$ 0.30$ 255.30
Subtotal$ 7,905.30
5Locality Adjustment @42%$ 3,320.23
6Mobilization and preparatory work @20%$ 1,581.06
SubTotal per Asset$ 12,806.59
7Engineering Services @10%$ 1,280.66
Asset Total$ 14,087.24
1Quarters 4-1 and 4-2: Shingle Replacement2568SF$ 2.00$ 5,136.00
2Quarters 4-1 and 4-2: Deck replacement2568SF$ 1.50$ 3,852.00
3Quarters 4-1 and 4-2: Insulation replacement2568SF$ 1.00$ 2,568.00
4Quarters 4-1 and 4-2: Insulation removal1284CF$ 0.30$ 385.20
Subtotal$ 11,941.20
5Locality Adjustment @42%$ 5,015.30
6Mobilization and preparatory work @20%$ 2,388.24
SubTotal per Asset$ 19,344.74
7Engineering Services @10%$ 1,934.47
Asset Total$ 21,279.22

TOTAL FOR SCHEDULE $ 63,540.95

&"Arial,Bold"&12Confidential Government Estimate

Prepared by Charles Caldwell &D

BUILDING

Rod Repair
Attach-2-RFP 140F0220R0037
ITEM NO.DescriptionQUANTITYUNITUNIT PRICEAMOUNT
1Bonds & Insurance,1LS$ - 0
2Mobilization1LS$ - 0
$ - 0
3Reshape and Grade Roadway10,666LF$ - 0

4 Ditch Rehabilitation 10,666 LF $ - 0

5 Aggregate Surfacing 9,007 Tons $ - 0

Subtotal $ - 0

11 Oerverhead % % $ - 0

12 Profit % % $ - 0

Total Price $ - 0