FOY Method
| Dover AFB - FA4497-10-R-0006 | |
| TAMMY - THIS PAGE WAS NOT SENT TO BRENDA - CURT HAD HIS OWN DESCRIPTION) | |
| Dover AFB Custodial Service Follow On Year Methodology: | |
| Direct Labor: | |
| Direct Labor wages shall be adjusted each Option Year to reflect the current Wage Determination Rate and will be applied to estimated labor hours. | |
| Indirect Labor (Janitor-Floor Tech, Supervisor and Project Manager): | |
| Indirect labor rates will be adjusted at 2.5% each Option Year. | |
| Direct Labor Health and Welfare: | |
| Health and Welfare rate shall be adjusted each Option Year per the current Wage Determination Rate and will be applied to estimated labor hours. | |
| Indirect Labor Health and Welfare (Janitor-Floor Tech, Supervisor and Project Manager : | |
| Health and Welfare rate shall be adjusted each Option Year per the current Wage Determination Rate and will be applied to estimated labor hours. | |
| Payroll Taxes: | |
| Payroll Taxes will be escalated at 2% each Option Year. | |
| Overhead/G&A/Net Proceeds: | |
| Overhead/G&A/Net Proceeds amount shall be escalated at 2% each Option Year. | |
| Expendable Supplies, Subcontracting and Minor Equipment: | |
| Expendable Supplies and Minor Equipment costs will be escalated at 2% each Option Year. | |
| Fuel Cost: | |
| Fuel cost per Gallon will be adjusted each Option Year based on market research within surrounding area. |
BidSch BY
| 02 May 2022 THROUGH 01 MAY 2023 | 2-Mar-22 | ||||||||||||
| CLIN | Description | Units | Estimated | Estimated | Estimated | ||||||||
| Quantity | Unit Price | Cost | |||||||||||
| Provide all plant, labor, equipment, appliances, and material to remove and dispose of asbestos containing material in accordance with technical specifications. | |||||||||||||
| 0001 | Removal of steel or wood stud walls (non-asbestos) | Sq. Ft. | 1 | $0.00 | |||||||||
| 0002 | Removal of gypsum board materials from wall and ceiling to include asbestos containing joint compound | Sq. Ft. | 1 | $0.00 | |||||||||
| 0003 | Removal of non-asbestos carpet | Sq. Ft. | 1 | $0.00 | |||||||||
| 0004 | Removal of non-asbestos flooring (i.e. ceramic floor or non-asbestos Floor tiles) | Sq. Ft. | 1 | $0.00 | $33,273.66 | $33,273.72 | |||||||
| 0005 | Removal of asbestos containing mastic | Sq. Ft. | 1 | $0.00 | |||||||||
| 0006 | Removal of flooring identified as asbestos containing material to include all removal of mastic. Includes cleaning to clearance standards | $31,884.42 | $31,884.48 | $65,158.20 | $65,142.04 | $65,158.08 | $16.04 | ||||||
| 0006AA | Removal of vinyl asbestos tile | Sq. Ft. | 1 | $0.00 | $24,793.93 | $24,793.92 | |||||||
| 0006AB | Removal of each additional layer of vinyl asbestos tile | Sq. Ft. | 1 | $0.00 | |||||||||
| 0006AC | Removal of asbestos sheet flooring | Sq. Ft. | 1 | $0.00 | $17,316.16 | $17,316.12 | $42,110.04 | $41,733.04 | $42,110.09 | $377.05 | |||
| 0007 | Removal of non-asbestos bathroom fixtures when abatement is required - component reinstalled by others | EA | 1 | $0.00 | $241,572.10 | $241,572.12 | |||||||
| 0008 | Removal of asbestos containing suspended ceilings (drop lay in panel spline) | Sq. Ft. | 1 | $0.00 | |||||||||
| 0009 | Removal of asbestos pipe and fitting insulation for pipes up to 15' above floor (enclosure). Includes Cleaning to Clearance Standards | ||||||||||||
| 0009AA | 3-1/2" or less diameter | L. Ft. | 1 | $0.00 | |||||||||
| 0009AB | 4" to 8" diameter | L. Ft. | 1 | $0.00 | |||||||||
| 0009AC | 9" to 12" diameter | L. Ft. | 1 | $0.00 | $197,020.46 | $197,020.44 | |||||||
| 0009AD | 13" to 18" diameter | L. Ft. | 1 | $0.00 | |||||||||
| 0010 | Removal of asbestos pipe and fitting insulation by glove bag up to 15' above floor. Includes cleaning To clearance standards | ||||||||||||
| 0010AA | 3 1/2" or less diameter | L. Ft. | 1 | $0.00 | $106,668.20 | $106,668.24 | |||||||
| 0010AB | 4" to 8" diameter | L. Ft. | 1 | $0.00 | $51,998.58 | $51,998.64 | $158,666.88 | $157,466.44 | $158,666.78 | $1,200.34 | |||
| 0010AC | 9" to 12" diameter | L. Ft. | 1 | $0.00 | |||||||||
| 0010AD | 13" to 18" diameter | L. Ft. | 1 | $0.00 | |||||||||
| 0011 | Removal of asbestos pipe and fitting insulation for pipes 15' to 75' above floor (enclosure). Includes cleaning To clearance standards | ||||||||||||
| 0011AA | 3-1/2" or less diameter | L. Ft. | 1 | $0.00 | |||||||||
| 0011AB | 4" to 8" diameter | L. Ft. | 1 | $0.00 | $12,885.25 | $12,885.24 | $12,885.24 | $12,883.37 | $12,885.25 | $1.88 | |||
| 0011AC | 9" to 12" diameter | L. Ft. | 1 | $0.00 | $29,091.66 | $29,263.80 | $29,263.80 | $29,297.41 | $29,091.66 | -$205.75 | |||
| 0011AD | 13" to 18" diameter | L. Ft. | 1 | $0.00 | $117,989.69 | $117,989.64 | $117,989.64 | $118,074.13 | $117,989.69 | -$84.44 | |||
| 0012 | Removal of asbestos pipe and fitting insulation by glove bag 15' to 75' above floor. Includes cleaning To clearance standards | ||||||||||||
| 0012AA | 3-1/2" or less diameter | L. Ft. | 1 | $0.00 | $91,184.73 | $91,424.04 | $91,424.04 | $91,535.67 | $91,184.73 | -$350.94 | |||
| 0012AB | 4" to 8" diameter | L. Ft. | 1 | $0.00 | $172,155.90 | $172,155.96 | $172,155.96 | $172,082.39 | $172,155.90 | $73.51 | |||
| 0012AC | 9" to 12" diameter | L. Ft. | 1 | $0.00 | |||||||||
| 0012AD | 13" to 18" diameter | L. Ft. | 1 | $0.00 | $30,422.07 | $30,422.04 | $30,422.04 | $30,316.01 | $30,422.07 | $106.06 | |||
| 0013 | Removal of insulation from equipment or pipes greater than 18" diameter and up to 15' above floor. Includes Cleaning to Clearance Standards | Sq. Ft. | 1 | $0.00 | |||||||||
| 0014 | Removal of insulation from equipment or pipes greater than 18" diameter and up to 15' to 75' above floor. Includes Cleaning to Clearance Standards | Sq. Ft. | 1 | $0.00 | |||||||||
| 0015 | Removal of asbestos cement Panels (transite). Includes Cleaning to Clearance Standards | Sq. Ft. | 1 | $0.00 | |||||||||
| 0016 | Removal of asbestos shingles from roofing | Sq. Ft. | 1 | $0.00 | |||||||||
| 0017 | Removal of asbestos containing built up roofing from deck to include flashing, tar and coatings | Sq. Ft. | 1 | $0.00 | |||||||||
| 0018 | Removal of acoustic tile and asbestos mastic from ceiling and wall and other mastic applications Includes Cleaning to Clearance Standards | Sq. Ft. | 1 | $0.00 | |||||||||
| 0019 | Removal of asbestos containing Gaskets from mechanical rooms | EA | 1 | $0.00 | |||||||||
| 0020 | Removal of asbestos contaminated soil in open areas only | CF | 1 | $0.00 | |||||||||
| 0021 | Removal of asbestos contaminated soil in confined areas only | CF | 1 | $0.00 | |||||||||
| 0022 | Removal of asbestos containing doors from the building | EA | 1 | $0.00 | |||||||||
| 0023 | Removal of asbestos containing window systems from the building to include glazing and caulking | EA | 1 | $0.00 | |||||||||
| 0024 | Decontamination of all interior surfaces using HEPA vacuum and wet wiping methods This CLIN is for cleanup of a Contaminated area, not for cleaning After an abatement | Sq. Ft. | 1 | $0.00 | |||||||||
| 0025 | Decontamination of interior goods and products using HEPA vacuum and wet wiping methods This CLIN is for cleanup of a Contaminated area, not for cleaning After an abatement | Sq. Ft. | 1 | $0.00 | |||||||||
| 0026 | Removal of asbestos contaminated debris | CF | 1 | $0.00 | |||||||||
| 0027 | Removal of non asbestos cinder block wall to access asbestos material | ||||||||||||
| 0027AA | 4 inch cinder block wall | Sq. Ft. | 1 | $0.00 | |||||||||
| 0027AB | 8 inch cinder block wall | Sq. Ft. | 1 | $0.00 | |||||||||
| 0028 | Removal of asbestos containing duct expansion joints from ducts | ||||||||||||
| 0028AA | 0" to 36" up to 25' above floor | L. Ft. | 1 | $0.00 | |||||||||
| 0028AB | 36" to 72" up to 25' above floor | L. Ft. | 1 | $0.00 | |||||||||
| 0028AC | 0" to 36" up to 25' to 75' above floor | L. Ft. | 1 | $0.00 | |||||||||
| 0028AD | 36" to 72" up to 25' to 75' above floor | L. Ft. | 1 | $0.00 | |||||||||
| 0029 | Removal of Asbestos containing cement water pipe. Majority of Digging performed by someone else Minor digging required. High Temperature water may be involved | L. Ft. | 1 | $0.00 | |||||||||
| 0030 | Removal of exterior wall siding containing asbestos | SF | 1 | $0.00 | |||||||||
| 0031 | Removal of piping and asbestos containing insulation underground, within 6 feet of surface. | L. Ft. | 1 | $0.00 | |||||||||
| 0032 | 4 hour response to asbestos Abatement Emergency requests by Dover AFB (Mobilization Cost) | EA | 1 | $0.00 | |||||||||
| Total CLINs 0001 through 0032 | $0.00 | $1,158,256.81 | $1,158,668.40 | $720,075.84 | $718,530.50 | $719,664.25 | $1,133.75 |
&CPage 2 of 10 Attachment 3
BidSch OY1
| 02 May 2023 THROUGH 01 MAY 2024 | ||||||||||||
| CLIN | Description | Units | Estimated | Estimated | Estimated | |||||||
| Quantity | Unit Price | Cost | ||||||||||
| Provide all plant, labor, equipment, appliances, and material to remove and dispose of asbestos containing material in accordance with technical specifications. | ||||||||||||
| 1001 | Removal of steel or wood stud walls (non-asbestos) | Sq. Ft. | 1 | $0.00 | ||||||||
| 1002 | Removal of gypsum board materials from wall and ceiling to include asbestos containing joint compound | Sq. Ft. | 1 | $0.00 | ||||||||
| 1003 | Removal of non-asbestos carpet | Sq. Ft. | 1 | $0.00 | ||||||||
| 1004 | Removal of non-asbestos flooring (i.e. ceramic floor or non-asbestos Floor tiles) | Sq. Ft. | 1 | $0.00 | ||||||||
| 1005 | Removal of asbestos containing mastic | Sq. Ft. | 1 | $0.00 | ||||||||
| 1006 | Removal of flooring identified as asbestos containing material to include all removal of mastic. Includes cleaning to clearance standards | $33,273.66 | $33,273.72 | |||||||||
| 1006AA | Removal of vinyl asbestos tile | Sq. Ft. | 1 | $0.00 | ||||||||
| 1006AB | Removal of each additional layer of vinyl asbestos tile | Sq. Ft. | 1 | $0.00 | $31,884.42 | $31,884.48 | $65,158.20 | $65,142.04 | $65,158.08 | $16.04 | ||
| 1006AC | Removal of asbestos sheet flooring | Sq. Ft. | 1 | $0.00 | ||||||||
| 1007 | Removal of non-asbestos bathroom fixtures when abatement is required - component reinstalled by others | EA | 1 | $0.00 | $24,793.93 | $24,793.92 | ||||||
| 1008 | Removal of asbestos containing suspended ceilings (drop lay in panel spline) | Sq. Ft. | 1 | $0.00 | ||||||||
| 1009 | Removal of asbestos pipe and fitting insulation for pipes up to 15' above floor (enclosure). Includes Cleaning to Clearance Standards | $17,316.16 | $17,316.12 | $42,110.04 | $41,733.04 | $42,110.09 | $377.05 | |||||
| 1009AA | 3-1/2" or less diameter | L. Ft. | 1 | $0.00 | ||||||||
| 1009AB | 4" to 8" diameter | L. Ft. | 1 | $0.00 | $241,572.10 | $241,572.12 | ||||||
| 1009AC | 9" to 12" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 1009AD | 13" to 18" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 1010 | Removal of asbestos pipe and fitting insulation by glove bag up to 15' above floor. Includes cleaning To clearance standards | |||||||||||
| 1010AA | 3 1/2" or less diameter | L. Ft. | 1 | $0.00 | ||||||||
| 1010AB | 4" to 8" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 1010AC | 9" to 12" diameter | L. Ft. | 1 | $0.00 | $197,020.46 | $197,020.44 | ||||||
| 1010AD | 13" to 18" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 1011 | Removal of asbestos pipe and fitting insulation for pipes 15' to 75' above floor (enclosure). Includes cleaning To clearance standards | |||||||||||
| 1011AA | 3-1/2" or less diameter | L. Ft. | 1 | $0.00 | ||||||||
| 1011AB | 4" to 8" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 1011AC | 9" to 12" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 1011AD | 13" to 18" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 1012 | Removal of asbestos pipe and fitting insulation by glove bag 15' to 75' above floor. Includes cleaning To clearance standards | $106,668.20 | $106,668.24 | |||||||||
| 1012AA | 3-1/2" or less diameter | L. Ft. | 1 | $0.00 | $51,998.58 | $51,998.64 | $158,666.88 | $157,466.44 | $158,666.78 | $1,200.34 | ||
| 1012AB | 4" to 8" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 1012AC | 9" to 12" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 1012AD | 13" to 18" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 1013 | Removal of insulation from equipment or pipes greater than 18" diameter and up to 15' above floor. Includes Cleaning to Clearance Standards | Sq. Ft. | 1 | $0.00 | ||||||||
| 1014 | Removal of insulation from equipment or pipes greater than 18" diameter and up to 15' to 75' above floor. Includes Cleaning to Clearance Standards | Sq. Ft. | 1 | $0.00 | ||||||||
| 1015 | Removal of asbestos cement Panels (transite). Includes Cleaning to Clearance Standards | Sq. Ft. | 1 | $0.00 | $12,885.25 | $12,885.24 | $12,885.24 | $12,883.37 | $12,885.25 | $1.88 | ||
| 1016 | Removal of asbestos shingles from roofing | Sq. Ft. | 1 | $0.00 | $29,091.66 | $29,263.80 | $29,263.80 | $29,297.41 | $29,091.66 | -$205.75 | ||
| 1017 | Removal of asbestos containing built up roofing from deck to include flashing, tar and coatings | Sq. Ft. | 1 | $0.00 | ||||||||
| 1018 | Removal of acoustic tile and asbestos mastic from ceiling and wall and other mastic applications Includes Cleaning to Clearance Standards | Sq. Ft. | 1 | $0.00 | $117,989.69 | $117,989.64 | $117,989.64 | $118,074.13 | $117,989.69 | -$84.44 | ||
| 1019 | Removal of asbestos containing Gaskets from mechanical rooms | EA | 1 | $0.00 | ||||||||
| 1020 | Removal of asbestos contaminated soil in open areas only | CF | 1 | $0.00 | $91,184.73 | $91,424.04 | $91,424.04 | $91,535.67 | $91,184.73 | -$350.94 | ||
| 1021 | Removal of asbestos contaminated soil in confined areas only | CF | 1 | $0.00 | ||||||||
| 1022 | Removal of asbestos containing doors from the building | EA | 1 | $0.00 | $172,155.90 | $172,155.96 | $172,155.96 | $172,082.39 | $172,155.90 | $73.51 | ||
| 1023 | Removal of asbestos containing window systems from the building to include glazing and caulking | EA | 1 | $0.00 | ||||||||
| 1024 | Decontamination of all interior surfaces using HEPA vacuum and wet wiping methods This CLIN is for cleanup of a Contaminated area, not for cleaning After an abatement | Sq. Ft. | 1 | $0.00 | $30,422.07 | $30,422.04 | $30,422.04 | $30,316.01 | $30,422.07 | $106.06 | ||
| 1025 | Decontamination of interior goods and products using HEPA vacuum and wet wiping methods This CLIN is for cleanup of a Contaminated area, not for cleaning After an abatement | Sq. Ft. | 1 | $0.00 | ||||||||
| 1026 | Removal of asbestos contaminated debris | CF | 1 | $0.00 | ||||||||
| 1027 | Removal of non asbestos cinder block wall to access asbestos material | |||||||||||
| 1027AA | 4 inch cinder block wall | Sq. Ft. | 1 | $0.00 | ||||||||
| 1027AB | 8 inch cinder block wall | Sq. Ft. | 1 | $0.00 | $1,158,256.81 | $1,158,668.40 | $720,075.84 | $718,530.50 | $719,664.25 | $1,133.75 | ||
| 1028 | Removal of asbestos containing duct expansion joints from ducts | |||||||||||
| 1028AA | 0" to 36" up to 25' above floor | L. Ft. | 1 | $0.00 | ||||||||
| 1028AB | 36" to 72" up to 25' above floor | L. Ft. | 1 | $0.00 | ||||||||
| 1028AC | 0" to 36" up to 25' to 75' above floor | L. Ft. | 1 | $0.00 | ||||||||
| 1028AD | 36" to 72" up to 25' to 75' above floor | L. Ft. | 1 | $0.00 | ||||||||
| 1029 | Removal of Asbestos containing cement water pipe. Majority of Digging performed by someone else Minor digging required. High Temperature water may be involved | L. Ft. | 1 | $0.00 | ||||||||
| 1030 | Removal of exterior wall siding containing asbestos | Sq. Ft. | 1 | $0.00 | ||||||||
| 1031 | Removal of piping and asbestos containing insulation underground, within 6 feet of surface. | L. Ft. | 1 | $0.00 | ||||||||
| 1032 | 4 hour response to asbestos Abatement Emergency requests by Dover AFB (Mobilization Cost) | EA | 1 | $0.00 | ||||||||
| Total CLINs 1001 through 1032 | $0.00 |
&CPage 4 of 10 Attachment 3
BidSch OY2
| 02 MAY 2024 THROUGH 01 MAY 2025 | ||||||||||||
| CLIN | Description | Units | Estimated | Estimated | Estimated | |||||||
| Quantity | Unit Price | Cost | ||||||||||
| Provide all plant, labor, equipment, appliances, and material to remove and dispose of asbestos containing material in accordance with technical specifications. | ||||||||||||
| 2001 | Removal of steel or wood stud walls (non-asbestos) | Sq. Ft. | 1 | $0.00 | ||||||||
| 2002 | Removal of gypsum board materials from wall and ceiling to include asbestos containing joint compound | Sq. Ft. | 1 | $0.00 | ||||||||
| 2003 | Removal of non-asbestos carpet | Sq. Ft. | 1 | $0.00 | ||||||||
| 2004 | Removal of non-asbestos flooring (i.e. ceramic floor or non-asbestos Floor tiles) | Sq. Ft. | 1 | $0.00 | ||||||||
| 2005 | Removal of asbestos containing mastic | Sq. Ft. | 1 | $0.00 | ||||||||
| 2006 | Removal of flooring identified as asbestos containing material to include all removal of mastic. Includes cleaning to clearance standards | |||||||||||
| 2006AA | Removal of vinyl asbestos tile | Sq. Ft. | 1 | $0.00 | ||||||||
| 2006AB | Removal of each additional layer of vinyl asbestos tile | Sq. Ft. | 1 | $0.00 | $33,325.44 | $33,325.44 | $33,325.44 | $81,236.05 | $33,325.44 | -$47,910.61 | ||
| 2006AC | Removal of asbestos sheet flooring | Sq. Ft. | 1 | $0.00 | ||||||||
| 2007 | Removal of non-asbestos bathroom fixtures when abatement is required - component reinstalled by others | EA | 1 | $0.00 | $24,793.93 | $24,793.92 | ||||||
| 2008 | Removal of asbestos containing suspended ceilings (drop lay in panel spline) | Sq. Ft. | 1 | $0.00 | ||||||||
| 2009 | Removal of asbestos pipe and fitting insulation for pipes up to 15' above floor (enclosure). Includes Cleaning to Clearance Standards | $17,316.16 | $17,316.12 | $42,110.04 | $41,733.04 | $42,110.09 | $377.05 | |||||
| 2009AA | 3-1/2" or less diameter | L. Ft. | 1 | $0.00 | ||||||||
| 2009AB | 4" to 8" diameter | L. Ft. | 1 | $0.00 | $241,572.10 | $241,572.12 | ||||||
| 2009AC | 9" to 12" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 2009AD | 13" to 18" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 2010 | Removal of asbestos pipe and fitting insulation by glove bag up to 15' above floor. Includes cleaning To clearance standards | |||||||||||
| 2010AA | 3 1/2" or less diameter | L. Ft. | 1 | $0.00 | ||||||||
| 2010AB | 4" to 8" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 2010AC | 9" to 12" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 2010AD | 13" to 18" diameter | L. Ft. | 1 | $0.00 | $117,761.49 | $117,761.52 | $359,333.64 | $360,061.21 | $359,333.59 | -$727.62 | ||
| 2011 | Removal of asbestos pipe and fitting insulation for pipes 15' to 75' above floor (enclosure). Includes cleaning To clearance standards | |||||||||||
| 2011AA | 3-1/2" or less diameter | L. Ft. | 1 | $0.00 | ||||||||
| 2011AB | 4" to 8" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 2011AC | 9" to 12" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 2011AD | 13" to 18" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 2012 | Removal of asbestos pipe and fitting insulation by glove bag 15' to 75' above floor. Includes cleaning To clearance standards | 1 | $106,668.20 | $106,668.24 | ||||||||
| 2012AA | 3-1/2" or less diameter | L. Ft. | 1 | $0.00 | $51,998.58 | $51,998.64 | $158,666.88 | $157,466.44 | $158,666.78 | $1,200.34 | ||
| 2012AB | 4" to 8" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 2012AC | 9" to 12" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 2012AD | 13" to 18" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 2013 | Removal of insulation from equipment or pipes greater than 18" diameter and up to 15' above floor. Includes Cleaning to Clearance Standards | Sq. Ft. | 1 | $0.00 | ||||||||
| 2014 | Removal of insulation from equipment or pipes greater than 18" diameter and up to 15' to 75' above floor. Includes Cleaning to Clearance Standards | Sq. Ft. | 1 | $0.00 | $182,812.68 | $182,812.68 | $182,812.68 | $182,895.68 | $182,812.68 | -$83.00 | ||
| 2015 | Removal of asbestos cement Panels (transite). Includes Cleaning to Clearance Standards | Sq. Ft. | 1 | $0.00 | ||||||||
| 2016 | Removal of asbestos shingles from roofing | Sq. Ft. | 1 | $0.00 | ||||||||
| 2017 | Removal of asbestos containing built up roofing from deck to include flashing, tar and coatings | Sq. Ft. | 1 | $0.00 | ||||||||
| 2018 | Removal of acoustic tile and asbestos mastic from ceiling and wall and other mastic applications Includes Cleaning to Clearance Standards | Sq. Ft. | 1 | $0.00 | $117,989.69 | $117,989.64 | $117,989.64 | $118,074.13 | $117,989.69 | -$84.44 | ||
| 2019 | Removal of asbestos containing Gaskets from mechanical rooms | EA | 1 | $0.00 | ||||||||
| 2020 | Removal of asbestos contaminated soil in open areas only | CF | 1 | $0.00 | ||||||||
| 2021 | Removal of asbestos contaminated soil in confined areas only | CF | 1 | $0.00 | ||||||||
| 2022 | Removal of asbestos containing doors from the building | EA | 1 | $0.00 | ||||||||
| 2023 | Removal of asbestos containing window systems from the building to include glazing and caulking | EA | 1 | $0.00 | ||||||||
| 2024 | Decontamination of all interior surfaces using HEPA vacuum and wet wiping methods This CLIN is for cleanup of a Contaminated area, not for cleaning After an abatement | Sq. Ft. | 1 | $0.00 | $30,422.07 | $30,422.04 | $30,422.04 | $30,316.01 | $30,422.07 | $106.06 | ||
| 2025 | Decontamination of interior goods and products using HEPA vacuum and wet wiping methods This CLIN is for cleanup of a Contaminated area, not for cleaning After an abatement | Sq. Ft. | 1 | $0.00 | ||||||||
| 2026 | Removal of asbestos contaminated debris | CF | 1 | $0.00 | ||||||||
| 2027 | Removal of non asbestos cinder block wall to access asbestos material | |||||||||||
| 2027AA | 4 inch cinder block wall | Sq. Ft. | 1 | $0.00 | ||||||||
| 2027AB | 8 inch cinder block wall | Sq. Ft. | 1 | $0.00 | $924,660.34 | $924,660.36 | $924,660.36 | $971,782.56 | $924,660.34 | -$47,122.22 | ||
| 2028 | Removal of asbestos containing duct expansion joints from ducts | |||||||||||
| 2028AA | 0" to 36" up to 25' above floor | L. Ft. | 1 | $0.00 | ||||||||
| 2028AB | 36" to 72" up to 25' above floor | L. Ft. | 1 | $0.00 | ||||||||
| 2028AC | 0" to 36" up to 25' to 75' above floor | L. Ft. | 1 | $0.00 | ||||||||
| 2028AD | 36" to 72" up to 25' to 75' above floor | L. Ft. | 1 | $0.00 | ||||||||
| 2029 | Removal of Asbestos containing cement water pipe. Majority of Digging performed by someone else Minor digging required. High Temperature water may be involved | L. Ft. | 1 | $0.00 | ||||||||
| 2030 | Removal of exterior wall siding containing asbestos | Sq. Ft. | 1 | $0.00 | ||||||||
| 2031 | Removal of piping and asbestos containing insulation underground, within 6 feet of surface. | L. Ft. | 1 | $0.00 | ||||||||
| 2032 | 4 hour response to asbestos Abatement Emergency requests by Dover AFB Mobilization Cost | EA | 1 | $0.00 | ||||||||
| Total CLINs 2001 through 2032 | $0.00 |
&C&"Arial,Bold"ASBESTOS ABATEMENT CONTRACT
PRICING SCHEDULE
Option Year 2 &CPage 5 of 10 Attachment 3
BidSch OY3
| 02 MAY 2025 THROUGH 01 MAY 2026 | ||||||||||||
| CLIN | Description | Units | Estimated | Estimated | Estimated | |||||||
| Quantity | Unit Price | Cost | ||||||||||
| Provide all plant, labor, equipment, appliances, and material to remove and dispose of asbestos containing material in accordance with technical specifications. | ||||||||||||
| 3001 | Removal of steel or wood stud walls (non-asbestos) | Sq. Ft. | 1 | $0.00 | ||||||||
| 3002 | Removal of gypsum board materials from wall and ceiling to include asbestos containing joint compound | Sq. Ft. | 1 | $0.00 | ||||||||
| 3003 | Removal of non-asbestos carpet | Sq. Ft. | 1 | $0.00 | ||||||||
| 3004 | Removal of non-asbestos flooring (i.e. ceramic floor or non-asbestos Floor tiles) | Sq. Ft. | 1 | $0.00 | ||||||||
| 3005 | Removal of asbestos containing mastic | Sq. Ft. | 1 | $0.00 | ||||||||
| 3006 | Removal of flooring identified as asbestos containing material to include all removal of mastic. Includes cleaning to clearance standards | |||||||||||
| 3006AA | Removal of vinyl asbestos tile | Sq. Ft. | 1 | $0.00 | ||||||||
| 3006AB | Removal of each additional layer of vinyl asbestos tile | Sq. Ft. | 1 | $0.00 | $33,325.44 | $33,325.44 | $33,325.44 | $81,236.05 | $33,325.44 | -$47,910.61 | ||
| 3006AC | Removal of asbestos sheet flooring | Sq. Ft. | 1 | $0.00 | ||||||||
| 3007 | Removal of non-asbestos bathroom fixtures when abatement is required - component reinstalled by others | EA | 1 | $0.00 | $24,793.93 | $24,793.92 | ||||||
| 3008 | Removal of asbestos containing suspended ceilings (drop lay in panel spline) | Sq. Ft. | 1 | $0.00 | ||||||||
| 3009 | Removal of asbestos pipe and fitting insulation for pipes up to 15' above floor (enclosure). Includes Cleaning to Clearance Standards | $17,316.16 | $17,316.12 | $42,110.04 | $41,733.04 | $42,110.09 | $377.05 | |||||
| 3009AA | 3-1/2" or less diameter | L. Ft. | 1 | $0.00 | ||||||||
| 3009AB | 4" to 8" diameter | L. Ft. | 1 | $0.00 | $241,572.10 | $241,572.12 | ||||||
| 3009AC | 9" to 12" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 3009AD | 13" to 18" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 3010 | Removal of asbestos pipe and fitting insulation by glove bag up to 15' above floor. Includes cleaning To clearance standards | |||||||||||
| 3010AA | 3 1/2" or less diameter | L. Ft. | 1 | $0.00 | ||||||||
| 3010AB | 4" to 8" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 3010AC | 9" to 12" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 3010AD | 13" to 18" diameter | L. Ft. | 1 | $0.00 | $117,761.49 | $117,761.52 | $359,333.64 | $360,061.21 | $359,333.59 | -$727.62 | ||
| 3011 | Removal of asbestos pipe and fitting insulation for pipes 15' to 75' above floor (enclosure). Includes cleaning To clearance standards | |||||||||||
| 3011AA | 3-1/2" or less diameter | L. Ft. | 1 | $0.00 | ||||||||
| 3011AB | 4" to 8" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 3011AC | 9" to 12" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 3011AD | 13" to 18" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 3012 | Removal of asbestos pipe and fitting insulation by glove bag 15' to 75' above floor. Includes cleaning To clearance standards | $106,668.20 | $106,668.24 | |||||||||
| 3012AA | 3-1/2" or less diameter | L. Ft. | 1 | $0.00 | $51,998.58 | $51,998.64 | $158,666.88 | $157,466.44 | $158,666.78 | $1,200.34 | ||
| 3012AB | 4" to 8" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 3012AC | 9" to 12" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 3012AD | 13" to 18" diameter | L. Ft. | 1 | $0.00 | ||||||||
| 3013 | Removal of insulation from equipment or pipes greater than 18" diameter and up to 15' above floor. Includes Cleaning to Clearance Standards | Sq. Ft. | 1 | $0.00 | ||||||||
| 3014 | Removal of insulation from equipment or pipes greater than 18" diameter and up to 15' to 75' above floor. Includes Cleaning to Clearance Standards | Sq. Ft. | 1 | $0.00 | ||||||||
| 3015 | Removal of asbestos cement Panels (transite). Includes Cleaning to Clearance Standards | Sq. Ft. | 1 | $0.00 | ||||||||
| 3016 | Removal of asbestos shingles from roofing | Sq. Ft. | 1 | $0.00 | $29,091.66 | $29,263.80 | $29,263.80 | $29,297.41 | $29,091.66 | -$205.75 | ||
| 3017 | Removal of asbestos containing built up roofing from deck to include flashing, tar and coatings | Sq. Ft. | 1 | $0.00 | ||||||||
| 3018 | Removal of acoustic tile and asbestos mastic from ceiling and wall and other mastic applications Includes Cleaning to Clearance Standards | Sq. Ft. | 1 | $0.00 | ||||||||
| 3019 | Removal of asbestos containing Gaskets from mechanical rooms | EA | 1 | $0.00 | ||||||||
| 3020 | Removal of asbestos contaminated soil in open areas only | CF | 1 | $0.00 | $91,184.73 | $91,424.04 | $91,424.04 | $91,535.67 | $91,184.73 | -$350.94 | ||
| 3021 | Removal of asbestos contaminated soil in confined areas only | CF | 1 | $0.00 | ||||||||
| 3022 | Removal of asbestos containing doors from the building | EA | 1 | $0.00 | $172,155.90 | $172,155.96 | $172,155.96 | $172,082.39 | $172,155.90 | $73.51 | ||
| 3023 | Removal of asbestos containing window systems from the building to include glazing and caulking | EA | 1 | $0.00 | ||||||||
| 3024 | Decontamination of all interior surfaces using HEPA vacuum and wet wiping methods This CLIN is for cleanup of a Contaminated area, not for cleaning After an abatement | Sq. Ft. | 1 | $0.00 | ||||||||
| 3025 | Decontamination of interior goods and products using HEPA vacuum and wet wiping methods This CLIN is for cleanup of a Contaminated area, not for cleaning After an abatement | Sq. Ft. | 1 | $0.00 | ||||||||
| 3026 | Removal of asbestos contaminated debris | CF | 1 | $0.00 | ||||||||
| 3027 | Removal of non asbestos cinder block wall to access asbestos material | |||||||||||
| 3027AA | 4 inch cinder block wall | Sq. Ft. | 1 | $0.00 | ||||||||
| 3027AB | 8 inch cinder block wall | Sq. Ft. | 1 | $0.00 | $885,868.19 | $886,279.80 | $886,279.80 | $933,412.21 | $885,868.19 | -$47,544.02 | ||
| 3028 | Removal of asbestos containing duct expansion joints from ducts | |||||||||||
| 3028AA | 0" to 36" up to 25' above floor | L. Ft. | 1 | $0.00 | ||||||||
| 3028AB | 36" to 72" up to 25' above floor | L. Ft. | 1 | $0.00 | ||||||||
| 3028AC | 0" to 36" up to 25' to 75' above floor | L. Ft. | 1 | $0.00 | ||||||||
| 3028AD | 36" to 72" up to 25' to 75' above floor | L. Ft. | 1 | $0.00 | ||||||||
| 3029 | Removal of Asbestos containing cement water pipe. Majority of Digging performed by someone else Minor digging required. High Temperature water may be involved | L. Ft. | 1 | $0.00 | ||||||||
| 3030 | Removal of exterior wall siding containing asbestos | Sq. Ft. | 1 | $0.00 | ||||||||
| 3031 | Removal of piping and asbestos containing insulation underground, within 6 feet of surface. | L. Ft. | 1 | $0.00 | ||||||||
| 3032 | 4 hour response to asbestos Abatement Emergency requests by Dover AFB Mobilization Cost | EA | 1 | $0.00 | ||||||||
| Total CLINs 3001 through 3032 | $0.00 |
&C&"Arial,Bold"ASBESTOS ABATEMENT CONTRACT
PRICING SCHEDULE
Option Year 3 &CPage 7 of 10 Attachment 3
BidSch OY4
| 02 MAY 2026 THROUGH 01 MAY 2027 | |||||||||||||
| CLIN | Description | Units | Estimated | Estimated | Estimated | ||||||||
| Quantity | Unit Price | Cost | |||||||||||
| Provide all plant, labor, equipment, appliances, and material to remove and dispose of asbestos containing material in accordance with technical specifications. | |||||||||||||
| 4001 | Removal of steel or wood stud walls (non-asbestos) | Sq. Ft. | 1 | $0.00 | |||||||||
| 4002 | Removal of gypsum board materials from wall and ceiling to include asbestos containing joint compound | Sq. Ft. | 1 | $0.00 | |||||||||
| 4003 | Removal of non-asbestos carpet | Sq. Ft. | 1 | $0.00 | |||||||||
| 4004 | Removal of non-asbestos flooring (i.e. ceramic floor or non-asbestos Floor tiles) | Sq. Ft. | 1 | $0.00 | |||||||||
| 4005 | Removal of asbestos containing mastic | Sq. Ft. | 1 | $0.00 | |||||||||
| 4006 | Removal of flooring identified as asbestos containing material to include all removal of mastic. Includes cleaning to clearance standards | ||||||||||||
| 4006AA | Removal of vinyl asbestos tile | Sq. Ft. | 1 | $0.00 | |||||||||
| 4006AB | Removal of each additional layer of vinyl asbestos tile | Sq. Ft. | 1 | $0.00 | $33,325.44 | $33,325.44 | $33,325.44 | $81,236.05 | $33,325.44 | -$47,910.61 | |||
| 4006AC | Removal of asbestos sheet flooring | Sq. Ft. | 1 | $0.00 | |||||||||
| 4007 | Removal of non-asbestos bathroom fixtures when abatement is required - component reinstalled by others | EA | 1 | $0.00 | $24,793.93 | $24,793.92 | |||||||
| 4008 | Removal of asbestos containing suspended ceilings (drop lay in panel spline) | Sq. Ft. | 1 | $0.00 | |||||||||
| 4009 | Removal of asbestos pipe and fitting insulation for pipes up to 15' above floor (enclosure). Includes Cleaning to Clearance Standards | $17,316.16 | $17,316.12 | $42,110.04 | $41,733.04 | $42,110.09 | $377.05 | ||||||
| 4009AA | 3-1/2" or less diameter | L. Ft. | 1 | $0.00 | |||||||||
| 4009AB | 4" to 8" diameter | L. Ft. | 1 | $0.00 | $241,572.10 | $241,572.12 | |||||||
| 4009AC | 9" to 12" diameter | L. Ft. | 1 | $0.00 | |||||||||
| 4009AD | 13" to 18" diameter | L. Ft. | 1 | $0.00 | |||||||||
| 4010 | Removal of asbestos pipe and fitting insulation by glove bag up to 15' above floor. Includes cleaning To clearance standards | ||||||||||||
| 4010AA | 3 1/2" or less diameter | L. Ft. | 1 | $0.00 | |||||||||
| 4010AB | 4" to 8" diameter | L. Ft. | 1 | $0.00 | |||||||||
| 4010AC | 9" to 12" diameter | L. Ft. | 1 | $0.00 | |||||||||
| 4010AD | 13" to 18" diameter | L. Ft. | 1 | $0.00 | $117,761.49 | $117,761.52 | $359,333.64 | $360,061.21 | $359,333.59 | -$727.62 | |||
| 4011 | Removal of asbestos pipe and fitting insulation for pipes 15' to 75' above floor (enclosure). Includes cleaning To clearance standards | ||||||||||||
| 4011AA | 3-1/2" or less diameter | L. Ft. | 1 | $0.00 | |||||||||
| 4011AB | 4" to 8" diameter | L. Ft. | 1 | $0.00 | |||||||||
| 4011AC | 9" to 12" diameter | L. Ft. | 1 | $0.00 | |||||||||
| 4011AD | 13" to 18" diameter | L. Ft. | 1 | $0.00 | |||||||||
| 4012 | Removal of asbestos pipe and fitting insulation by glove bag 15' to 75' above floor. Includes cleaning To clearance standards | $106,668.20 | $106,668.24 | ||||||||||
| 4012AA | 3-1/2" or less diameter | L. Ft. | 1 | $0.00 | $51,998.58 | $51,998.64 | $158,666.88 | $157,466.44 | $158,666.78 | $1,200.34 | |||
| 4012AB | 4" to 8" diameter | L. Ft. | 1 | $0.00 | |||||||||
| 4012AC | 9" to 12" diameter | L. Ft. | 1 | $0.00 | |||||||||
| 4012AD | 13" to 18" diameter | L. Ft. | 1 | $0.00 | |||||||||
| 4013 | Removal of insulation from equipment or pipes greater than 18" diameter and up to 15' above floor. Includes Cleaning to Clearance Standards | Sq. Ft. | 1 | $0.00 | |||||||||
| 4014 | Removal of insulation from equipment or pipes greater than 18" diameter and up to 15' to 75' above floor. Includes Cleaning to Clearance Standards | Sq. Ft. | 1 | $0.00 | $182,812.68 | $182,812.68 | $182,812.68 | $182,895.68 | $182,812.68 | -$83.00 | |||
| 4015 | Removal of asbestos cement Panels (transite). Includes Cleaning to Clearance Standards | Sq. Ft. | 1 | $0.00 | |||||||||
| 4016 | Removal of asbestos shingles from roofing | Sq. Ft. | 1 | $0.00 | |||||||||
| 4017 | Removal of asbestos containing built up roofing from deck to include flashing, tar and coatings | Sq. Ft. | 1 | $0.00 | |||||||||
| 4018 | Removal of acoustic tile and asbestos mastic from ceiling and wall and other mastic applications Includes Cleaning to Clearance Standards | Sq. Ft. | 1 | $0.00 | $117,989.69 | $117,989.64 | $117,989.64 | $118,074.13 | $117,989.69 | -$84.44 | |||
| 4019 | Removal of asbestos containing Gaskets from mechanical rooms | EA | 1 | $0.00 | |||||||||
| 4020 | Removal of asbestos contaminated soil in open areas only | CF | 1 | $0.00 | |||||||||
| 4021 | Removal of asbestos contaminated soil in confined areas only | CF | 1 | $0.00 | |||||||||
| 4022 | Removal of asbestos containing doors from the building | EA | 1 | $0.00 | $172,155.90 | $172,155.96 | $172,155.96 | $172,082.39 | $172,155.90 | $73.51 | |||
| 4023 | Removal of asbestos containing window systems from the building to include glazing and caulking | EA | 1 | $0.00 | |||||||||
| 4024 | Decontamination of all interior surfaces using HEPA vacuum and wet wiping methods This CLIN is for cleanup of a Contaminated area, not for cleaning After an abatement | Sq. Ft. | 1 | $0.00 | |||||||||
| 4025 | Decontamination of interior goods and products using HEPA vacuum and wet wiping methods This CLIN is for cleanup of a Contaminated area, not for cleaning After an abatement | Sq. Ft. | 1 | $0.00 | |||||||||
| 4026 | Removal of asbestos contaminated debris | CF | 1 | $0.00 | |||||||||
| 4027 | Removal of non asbestos cinder block wall to access asbestos material | ||||||||||||
| 4027AA | 4 inch cinder block wall | Sq. Ft. | 1 | $0.00 | |||||||||
| 4027AB | 8 inch cinder block wall | Sq. Ft. | 1 | $0.00 | $1,066,394.17 | $1,066,394.28 | $1,066,394.28 | $1,113,548.94 | $1,066,394.17 | -$47,154.77 | |||
| 4028 | Removal of asbestos containing duct expansion joints from ducts | ||||||||||||
| 4028AA | 0" to 36" up to 25' above floor | L. Ft. | 1 | $0.00 | |||||||||
| 4028AB | 36" to 72" up to 25' above floor | L. Ft. | 1 | $0.00 | |||||||||
| 4028AC | 0" to 36" up to 25' to 75' above floor | L. Ft. | 1 | $0.00 | |||||||||
| 4028AD | 36" to 72" up to 25' to 75' above floor | L. Ft. | 1 | $0.00 | |||||||||
| 4029 | Removal of Asbestos containing cement water pipe. Majority of Digging performed by someone else Minor digging required. High Temperature water may be involved | L. Ft. | 1 | $0.00 | |||||||||
| 4030 | Removal of exterior wall siding containing asbestos | Sq. Ft. | 1 | $0.00 | |||||||||
| 4031 | Removal of piping and asbestos containing insulation underground, within 6 feet of surface. | L. Ft. | 1 | $0.00 | |||||||||
| 4032 | 4 hour response to asbestos Abatement Emergency requests by Dover AFB Mobilization Cost | EA | 1 | $0.00 | |||||||||
| Total CLINs 4001 through 4032 | $0.00 | ||||||||||||
| Total Base Year CLINs 0001 through 0032 | $0.00 | ||||||||||||
| Total Option Year 1 CLINs 1001 through 1032 | $0.00 | ||||||||||||
| Total Option Year 2 CLINs 2001 through 2032 | $0.00 | ||||||||||||
| Total Option Year 3 CLINs 3001 through 3032 | $0.00 | ||||||||||||
| Total Option Year 4 CLINs 4001 through 4032 | $0.00 | ||||||||||||
| Total Initial and Four Option Years 0001 through 4032 | $0.00 |
&C&"Arial,Bold"ASBESTOS ABATEMENT CONTRACT
PRICING SCHEDULE
Option Year 4 &CPage 9 of 10 Attachment 3