Attach 1 - Statement of Work.pdf
PDF 275 KB Posted
- Solicitation number
- NB688000-26-01975
About this file
This is a Statement of Work (SOW) for the provision of Ku-band geostationary satellite transponder bandwidth to support two-way satellite time/frequency transfer (TWSTFT) operations.
NIST and a collaboration of 19 national metrological laboratories and technical institutes require non-preemptable (reserved) transponder bandwidth on a station-kept geostationary satellite to enable high-precision exchange of time signals for international atomic time (TAI and UTC) coordination. The service must support existing TimeTech SATRE Earth station modems operating at 2.5 Mc/s symbol rate with binary phase-shift keying (BPSK) modulation and approximately 4 MHz occupied bandwidth. Technical specifications require uplink carriers within 14.0–14.5 GHz, downlink carriers within 10.95–12.5 GHz, linear cross-polarized configuration, equivalent isotropically radiated power (EIRP) ≥42 dBW (unless justified), and coverage accommodating 17 Earth stations across North America and Europe with specific communication requirements. The satellite longitude must fall within 30°W through 45°W. The contractor must provide a comprehensive transmission plan including link power budget, availability estimate, and coverage analysis. The period of performance extends from November 27, 2026, 00:00 UTC through November 26, 2027, 23:59 UTC.
Two deliverables are required: (1) authorization to transmit with assigned carrier frequencies and transmission control parameters due November 20, 2026, and (2) one year of operational transponder bandwidth service commencing November 27, 2026. Payment is 100% upon installation, acceptance, successful testing, and proper invoicing under Net 30-day terms. Annual service costs are distributed as 25% to NIST, 25% to U.S. Naval Observatory (USNO), and 50% to Physikalisch-Technische Bundesanstalt (PTB), Germany. Monthly invoices will be issued to the three cost-sharing members. If the vendor is not the direct satellite owner/operator, a signed letter of supply guaranteeing service availability must be provided. Performance testing will be conducted prior to November 27, 2026, and the vendor may be present at its own expense.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attch 5- QAs.xls | XLS spreadsheet | |
| Attch 3- Experience Project Data Sheet.docx | DOCX document | |
| Attch 2 - Additional Specs ROM.pdf | ||
| RFQ NB688000-26-01975.pdf | ||
| Attch 4- Past Performance Questionnaire.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Title: Ku-band geostationary satellite transponder bandwidth
Date: 5 June 2026
I. BACKGROUND INFORMATION
NIST is one of the official sources of time and frequency for the United States and for international coordination of time and frequency. The Time Realization and Distribution group maintains the primary frequency standards, the time scale, and the time transfer operations for the U.S. contribution to the International Bureau of Weights and Measures. The primary frequency standard for the U.S. is currently our cesium fountain standard, NIST-F4. The time scale is a weighted average of several atomic clocks whose frequencies and linear frequency drifts are regularly measured against primary frequency standards. Two-way satellite time/frequency transfer (TWSTFT) is the method for comparing our clocks with standards around the world for our participation in the generation of international atomic time (TAI and
UTC).
II. PURPOSE
A network of nineteen national metrological laboratories (NMIs) and technical institutes (the Collaboration), including NIST, uses Ku-band geostationary satellite transponder bandwidth to enable high precision exchange of time signals using the two-way satellite time/frequency transfer (TWSTFT) technique. NIST uses the satellite link as the primary method of transmitting NIST’s realization of Coordinated Universal Time (UTC) to the International Bureau of Weights and Measures (BIPM) via European NMIs.
The satellite TWSTFT technique is the only time transfer method capable of the required sub-nanosecond precision over trans-continental distances, free from dependence on Global Navigation Satellite Systems (GNSS) like GPS, and accepted by BIPM. Because the Collaboration’s TWSTFT network is currently operating with an installed base of equipment (here, “Earth stations”), several service parameters are fixed for compatibility. The purpose of this acquisition is continuation of the active network without interruption.
PLACE OF PERFORMANCE
A satellite transponder physically exists in geostationary orbit around Earth. Transponder service is provided by administrative activities at vendor’s place(s) of business. Once authorized, transponder service is highly automated and available with little to no interruptions over the entire period of performance.
PERIOD OF PERFORMANCE
From November 27, 2026, 00:00 UTC through November 26, 2027, 23:59 UTC.
III. SPECIFIC REQUIREMENTS
TASKS
Task 1 – Provision of compatible Ku-band geostationary satellite bandwidth
The contractor shall:
1.1 Acquire and permit NIST and the network of laboratories listed in Table 1 below (the Collaboration) the use of non-preemptable (reserved) transponder bandwidth on a station-kept geostationary satellite. Additional requirements follow.
1.2 Ensure uplink carrier(s) are within the range 14.0 GHz to 14.5 GHz.
1.3 Ensure downlink carrier(s) are within the range 10.95 to 12.5 GHz.
1.4 Ensure the polarization type is linear and cross-polarized. Collaboration Earth stations must not be required to change polarizations or re-point antennas to communicate with any other Collaboration Earth station. Carrier frequencies may change to support “cross-strapped” transponders enabling communication links between North America and Europe. See attached document “2026_05_16_request_for_Ku_bandwidth_ROM” for additional details and examples.
1.5 Provide a transmission plan including a link power budget, availability estimate, and coverage for all Earth stations listed in Table 1 below. Note: the two North American stations need not communicate with each other but must be able to communicate with all European stations. All European stations must be able to communicate with each other and the North American stations. Roughly, based on public information, the required longitude of the satellite will be within 30°W through 45°W.
1.6 Ensure the transponder’s equivalent isotopically radiated power (EIRP) >= 42 dBW unless justified by the vendor’s transmission plan and link budget.
1.7 Ensure the transponder service is compatible with existing, already-deployed Earth station modems: make/model is TimeTech SATRE. The transmission mode is a pseudorandom noise (PRN) code at a 2.5 Mc/s symbol rate. Modulation is binary phase-shift keying (BPSK). The occupied bandwidth is approximately 4 MHz but should be accurately budgeted by the vendor’s transmission plan. Additional Earth station information needed to compute a transmission plan is listed in Table 1, below.
1.8 Ensure the Collaboration is permitted to use the transponder service over the full term of service, one year from November 27, 2026, through November 26, 2027.
1.9 Provide for a billing arrangement that allows for an existing cost-sharing arrangement between Collaboration members: 25% to NIST, 25% to U.S. Naval Observatory (USNO), 50% to Physikalisch-Technische Bundesanstalt (PTB), 38116 Braunschweig, Germany.
1.10 If not included in the transmission plan, vendor shall provide a signed letter of supply from the owner/operator of the proposed geostationary satellite transponder, guaranteeing availability of service over the specified term.
IV. GENERAL REQUIREMENTS
Include all requirements that are not specific tasks but are applicable to the overall contract and the work that will be performed. For example, IT Security, Government Property, Public Affairs Clearance, OMB clearance, printing, data rights, etc.
Government Responsibilities NIST and each Earth station in the Collaboration, agree to perform transmission test and tuning to the satisfaction of the geostationary satellite transponder owner/operator prior to regular link operation. The Collaboration also agrees to abide by transmission control requirements issued by the transponder owner/operator.
Government Furnished Property
All government furnished property required to enable use of the transponder link already exist at Collaboration Earth stations and shall remain the property of NIST or respective Collaboration members.
Inspection & Acceptance In addition to the inspection and acceptance terms articulated in 52.212-4, the Government reserves the right to perform such performance tests and evaluations as defined below to verify specified system performance. Such tests and evaluations, if performed, shall be conducted within the environment that the system is to be operated. The Contractor has the right to be present during the tests and evaluations, if performed, at the Contractor’s expense.
Performance Tests:
1. NIST and other Collaboration Earth stations shall perform transmission tests to confirm operation of the geostationary satellite transponder service on or (if authorized by vendor) before November 27, 2026.
Authorized representative: If vendor is not the direct owner/operator of the proposed geostationary satellite transponder, vendor must be authorized to reserve, broker, or resell geostationary satellite transponder bandwidth on behalf of the owner/operator.
V. SCHEDULE OF DELIVERABLES
Define all deliverables and indicate (1) the quantity desired; (2) the format in which each deliverable is to be supplied; (3) the delivery date (based on the number of weeks/days); (4) the place of delivery. The context of each deliverable shall be clear. Keep in mind that every task does not require a deliverable. Deliverables are always tangible items (i.e., report, minutes, etc.)
Complete the table providing the information for all the tasks identified above.
Deliverable Number Description Format Due Date
Quantity
1 Authorization to transmit on a geostationary satellite transponder;
service meeting all requirements in Task 1.
Assignment of carrier frequencies and transmission control parameters.
Electronic data transmission
One week prior to transponder service start date, November 20, 2026.
2 One year of geostationary transponder bandwidth service
Performance of geostationary satellite transponder
November 27, 2026, at 00:00
UTC.
1 year meeting all requirements in Task 1.
Standards of Acceptance: The NIST POC or COR shall review all the above deliverables and respond with an acceptance or request for revision email to the Contractor Point of Contact (POC) within 7 days. This section applies to deliverables which must be reviewed and approved for acceptances (e.g., draft plans, drawings, etc.)
VI. PAYMENT SCHEDULE
Define how the contractor will be compensated. If firm fixed price define percentage of payment or amount for each deliverable.
Advance payment is not authorized. The Contractor must invoice in the arrears according to the payment schedule. The Contractor shall be paid, in accordance with Net 30-day payment terms, upon receipt and acceptance of a proper invoice, in accordance with the following schedule:
1. 100% after installation and acceptance by the POC of fully installed system, AND
2. After the successful completion of the testing requirements set forth in this document under section set forth in this document, AND
3. After successful demonstration by the instrumentation that it performs IAW the technical requirements set forth in this document AND
4. After receiving an invoice submitted properly, IAW the purchase order terms and conditions.
Annual service shall be billed monthly, with invoices issued to the three Collaboration members in accordance with Task element 1.9: 25% of service cost to NIST, 25% to USNO, 50% to PTB, Germany.
NOTE: Partial shipments and partial invoices will not be accepted, unless otherwise requested and accepted by the Contracting Officer prior to award offer. Proposed payment schedules shall be submitted with vendor’s response to the RFQ for consideration.
Table 1
Collaboration Earth station information
No. Location Station ID Antenna size (m)
Nominal Tx Power (W)
Max Tx Power (W)
North America 1 Boulder, CO, USA NIST01-E1 3.7 0.5 1 2 Washington DC, USA USNO2-E2 4.5 1 5
Europe 1 Delft, The Netherlands VSL01 2.4 1 5 2 PTB, Braunschweig, Germany BRS-02G 1.8 6.3 8 3 Torino, Italy IEN-02K2 1.8 4 4
4 Boras, Sweden SP01 1.8 1.5 8 5 Paris, France PARIS OP01 2.4 0.1 8 6 San Fernando, Spain ROA01 1.8 4 4 7 Lisboa, Portugal LSB-02K3 1.8 4 4 8 Teddington, UK NPL-02G 2.4 0.2 6 9 Bern, Switzerland BEW-01NP 1.8 0.4 4
10 Borowiec, Poland AOS01 2.4 4 8 11 Plateau Calern, France CAUSSOLS OCA01 1.8 4 4 12 Besançon, France BESANCON LTFB01 2.4 0.1 16 13 Fucino, Italy PTF101 1.8 2 8 14 Oberpfaffenhofen, Germany PTF201 1.8 2 8 15 Stuttgart, Germany TIM01 1.8 2 8 16 Kocaeli, Turkey UME0 1.8 2 8 17 Warsaw, Poland PL01 1.8 2 8
File details come from the government source that posted it. Updated .