Southwestern Native Aquatic Resources & Recovery Center Chaves County, NM Rehab Well #4
PART 1 GENERAL
1.1 PROJECT DESCRIPTION
A. Perform the following work on Rehab and Repair of Well #4 at the Southwestern Native Aquatic Resources & Recovery Center, located approximately 16 miles southeast of Roswell, New Mexico.
1.2 DESCRIPTION OF WORK
A. The work includes the following as specified in section1.3
1. Remove and inspect Pump, replace worn parts.
B. Total Period of Performance is 30 calendar days as stated in the solicitation exclusive of Government review time.
C. SOW Questions please contact Manuel Ulibarri 575-420-1580 email: manuel_ulibarri@fws.gov
1.3 REQUIREMENTS
A. Pumps and motors shall have the following characteristics and properties:
1. Install one 3 stage bowl assembly. Bowl assembly shall be manufactured by Simflo or equal.
2. Install one 8”x10’open bottom suction pipe.
3. Install twelve 8" X 9' 11-1/4" X .322 wall butt column pipe T&C.
4. Install one 8" X 4' 11-1/4" X .322 wall butt column pipe T&C.
5. Install 13 water lube spider 18-8SS 8" X 2" X .75" drop in.
6. Install 13 rubber spider bearing insert 1.18" X 2.00" R3.
7. Install one 1.18" X 5' 10THRD 416SS water lube shaft.
8. Install twelve 1.18" X 10' 10THRD 416SS water lube shaft.
9. Install one 1.18" rubber slinger ring.
10. Install 90 inches of 1.18" 416SS headshaft.
11. Install one 6” full face rubber gasket 1/8”.
12. Install thirteen 1.18" shaft coupling 10TPI 416SS.
13. Video tape well #4 casing to determine overall condition.
All work shall include all labor for machining, pump removal, pump installation, packing box overhaul, and test pumping.
B. Well shall be purged of all rust and dirt for a minimum of 6 hours once operational.
C. Submit cost proposal for additional work other than that specified in section 1.3A if necessary.
1.4 UTILITIES
A. Power and water for construction is available at the site. The contractor shall make all arrangements to provide power and water if needed for its operation.
1.5 USE OF PREMISES
Southwestern Native Aquatic Resources & Recovery Center Chaves County, NM Rehab Well #4
A. Contractor activities are limited to Hatchery hours of work: during official daylight hours, Monday through Wednesday, 6:30 am to 4:00 pm. No work will be permitted on Thursdays or Fridays. Work is not permitted on weekends or Federal Holidays without prior approval by Hatchery Manager.
B. All work is to be scheduled with the facility Manager prior to any power being disconnected and/or any wells being turned off. Maximum amount of time to be off is 4 hours.
C. Remove surplus waste materials, trash, and debris, and legally dispose of them off government property
D. Daily housekeeping is required to ensure that trash and debris are not left at construction site or affect nearby wetlands.
1.6 QUALITY ASSURANCE AND TESTING
A. The contractor will verify water flow and motor amperage. Provide copies of all test results to the onsite Government Inspector and Contracting Officer’s Representation within 2 working days.
1.7 CONTRACT SUBMITTALS
A. Product data for items being installed. Submit to Contracting Officer’s Representative for approval before commencing site work.
B. Field test reports to support compliance with requirements including flow tests of newly rehabilitated pump.
PART 2 – PRODUCTS
NOT USED – product information described above in Part 1 or provided by Contractor
PART 3 – EXECUTION
3.1 COMPLIANCE
Comply with applicable safety codes and standards, and follow approved construction plans to ensure safe and satisfactory project completion.
3.2 FIELD QUALITY CONTROL
A. Contractor shall have an internal quality control system in place to assure compliance with these specifications. Provide copies of and test reports to onsite Government inspector within five working days of testing.