Attach-1-SOW.pdf
PDF 113 KB Posted
- Attached to
- OK-DEEP FORK NWR-GRAVEL-BANK STABILIZATI
- Solicitation number
- 140F0220Q0066
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140F0220Q0066_Amd_0001.pdf | ||
| Attach-3-Map-1_0001.pdf | ||
| Attach-4-Map-2_0001.pdf | ||
| Attach-2-Clauses.pdf | ||
| Sol_140F0220Q0066.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GENERAL INFORMATION AND REQUIREMENTS
PART 1: GENERAL
1.1 PROJECT DESCRIPTION
A. Furnish, deliver and stockpile approximately 3300 tons of standard 18-inch-minimum rip-rap material to be used for bank stabilization along a riverine system. Furnish, deliver and stockpile approximated 1600 tons of 3-inch clean limestone rock in the same approximate location of rip rap placement mentioned above.
Delivery Location: Sequoyah National Wildlife Refuge (NWR) in Vian, Oklahoma, 3 miles south of Interstate 40. The refuge is located approximately 85 miles southeast of Tulsa, OK and 35 miles west of Fort Smith, AR. (See Attached Location Map).
B. Deliver and stockpile material in the area marked on the attached map. Note that the stock pile location(s) are not at headquarters office maintenance area. Locations are up to 12 miles round-trip away from headquarters location.
Area marked as “Stockpile Area (linear)” on map should be stockpiled in a linear fashion along river bank. Area marked “Stockpile Area (point)” should be stockpiled in a consolidated fashion at that location.
C. Delivery POC: Site Visit. Contact Damon Taylor (918) 774-2842. Damon_Taylor@fws.gov
D. Delivery Vehicles. Contractor may elect to use end dump or side dump trailers. Absolutely no turnarounds except in designated areas.
E. Delivery Schedule. To be delivered upon the request from Damon Taylor with a two week notice for delivery with a completion date no later than OCT 30, 2020.
1.2 PRICE.
A. Contractor must provide a price per ton.
B. Costs of all required work including labor, equipment, materials, weighing, testing, transportation, overhead, profit, and contractor owed taxes, are to be included in the prices bid in the schedule for which the work is required.
C. Measurement for Payment: Material shall be weighed on platform scales furnished at the Contractor’s expense or on public scales, provided that weight tickets are prepared by certified weighmasters. Weight tickets shall include, at a minimum, the date, truck number, gross weight, tare weight, net weight, time of weighing, and signature of certified weigh-master. Payment will be made for gravel at the unit price bid per ton in the schedule. Payment will be made for only quantities listed in the schedule.
1.3 CODE COMPLIANCE
Comply with the following listed codes and standards.
OSHA Safety and Health Standards for the Construction Industry (29 CFR Part 1926).
1.4 PERMITS
Contractor is responsible for any other permits needed.
1.5 UTILITIES
Power and water is not available at the site. The Contractor shall make all arrangements to provide power and water if needed for its operations.
1.6 USE OF PREMISES
A. Contractor activities are limited to Refuge hours of work: 7:00 a.m. to 4:00 p.m., Monday through Friday. Work outside these hours or on weekends or Federal holidays is not permitted unless approved in writing by Damon Taylor.
B. Remove surplus waste materials, trash, and debris, and legally dispose of them off Refuge's property.
C. Daily housekeeping is required to ensure trash and debris do not leave site or affect nearby areas.
D. Contractors must stay on designated roads.
E. Contractor must obey all posted speed limits while on the Refuge property.
1.7 SUBMITTALS
A. Product data for base material.
B. Weight tickets for all material.
PART 2 - PRODUCTS
2.1 MATERIAL
A. Provide hard, durable particles or fragments of rip-rap.
B. Crushed concrete or asphalt is not acceptable.
C. Provide weight tickets to the on-site Government representative with each load of gravel delivered for the work. Weight tickets shall include, at a minimum, the date, truck number, gross weight, tare weight, net weight, time of weighing, and signature of certified weighmaster.
PART 3 - EXECUTION
3.1 COMPLIANCE
A. Comply with specified codes and standards to ensure safe and satisfactory project completion.
End.