Attach 1 - Scope of Work.pdf

PDF 107 KB Posted

Attached to
Disaster, Ranch M10 Road Repair Design/Build
Solicitation number
12970224R0047
Issued by

About this file

This document is a Scope of Work for a federal contract opportunity to perform design and construction for the repair of Forest Road M10 in the Mendocino National Forest. The contractor shall perform additional geotechnical investigations before commencing design work to confirm current conditions, which include significant amounts of slide debris on the road. The design phase requirements include submitting preliminary schedules, conducting geotechnical investigations, and submitting design recommendations and the final design for government review. Construction phase requirements include submitting an initial work schedule, maintaining traffic control, and managing site cleanup and material utilization. The contract has a 254-day period of performance and is being solicited by the U.S. Department of Agriculture Forest Service.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Mendocino National Forest Forest Road M10 – Slide Repair

Section C - Scope of Work

Current Conditions

Significant amounts of flow and slide debris remain on the road after emergency removal this past spring. Also, sloughing of the road template fill may have occurred.

The information available to the government relating to the surface and sub-surface geotechnical conditions at and immediately surrounding the site is included as narrative and graphics in Attachment 01.

No other data is known to be available. The presumptions and conclusions, as shown in the Attachment are as stated and no inference should be made beyond that which is specifically contained herein.

Elements of the Work

1. Within 15 days after contract award, the Contractor shall submit for government review both a preliminary Design Phase Schedule and a preliminary Construction Phase Schedule. It is understood that the preliminary schedules are not strictly binding on the contractor. This action is to allow the government to consider its staffing needs for contract administration. See Attachment 03.

2. Design

A. Prior to undertaking the design phase of the project, the Contractor shall submit to the Government an initial design schedule. Updates to this schedule shall be in accordance with the requirements contained in Attachment 03

B. Prior to undertaking the initial design of the project, the Contractor shall perform additional surface and sub-surface geotechnical investigation(s) to the extent deemed necessary to confirm or correct the conclusions contained in Attachment 01. The results of such investigation(s) shall be submitted to the government for review prior to any detailed design work.

C. The Contractor shall submit for review, their recommendations on design and construction strategies and scheduling based on the aggregated geotechnical data.

D. The Contractor shall commence design work in accordance with the requirements of Appendix 1 of the SoW, the approved schedule, and the submittals noted in Section H.

E. The Final Design shall provide for the following:

i. Width of AC pavement shall be no less than 16’ with a minimum 2’ aggregate shoulder on each side. If, during design, the Contractor determines that a 20’ wide roadway is not practical or feasible, they shall consult with the Contracting Officer on the best compromise solution. (See Appendix 1, F-2)

ii. Side slope of the finished road surface shall be no greater than 2% whether out sloped, in sloped, or crowned.

iii. AC pavement shall conform with FP-14, Section 403 or as approved by the Contracting Officer.

3. Construction

A. Prior to commencing construction, the Contractor shall submit for government approval the initial work schedule and the various submittals as required in Section H and as provided for in Appendix 1

B. Prior to commencing construction, all required Traffic Control measures shall be in place.

C. The site shall be cleaned of all slide and slump debris and stockpiled at the location(s) so noted on the Site Map 1. (Attachment 02) D. The Contractor shall undertake the construction work, consistent with the accepted design, in accordance with the submitted schedule and within the approved construction area.

E. The Contractor is solely responsible for determining the order of construction and the incorporating of materials. The Contractor is also required to maintain an adequate workforce and equipment inventory capable of keeping current with the project schedule.

Specific details relating to the Contractor’s work requirements are contained in Appendix 1 of this Scope of Work.

Road M10 – Scope of Work

Appendix 1

Definitions Stage of Completeness

• Preliminary: The first or very early iteration of a document or plan. Applies to early efforts at estimating time, quantities, or costs.

• Initial: The first firm document or plan. Based on the preponderance of known (or reasonably expected) factors. Created with a high degree of reliability. Typically include cost estimates, time schedules, informed presumptions on external conditions, etc.

• Intermediate: Documents, plans, etc. which are modified due to changing conditions or requirements. Typically found in progress schedules, newly discovered/acknowledged conditions, modifications, progress payments, etc.

• Final: The finish. As-Built drawings, Final costs (billings), applied specifications, etc.

Notes to the Elements of Work Design A. The work site is in a relatively remote area in the south-central part of the forest. In the design, consideration should be given to minimizing the amount of imported materials required for the construction. Currently, there is no identified local government source for aggregate and rock.

B. As noted in Attachment 01, there are presumptions presented which identify several current and past elements of movement within, and adjacent to, the project area. The Contractor is expected to employ reasonable and effective means to confirm these presumptions or to identify any changed or inaccurately described conditions. The Contractor may utilize various surface and/or sub-surface measurement techniques and visual surface surveys in determining the current geological conditions likely to affect the work and its results at the project site. Reports and other products produced as a result of these investigations shall be prepared by, or under the direct supervision of a Professional Geotechnical Engineer or Geologist currently licensed in the State of California. (See E below)

C. The Contractor’s submittals, reports, and recommendations shall be prepared by, or under the direct supervision of, a Professional Civil Engineer licensed in the State of California. (See E below)

D. The Contractor shall submit to the Contracting Officer, for government review, the design elements when they reach the following points:

1. 50% Substantially complete.

2. 80% Substantially complete

3. Final complete design.

4. Any subsequent design changes or revisions.

Although the government’s role in approving the design is limited, the government is not obligated to pay for, or proceed with, designs that are incomplete, not constructable, not sustainable, or unduly damaging to the environment. The Contractor shall consider any comments provided during the various stages of the design.

E. All calculations, instructions, designs, and drawings shall be prepared by, or under the direct supervision, of a Professional Civil Engineer licensed in the State of California and be reviewed and approved by the project’s Engineer of Record.

1. The design shall emphasize and prioritize the following:

a. Stability and sustainability over a projected forty-year service life for global stability with a safety factor consistent with industry standards.

b. Utilization of supplies and materials sourced locally. (Northen California)

c. Compatibility, in function and appearance, with the local environment.

2. The design shall identify and incorporate, as required, the following:

a. The mitigation of any surface-water flow and sub-surface flows (springs) likely to affect the repaired and constructed structures. This includes the interception, collection, diversion, and dissipation of any such flows.

b. Travel safety. Depending on the design, this could include object markers, signs, guardrails, etc.

3. The design, and resulting construction(s), shall incorporate the following:

a. All normally exposed components and elements of the construction shall consist of non-flammable materials*. These include steel, non-porous rock, concrete etc. Any flammable materials incorporated into the design/construction shall be adequately protected with non-flammable materials and appropriate separations.

* There is no generally available wood treatment that can withstand the prolonged effects frequently encountered in a wildfire. Most metals other than steel are either unable to withstand the intense heat or are too expensive to be practical. Zinc coated (galvanized) steel may be used in appropriate but limited exposures. Melted zinc poses a contamination hazard in soil and water as well as a post-fire maintenance problem.

Examples: Any wood elements would need to be protected with non-flammable materials like separated steel sheeting. A geo-textile formed MSE structure would include a minimum 16” retained rock façade or functional equivalent.

Products for the Design A. Documents and drawings shall conform to the following formats:

1. All text documents shall be produced in MS Word or compatible software. Submitted text documents not requiring Government input may be in PDF format.

2. Text documents shall be prepared on 8½” X 11” or 11” X 17” size sheets. Avoid use of other sized such as 8½” X 14” (legal). Font shall be no smaller than 11 points except for captions and references which may be 8 points.

3. Drawings may be prepared on ANSI sizes B, C, or D. Drawing elements and text on any drawing shall be legible when reproduced at 11” X 17”. Electronic construction drawings shall be submitted in PDF format. Final and as-build drawings shall be provided in both PDF and original .dwg (or compatible) format. Three complete sets of paper drawings shall be provided to the Government. These include any up-dated or revised drawings as construction proceeds.

4. All drawings, calculations, & text documents pertaining to the road repair and slide/slump mitigation design(s) shall be stamped and signed by a Professional Civil Engineer licensed in the State of California AND the Engineer of Record.

5. Design progress submittals shall be as noted above and in Section J.

For the Contractor’s information, Attachment 04 includes examples of recent constructions at sites on Forest Service Roads with similar conditions.

Construction

A. The Contractor shall create and maintain a “Master” schedule which shall include the initial schedule and any subsequent intermediate changes. Any expected changes to the schedule (intermediate) shall be submitted to the Contracting Officer no later than 3 days prior to such changes becoming effective. Sudden, unexpected substantial changes to the schedule shall be reported to the Contracting Officer within 24 hours of such change. The format for the master schedule shall be compatible with MS Project 2013 or later.

B. Road M10 will be closed to all public traffic during the construction. Any occasion where the Contractor wishes to allow the passage of public traffic during construction shall be approved in advance by the Contracting Officer. Forest Roads 17N12 and 17N63 have been identified as the adjacent detour route for access into the nearby administrative and recreation areas. They also serve as the Contractor’s alternate access. As provided for in Section H, the Contractor is responsible for regular maintenance on those and other roads that may be utilized during construction. Specific requirements of the Traffic Control Plan are identified in Section H.

C. It is expected that some of the rock and soil slide material removed from the road template will be suitable for utilization in the reconstruction. The Contractor shall take reasonable care in separating suitable and unsuitable materials. Slide and slough material shall be considered as borrow material and conform with the requirements of FP-14, sections 204 and 704. Unsuitable material shall be disposed of at locations shown in Attachment 2 or as otherwise indicated by the Contracting Officer. Wood debris, limbs, tops, etc. shall be disposed of in accordance with 203.05 (f & j). Quantities of imported materials shall be calculated and allowed for in the designs.

D. If at any time the Contractor determines that soil disturbing work must occur outside the identified and marked work area, they shall submit a plan and justification to the Contract Officer for approval. If an emergency occurs which requires such work without prior approval, the Contract Officer shall be notified within 24 hours with an initial justification for the need for such activity. Any and all work is subject to all the requirements and limitations of this contract.

E. The Contractor shall install an inclinometer and at least two piezometers to monitor Ground movement and groundwater elevations. Location and depth will be determined by the results of the design phase geo-technical survey and associated recommendations provided by a

Professional Geotechnical Engineer licensed in the State of California. Location(s) shall be established in consultation with the Contracting Officer.

F. The Contractor shall assure that all areas are safely accessible by its employees and government personnel for administrative purposes.

G. All applicable requirements of OSHA, CalOSHA, US Dept. of Labor, Cal LWDA, and FP-14, Section 107 shall be carried out and/or enforced by the Contractor.

Location The project area is located on Forest Road M10 approximatly 3.5 miles west of the Fouts Spring Recreation Area

The area is reached by traveling west from Stonyford, CA about 12 miles on Colusa Co 43A & FR M10, the Fauts Spring Road.

Approximate GPS location on the road at the slide is: 39.339134°, -122.698776°