Att3-SPECS Addendum 556-23-108 Expand Police Dispatch.pdf
PDF 124 KB Posted
- Attached to
- Y1DZ--556-23-108: (CON) Expand Police Dispatch Captain James A. Lovell FHCC, North Chicago, IL 60064-3048
- Solicitation number
- 36C25225B0008
About this file
This is a specification addendum for contract 556-23-108 Expand Police Dispatch at Captain James A. Lovell Federal Health Care Center that modifies three sections of the original specifications. The addendum strikes Section 1.3 "Statement of Bid Item(s)" from Specification 01 00 00, modifies Section 1.1.C of Specification 01 32 16.15 regarding long-lead items and their manufacturing/delivery timing, and updates Section 1.3.B of the same specification to require contractors to submit qualification proposals for Scheduling Consultants within 10 days after Notice to Proceed.
The related opportunity (36C25225B0008) is for renovation of Building 134 C-wing 2nd Floor CLC, requiring complete renovation of approximately 12,590 square feet including demolition, construction, electrical, HVAC, fire protection, and telecom work. The work requires temporary enclosures, dust control measures, and maintaining building systems during construction. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 12 is the contracting agency. Normal work hours are 7:00 AM to 3:30 PM Monday through Friday, with certain work restricted to weekends between 6 PM Saturday and 6 PM Sunday.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
556-23-108 Expand Police Dispatch Specification Addendum
Specification 01 00 00
Section 1.3 “Statement of Bid Item(s)”
- Stricken, not applicable to this contract.
Specification 01 32 16.15
Section 1.1 “Description”, section C. Modified text is in bold.
- Long-lead items (when applicable, see SOW) are materials or systems that have a long manufacturing or delivery time, and therefore need to be ordered well in advance of when they are required for a construction project. These items can include specialized equipment, custom-built machinery, or materials that are in high demand and have long manufacturing lead times.
Section 1.3 “Contractor’s Scheduling Consultant”, section B
- Is to be modified as follows:
o Prior to engaging a Scheduling Consultant, the Contractor shall submit a qualification proposal to the Contracting Officer and COR within 10 days after Notice to Proceed (NTP).