Att. 2 Performance Work Statement.docx

DOCX document 51 KB Posted

Attached to
White Mountain National Forest - FHQ Vis Leak Repair
Solicitation number
12445524Q0096
Issued by

About this file

This document is a Performance Work Statement (PWS) for a contract to repair water intrusion and related damage at the White Mountain National Forest Supervisor's Office. The key objectives are to identify the source of the water intrusion, permanently repair the point of water entry, and repair any resulting wall, insulation, and paint damage. The contractor is required to coordinate with the Contracting Officer's Representative (COR), provide a detailed repair schedule, and present multiple repair options with associated costs. The contractor's key personnel should include a superintendent, crew lead, and laborers. Performance measures include ensuring all water intrusion is stopped, damaged materials are replaced, and schedules and objectives are adhered to. The related federal contract opportunity is solicitation number 12445524Q0096 for the "White Mountain National Forest - FHQ Vis Leak Repair" requirement, issued by the Department of Agriculture Forest Service.

View the file

Other files

File Type Posted
RFQ 12445524Q0096 Signed.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Performance Work Statement

Contents

Project Title3
General Information3
1.0 Background and Purpose3
2.0 Definitions3
Contractor Requirements3
3.0 Technical Requirements / Tasks3
4.0 Deliverable / Schedule3
5.0 Government Furnished4
6.0 Travel4
7.0 Contractor’s Key Personnel4
8.0 Security Requirements4
9.0 Data Rights4
10.0 Section 508 - Electronic and Information Technology Standards4
11.0 Performance Requirement Measures4
Attachment5

Project Title 694237 WMNF VIS Leak Repair

General Information

1.0 Background and Purpose

During heavy rain events, large amounts of water enters the White Mountain National Forest Supervisor Office. The exact point of intrusion is unknown currently. Interior walls have been damaged due to the water entry.

2.0 Definitions

· COR: Contracting Officer’s Representative

· FHQ: Forest Headquarters

· SO: Supervisor’s Office

· WMNF: White Mountain National Forest

Contractor Requirements

3.0 Technical Requirements / Tasks

· Identify the precise location of water intrusion.

· Coordinate with COR to establish acceptable standards of water entry mitigation and repair of damaged entities due to water ingress.

· Permanently repair point of water entry.

· Repair damaged walls, insulation, paint.

· Color match paint to existing, non-affected walls.

· Replace any damaged insulation in affected wall.

· Identify any potential future points of failure and initiate preventative measures to ensure a permanent repair.

· Provide COR with a detailed schedule.

· Provide multiple options and associated costs to repair to COR.

4.0 Contractor’s Key Personnel

Describe positions which are considered key to successful performance of the contract and the information required to support key personnel qualifications, e.g., experience which correlates to SOW requirements, education, and past performance on similar projects. Specify if resumes are required and provide resume format if appropriate.

Insert Contractors Key Personnel Here

· Superintendent / Crew Lead / On site Supervisor

· Laborers

5.0 Performance Requirement Measures

· Below is an example of Performance Requirement Measure and Surveillance:

Performance Objective
Required Task or Deliverable
Performance Standard
Method of Surveillance
Positive/Negative Incentive

% for NOT meeting the Task

All water intrusion is to be stopped and any damaged materials must be replaced in kind and matched to
Schedules and objectives are to be stated clearly to the COR and adhered to.
All work is to be supervised by the contractor superintendent.
A supervisor must be on site at all times while work is being performed. The COR will periodically check in on the work.
Payment deduction will only occur if objectives are not met.