Att. 1 Statement of Work 240201.pdf
PDF 773 KB Posted
- Attached to
- Vertical Platform Lift Replacement - Minnesota Interagency Fire Center (MIFC) Superior National Forest
- Solicitation number
- 12445524Q0020
- Issued by
-
Department of Agriculture Forest Service
About this file
This solicitation is for the removal of two existing vertical platform lifts and replacement with an enclosed single, multistop lift at the Minnesota Interagency Fire Center in Superior National Forest. The selected contractor will demolish the current lifts, design and install the new lift providing ADA compliant access between the main floor, mezzanine training level, and second floor dispatch level. The work includes structural modifications, electrical connections, and obtaining required permits. Quotes are due by March 15, 2024 and the contract completion date is January 31, 2025. The opportunity is set aside for small businesses and subject to Construction Wage Rate Requirements. Interested contractors must be registered in SAM.gov by the quote due date. The solicitation and site visit details can be found on SAM.gov under opportunity number 12445524Q0020 issued by the US Department of Agriculture Forest Service.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Superior National Forest
MIFC Vertical Platform Lift Replacement
Grand Rapids, MN
Project Statement of Work (SOW)
US Department of Agriculture (USDA)
Contents Project General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards
11.0 Payment
Attachment
Project MIFC Vertical Platform Lift Replacement
General Information
1.0 Scope of Work
The intent of this contract is for the removal of the two vertical platform lifts in the Minnesota Interagency Fire Center (MIFC) facility and the replacement with an enclosed single, multi‐stop unit. The contractor will be responsible for the demolition, design, installation, and any required modifications to the building to accept the new lift.
The new platform lift shall provide an ADA compliant route from the main floor of the facility to both the mezzanine (training) level and the 2nd floor (dispatch) level with a single unit. This may require use of a 90 degree exit at one stop, and additional platform(s). The proposed product is a Genesis Model GVL‐EN‐168 by Garaventa Lift or equal. The owner shall have the opportunity to review and comment on all design documents.
Contractor shall be responsible for all modifications to the current building to support the new lift and provide multiple accessible stops including all electrical connections. Modifications to the building shall be completed in accordance with all federal and forest service regulations, the 2021 International Building Code and NFPA 70 NEC 2020 edition.
Contractor shall be responsible for purchasing and obtaining the required elevator permit and coordinating all inspections with the State of Minnesota. The COR shall be notified of any structural changes to the building and given a minimum 14 calendar days for evaluation and approval prior to modifications being made.
The result of this contract shall be a turnkey operational ADA compliant vertical platform lift providing access to all levels of the facility.
2.0 Background
The Minnesota Interagency Fire Center building is located at 402 SE 11th Street, Grand Rapids, MN 55744. The facility currently has two vertical lift platforms. One platform operates from the main floor level to the mezzanine level. The other lift provides access from the mezzanine floor level to the second‐floor level. Reliable operation of the platform lifts is essential to the use of the building as an accessible facility for performing daily work and as a training facility.
Frequent maintenance issues, coordinating general maintenance for two lifts, and difficulty finding replacement parts are the reasons to replace the lift system.
Contractor Requirements
3.0 Technical Requirements / Tasks
Provide for and furnish all labor, superintendence, materials, tools, equipment, transportation, certificates, permits, insurance, temporary protection, and other items designated under provisions of this contract necessary to install a single, multi-stop vertical platform lift in the Minnesota Interagency Fire Center building.
Shop Drawings
1. Show typical details of assembly, erection and anchorage.
2. Include wiring diagrams for power, control, and signal systems.
3. Show complete layout and location of equipment, including required clearances and coordination with shaft way.
Regulatory Requirements
▪ All work shall meet Manufacturer’s Specifications, the NFPA 70, National Electric Code, the 2021 International
Building Codes, and Forest Service Specifications. In the case of conflict use the requirement which is more protective. Copies of manufacturer’s product specifications and installation instructions shall be submitted to the CO prior to the start of work.
Provide platform lift in compliance with:
1. ASME A18.1 ‐ Safety Standard for Platform Lifts and Stairway Chairlifts.
2. ASME A17.1 ‐ Safety Code for Elevators and Escalators.
3. ASME A17.5 ‐ Elevator and Escalator Electrical Equipment.
4. NFPA 70 ‐ National Electric Code.
▪ All work shall be performed in compliance with OSHA Regulations.
Work plan
▪ Work area shall be cleaned up at the end of each workday.
▪ If necessary, the work area shall be barricaded to restrict access or passage.
▪ Dust and debris shall be contained during the demolition and construction, so the operations of the building are not impacted.
▪ Demolition of the vertical platform lift from the main floor to the mezzanine floor level and depending on the contractor’s project design, the demolition of the existing elevated platform.
▪ Demolition of the vertical platform lift from the mezzanine floor level to the 2nd floor level.
▪ After the demolition is complete, contractor shall inspect with the Contracting Officer’s Representative (COR) all existing conditions of the building to ensure there are no structural issues.
▪ The contractor shall construct the necessary structural supports and building reinforcement to accommodate a vertical platform lift.
▪ Install a guardrail at the landing at the top of the stairs on the dispatch level where the lift interfaced with the 2nd floor level.
Install new platform lift providing an ADA compliant route from the main floor of the facility to both the mezzanine (training) floor level and the 2nd (dispatch) floor level with a single unit. This may require use of a 90 degree exit at one stop. The location of the lift may be shifted from the previous location to access both floor levels and a new elevated platform may be required. An access to the 2nd floor level through the masonry block wall will likely need to be cut and framed. The new lift location may obstruct a main level window in the masonry block wall, which is acceptable.
Enclosed Vertical Wheelchair Lift
The lift shall be Genesis Model GVL‐EN‐168 by Garaventa Lift or approved equal.
The nominal clear platform dimensions shall be a minimum 37.25 inches x 60 inches.
The total lifting height is approximately 14 feet. Contractor to verify.
Doors and Gates: Doors and gates shall be self‐closing type.
Door Height: Flush mount, 80 inches.
Gate Height: Flush mount, 42 inches.
Door Construction: Aluminum frame with:
Panels of 16 gauge painted galvanized steel. D‐ Handle Pull: 12‐inch offset D‐Handle.
Power Door/Gate Operator: Automatically opens the door/gate when platform arrives at a landing. Will also open at landing by pressing call button.
ADA Compliant and obstruction sensitive.
Low voltage, 24 VDC with all wiring concealed.
Location:
Lower Landing: Door.
Intermediate Landing: Gate.
Upper landing: Door.
Building doors: Automatic door openers shall be installed on building doors adjacent to vertical lift.
Warranty: Manufacturer shall warrant the wheelchair lift materials and factory workmanship for two years following completion of installation.
Site mobilization may commence on June 24, 2024, or later.
Contract to be completed by: January 31, 2025.
4.0 Government Furnished
The government will review and approve the contractor provided design prior to commencing construction. The government will provide access to the MIFC facility on weekdays from 8:00 a.m. to 3:00 p.m. Access to the building will be through the main entrance and signing in at the receptionist’s desk. The building will be closed on the following holidays.
New Year’s Day Martin Luther King Jr. Day President’s Day Memorial Day Juneteenth Independence Day Labor Day Columbus Day Veteran’s Day Thanksgiving Day Christmas Day
5.0 Deliverables / Schedule
• The intent of the project is to complete the project as quickly as possible so the entire building will have accessibility. The Government understands that material supply issues may delay the progress of the project.
• Contractor shall submit the project schedules and reports outlined in the Key Deliverables Table including a written project schedule within 15 business days of receipt of project award.
• The design information (documentation, drawings, etc.) shall be reviewed and approved by the COR prior to proceeding with fabrication and construction.
• The Government may take up to 14 calendar days from date of receipt to review project submittals.
• Contractor shall notify the Government of the date of substantial completion. At that time the Government shall inspect the work and provide Contractor with a copy of a punch list of items to complete before the project status is considered final completion. The project shall be considered complete once the COR has verified that all items on the punch list have been addressed.
• Tasks and Associated Deliverables: Timely submission of deliverables is essential to successfully completing the project. Schedules for deliverables are specified in Table 1. All deliverables shall be prepared and submitted according to format, content, and schedule described in the SOW. The progress report shall cover all work completed during the specified period and shall present the work to be accomplished during the subsequent period. This report shall also identify any problems that arose and a statement explaining how the problem was resolved. This report shall also identify any problems that have arisen but have not been completely resolved and provide an explanation.
Table 1 Key Deliverables
Item No. Deliverable Objective Due
1 Proposed Project Plan Defining the responsibilities, timeline, project schedule, risks and milestones of contract objectives.
Ref. 3.0
No later than fifteen (15) business days after contract award
2 Revised Project Schedule
Report schedule changes/updates As project is updated until the contract expires
3 Weekly Status Report Report documenting tasks & issues weekly. Weekly, every Friday, by 3:00 PM CST until the contract expires
4 Monthly Status Report Monthly report documenting tasks and issues identified during the month
The 5th day of each month after contract award
6.0 Travel
Travel to the project site shall be included in the mobilization/demobilization costs for the construction project.
7.0 Contractor’s Key Personnel
The Contractor shall assign workers who are experienced in construction methods required to complete the described project. The Contractor’s personnel shall have the necessary certification to install lifts.
8.0 Security Requirements
There are no specific Security Requirements for the project other than access to the work area through signing in at the receptionist’s desk.
9.0 Data Rights
Data produced in the execution of the project (e.g., e‐mails, drawings, etc.) shall be subject to FOIA requirements. The correspondence and drawings produced for the completion of the MIFC Vertical Lift Platform Replacement project are only intended to apply to this project in the MIFC building.
10.0 Section 508 – Electronic and Information Technology Standards Supply of Information technology is not part of this contract, so Section 508 requirements are only required for project communication.
11.0 Payment
The quantities shall be paid for as lump sum quantities or by other methods of measure as listed in the SCHEDULE OF ITEMS. Such payment shall be considered full compensation for constructing the complete project in accordance with the plans and specifications. The invoices shall be submitted to the CO and must be input into the IPP System.
Additional Documents required to be submitted prior to final invoice processing are:
▪ Warranty
▪ Contract Release Form Final payment will not be processed until both the warranty and the contract release form have been received by the
CO.
Attachment
Attachments #1
MIFC Office Existing Vertical Lift Photos
Lift ‐ Main floor to Mezzanine (Training) level Lift ‐ Main floor to Mezzanine (Training) level
Vertical Lift from Mezzanine (Training) level to 2nd floor level
Mezzanine (Training) level to 2nd floor level (Door from lift platform from main floor to mezzanine level on left)
Exiting lift platform at Mezzanine (Training) level