Att B_SOW (230321).pdf

PDF 253 KB Posted

Attached to
Parsons exterior staining project Federal contract opportunity
Solicitation number
12445523Q0048
Issued by
Department of Agriculture Forest Service

View the file

Other files for this federal contract opportunity

Other files attached to Parsons exterior staining project, newest first.
File Type Posted
Q and A.docx DOCX document
12445523Q0048.pdf PDF
Att A_Schedule of Items (230330).docx DOCX document
Att C_Wage Rates (230203).pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Statement of Work

Contents Project General Information

1.0 Scope of Work

2.0 Background

Contractor Requirements

3.0 Technical Requirements / Tasks

4.0 Government Furnished

5.0 Deliverables / Schedule

6.0 Travel

7.0 Contractor’s Key Personnel

8.0 Security Requirements

9.0 Data Rights

10.0 Section 508 – Electronic and Information Technology Standards Attachment

Project Parsons, WV staining project

General Information

1.0 Scope of Work

Furnish all labor, materials, & equipment, to clean, pressure wash, replace any rotted siding and paint (high quality exterior wood stain) all exterior wood siding and trim, at the Parsons, WV Timber & Watershed Main Lab building (# 43401), and the attached computer building (#43408).

2.0 Background

The Parsons Main Lab building is approx. 8000sq. ft. And was constructed in the late 1960s and is a combination of T-1-11 and board and baton wood siding and hasn’t been stained in 10 + years. The siding is in good condition with very little rot. The attached Computer building approx. 1200 sq. ft. and was constructed in 1989 and is a combination of T-1-11 and board and baton and was also stained 10 + years ago. Windows on both facilities are vinyl clad and won’t require paint but will need pressure washed.

Contractor Requirements

3.0 Technical Requirements / Tasks

This project will involve the prepping (pressure wash) and painting of all wooden exterior surfaces, including eaves and overhangs. Stain for all wood surfaces shall be of high quality, exterior wood stain (Sherwin Williams “Woodscapes” or equal) color to be chosen by FS COR. Work will be done during normal business hours (7:00am-5:00pm M-F). This project should be done in a 1- 2-week period.

The contractor will provide all labor, equipment, material, supervision, transportation, clean up and related services to perform the following:

1. Pressure wash and prep all existing wood and metal surfaces.

2. Examine and with COR approval replace any rotted siding.

3. Apply1- 2 coats of high-quality oil-based stain to new siding, and a minimum of 1 coat to existing siding (new and existing must match in color)

4. Clean all work areas and instruct MTP staff on care and maintenance of newly painted surfaces.

Color to be chosen by U. S. Forest Service

4.0 Government Furnished

Contractor may use Government sanitary facilities, electrical, and water utilities during contract period, so long as use is efficient and economical.

5.0 Deliverables / Schedule

A. Product Data: Submit data on finishing products.

B. Manufacturer’s warranty.

C. Care and Maintenance Instructions.

6.0 Travel

NA

7.0 Contractor’s Key Personnel

A. Manufacturer:

Company specializing in manufacturing products specified in this section with minimum three years’ experience.

B. Installer:

Company specializing in performing this work with a minimum three years’ experience.

8.0 Security Requirements

Contractor will sign for and receive a gate key, and a door access card. Project will not be deemed complete until these are returned.

9.0 Data Rights

NA

10.0 Section 508 – Electronic and Information Technology Standards

NA

Attachment

Project
General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards
Attachment

File details come from the government source that posted it. Updated .