This statement of work outlines requirements for a carpet replacement project at Building 68 on Eglin Air Force Base in Florida. The contractor will be required to remove existing carpet, vinyl base, and transition strips covering approximately 143 square yards. New carpet squares, planks, or tiles from one of the tier 1 approved manufacturers will then be installed along with 4-inch vinyl cove base totaling 337 linear feet and matching transition strips where needed. The project must follow all applicable UFC, NFPA, and NEC standards and be completed in a timely manner with minimal disruption. The contracting officer representative is Curtis Keefer of the 96th Civil Engineer Squadron who can be reached at 850-882-5023.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Att 6 Tier 1 contract inquires Point of Contact.pdf | ||
| Att 5 Eglin Bldg 68 Contractor Pricing Form.xlsx | XLSX spreadsheet | |
| Questions and Anwsers bldg 68.pdf | ||
| FA282323Q4014 Rev 2 Combo RFQ.pdf | ||
| FA282323Q4014 Rev 1 Combo RFQ.pdf | ||
| Att 4 Floor Plan.pdf | ||
| FA282323Q4014 Combo RFQ.pdf | ||
| Att 1 Provisions and Clauses.pdf | ||
| Att 3 USAF Carpet II Program Ordering Guide (Jan 23).pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TRIRIGA : 10359198
Project Title: Replace Carpet, Second Floor Hallway, Bldg 68 Date: 04/13/2023
STATEMENT OF WORK
1. PURPOSE OF SECTION: The purpose of this section is to provide the Contractor with a Statement of Work for the above mentioned project. The Contractor shall follow the guidelines and Service Summary provided in the PWS of said contract. The Contractor shall seek clarification from the Contracting Officer (CO) if there is any question on the applicability of a provision. These provisions are for the purpose of general information only and are not intended to completely describe the regulations and restrictions that apply on Eglin AFB.
2. PROJECT SCOPE: The project is located on Eglin AFB, Florida. The Contractor shall be required to furnish all materials, equipment, plant, labor and personnel necessary to design, manage, and accomplish this work in accordance with the contract requirements. The Contractor is expected to maintain safety requirements and demonstrate standard construction methods, at all times.
A. Provide everything necessary to remove sheet carpet & vinyl base, then replace with carpet squares/tiles/planks along with new rubber/vinyl base as indicated on the Task Order. Scope is limited to second floor hallway within building 68 on Eglin AFB.
B. Contractors shall be responsible for the disposal of the old carpet, vinyl cove base, transition strips and any waste generated by the installation of flooring products.
3. PRINCIPAL FEATURES: Principal features of work are as follows:
A. Civil:
a. None.
B. Architectural:
a. Remove existing cove base, scrape and prep to receive new. (~ 337?? LF)
b. Remove existing transition strips, as required.
c. Remove existing roll/sheet carpet. Do not disturb substrate to ensure a smooth and secure bonding surface. (~ 143 SY)
d. Install new carpet squares/planks, 24”x24” or 12” x 36” or approved otherwise.
Tier 1 Approved Carpet Vendor See attached ordering guide on how to order carpet from the mandatory manufacturers (~ 143 SY)
e. Install 4” cove base (color will coordinate with carpet tiles/planks) ~ 337 LF
f. Install matching transition strips where required. ~ 75 LF (6’ metal and 69’ vinyl)
g. All work shall be in accordance with the latest NFPA and NEC requirements to ensure maximum protection against loss of life and property by fire.
h. Design and installation must meet all UFC 3-600-01 and applicable NFPA
Standards.
i. All interior finishes, contents and furnishings must meet NFPA 101 Chapter 10.
C. Mechanical (HVAC):
a. None
D. Electrical
a. All electrical work must be completed IAW NFPA 70 and by a certified electrician.
b. Any fire detection or fire alarm devices that are moved or disconnected for any reason will require reacceptance testing IAW NFPA 72.
c. All work must be in compliance with UFC 3-520-01 Interior Electrical Systems, latest edition.
d. Ensure compliance with the Eglin AFB specific electrical requirements.
E. COMMUNICATIONS: (Customer and 96 CS will verify)
a. All work shall be IAW 96 CS Eglin AFB Cable Installation Specifications, 2 March 2012 (96 CS), or latest release. Provides the technical criteria and information for the installation of base cable infrastructure.
F. SPECIAL INSTRUCTIONS:
a. This project must be completed in a timely matter with minimal impact. Notify CO immediately of any impact regarding long lead items, delays or anything that could affect the negotiated schedule and completion date.
b. Customer will provide escorts if needed.
c. The adjacent areas within this facility will be occupied during construction.
d. Ensure adequate ventilation and coordination prior to work generating fumes, dust, debris and vibration, prior to the activity.
e. Provide warranty, certificates of compliance plus maintenance/cleaning instructions, as applicable the COR prior to the invoice being paid.
COR (Contracting Officer Representative) will be: Curtis Keefer/796CES/CEOES Contracting Officer Representative 850-882-5023