This document is a Construction Safety Accident Prevention Plan for the North Texas VA Health Care Systems. The plan outlines the requirements for the prime contractor to develop and implement a detailed safety plan prior to commencing work on the contract. The plan must be reviewed and approved by government personnel before work can begin. Key elements of the plan include: identifying responsible personnel, subcontractor management, safety orientation and training, inspections, accident reporting, emergency response, and hazard analysis for each phase of work. Specific safety requirements are provided for hazards such as fall protection, fire protection, asbestos, confined spaces, and hot work. The plan also references a related federal contract opportunity for fire alarm and sprinkler system maintenance services at the North Texas VA facilities.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Statement of Work_Fire Alarm Sprinkler System - Draft.docx | DOCX document | |
| Att 1_NARA Records Management Language for Contracts.docx | DOCX document | |
| 36C25725Q0116.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
North Texas VA Health Care Systems
Construction Safety Accident Prevention Plan Prior to commencing work contractors must submit for approval Accident Prevention Plan. The prime contractor will write this plan for the specific work and hazards of the contract and implementing in detail the requirements for safety and occupational health. This plan shall be reviewed and found acceptable by Government personnel prior to initiation of work at the job site. The plan shall be developed by qualified personnel and shall be signed by a competent person AND a representative of management.
The prime contractor shall integrate all subcontractor work activities into the Safety and health Program, make the program available to all contractor and subcontractor employees and ensure all subcontractors integrate the provisions of the plan into their work activities.
The prime contractor shall integrate in their safety plan a requirement that all subcontractor lead personnel attend a onetime facility construction safety orientation;
Date: every 3rd Thursday
Time: 9:00 am
Location: 4500 Lancaster, Dallas, Texas 75216 (Engineering Building 9) NOTE: Please provide an anticipated attendance list prior to attendance
The safety plan shall include:
· Title, signature and phone number of the plan preparer
· Title, signature and phone number of the plan approver
· Background information on the project:
· Contractor, contract number, project name, description of work to be performed and location of work to be performed, contractor accident experience such as OSHA 200 forms, corporate safety trend analysis, and a listing of phases of work and hazardous activities requiring hazard analysis.
Statement of safety & health policy
· Administrative responsibilities for implementing the plan
· Identification and accountability of personnel responsible for accident prevention
· Means for controlling work activities of subcontractors and suppliers
· Responsibilities of subcontractors
· Plans for safety orientation of new employees / sub contractors
· Plans for continued safety training
· Provisions for safety inspections to include
· Work site/material and equipment inspection
· Means for recording inspection results
· Timetable for correction of deficiencies
· Procedures for follow-up inspections to ensure correction
· Responsibilities for investigation and reporting accidents/exposure
· All accidents incident to the project will be investigated & reported within 24 hours
· Accidents that result in a fatality, three or more persons admitted to a hospital or significant property damage will be reported immediately to the Contracting Officer. Contractors are responsible for notifying OSHA.
· First aid treatments shall be reported and recorded daily.
· Responsibilities for maintaining accident data, reports and logs
· Emergency response capabilities for disasters
· Emergency Plans will include emergency phone numbers and shall be tested periodically. Plans shall include escape procedures, employee accounting following an emergency evacuation, rescue and medical duties, means of reporting emergencies and persons to be contacted.
· Plans for maintaining job cleanup and safe access
· Public safety requirements (fencing/signs)
· Prevention of alcohol/drug abuse on the job
NOTE: Items that are commonly omitted in safety plans:
· Plans for hazard communication program must include:
1. A list of hazardous chemicals known to be present
2. Methods used to inform employees of the hazards
3. Containers must be present and labeled
4. MSDS for each hazardous chemical on site
Plans must identify monthly supervisor safety meeting and weekly worker safety meetings. Meetings shall be documented including the date, attendance, subjects, and the name of individuals who conducted the meeting.
· Fire protection plan: Establish and maintain a fire protection program in accordance with 29 CFR 1926. Prior to start of work; prepare a plan detailing project-specific fire safety measures. As part of the Fire Safety Plan the contractor shall include the following applicable standards NFPA 101, NFPA 1, NFPA 241. These standards describe requirements when the Fire protection Systems are impaired. Any open piping/conduit and/or penetrations extending through walls or floors from the construction area into a non-construction compartment will need to be capped off and fire stopped. All hot work will require a permit a facility Safety Officer will inspect the area before such work is performed.
NOTE: When fire protection systems are disrupted, contractors shall ensure procedures are incorporated to maintain equivalent levels of fire protection and provide formal notification to the facility. Procedures shall be approved by facility CSO (construction safety officer) or project COR (contracting officer representative) prior to implementation.
Safety requirements for the hazards identified on the job site such as listed but not limited to the following:
· Fall protection
· Alternate measures for impaired fire protection systems (sprinkler, fire alarm, etc)
· Asbestos exposure
· Confined space entry
· Lock out/tag out
· Excavations
· Electrical safety
· Machinery and mechanized equipment
· Hand and power tools
· Contingency plan for severe weather
· Hot work (welding, torch cutting, brazing etc)
· Flammable storage NOTE: Plan must indicate that no hot work shall be performed without required burn permit issued by safety)
Hazard Analysis
Prior to beginning EACH PHASE OF WORK, an activity hazard analysis shall be prepared by the contractor performing that work. Work shall not proceed until the hazard analysis has been accepted by facility Construction Safety Coordinator.
The analysis will:
· Define the activity being performed
· Identify the sequence of work to be accomplished
· Identify the specific hazards that are anticipated
· Identify the control measures that shall be implemented to reduce each hazard to an acceptable level
Hazard analysis shall identify the principal steps to be accomplished in sequence to accomplish the operations. Equipment used in the operation shall be listed on the hazard analysis form. Inspection requirements for the equipment and machinery shall be listed on the hazard analysis form. Each step shall be analyzed to identify its potential hazards and a recommended control shall be identified to reduce the hazard to an acceptable level.
Hazard Analysis Work Phase:
Activity
Analyzed by/Date
Reviewed by/Date
Principal
Potential
Recommended
Steps
Hazards
Controls
Identify the
Identify the potential hazards
List specific control measures sequence of work activities
Equipment
Inspection
Training / certification requirements to be used
Requirements
List equipment/machinery
List inspection
List trained /certified operators .
used in conducting the work requirement for activities equipment/machinery listed