This is a Design-Build Statement of Work for the renovation and conversion of Building 230 at Columbus Air Force Base in Mississippi, Project Number EEPZ252131, dated 22 January 2026. The project involves converting the facility into a consolidated Flying Training Squadron (FTS) facility for the 49th and 50th FTS after the T-1 Jayhawk divestment in Spring 2026.

The scope encompasses comprehensive interior renovation work including demolition and installation of new flooring (LVT plank, carpet, and epoxy finishes), suspended ceiling systems, interior partition walls with multiple new briefing rooms and offices, plumbing upgrades (sinks, showers, water closets, and washer connections), electrical system upgrades with new LED lighting and receptacles, HVAC modifications including standalone split systems for specific rooms, communication infrastructure upgrades, and fire alarm system enhancements. The contractor must also provide new drinking fountains, perform test and balance of the entire HVAC system, install controls upgrades converting from N2 to Bacnet protocol, replace chilled water and heating water piping, furnish new room numbering plaques, and prepare spaces for future equipment locker installation. The total period of performance is 365 days from Notice to Proceed. The contract requires submission of design documents at 35%, 65%, 95%, and 100% completion stages, with detailed architectural, structural, mechanical, electrical, and plumbing drawings prepared electronically in AutoCAD and PDF formats. The contractor must demonstrate qualified personnel including a Project Manager with minimum five years' experience managing multi-discipline commercial construction, a Site Superintendent with five years' project management experience, and a Quality Control Manager with five years' QC management experience. Standard warranty is one year from project acceptance, with extended warranties for specific products and systems. The contractor is responsible for all temporary utilities, site security, environmental compliance, hazardous material management, and final cleaning and closeout procedures including preparation of operation and maintenance manuals and spare parts delivery.

View the file

Other files

File Type Posted
Sources Sought Questionnaire.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DESIGN-BUILD STATEMENT OF WORK

PROJECT NUMBER: EEPZ252131

RENOVATE/CONVERT 50th 49th SQ OPS, B230

COLUMBUS AFB, MISSISSIPPI

22 JANUARY 2026

COLUMBUS AFB, MS PROJECT NUMBER: EEPZ252131

TABLE OF CONTENTS

NOMENCLATURE

1.1 ACRONYMS & ABBREVIATIONS

1.2 BASIC TERMS

DESCRIPTION OF PROJECT

2.1 SUMMARY

2.2 BACKGROUND

2.3 SCOPE OF PROJECT

2.4 GOVERNMENT FURNISHED EQUIPMENT/MATERIALS

2.5 SALVAGE

DESIGN REQUIREMENTS

3.1 SUMMARY

3.2 NATURE/EXTENT OF DESIGN

3.3 RESPONSIBILITY

3.4 DESIGN STANDARDS

3.5 DRAWINGS

3.6 DESIGN SUBMITTALS

3.7 DESIGN REVIEWS

3.8 CONFERENCES

ADMINISTRATION OF CONSTRUCTION

4.1 PERFORMANCE CAPABILITIES

4.2 COMMENCEMENT, PROSECUTION & COMPLETION

4.3 SCHEDULING

4.4 MANAGING

4.5 MATERIAL SUBMITTALS AND SHOP DRAWINGS

4.6 WORK BY GOVERNMENT

4.7 PRE-FINAL AND FINAL INSPECTION

4.8 WARRANTY

4.9 CONTRACTOR OFFICE

4.10 CONSTRUCTION SITES

4.11 CONSTRUCTION EQUIPMENT

4.12 AVAILABILITY OF UTILITY SERVICES AT JOB SITES

4.13 TEMPORARY UTILITIES

4.14 CONSTRUCTION SECURITY

QUALITY REQUIREMENTS

5.1 QUALITY CONTROL PLAN

5.2 TESTING AND INSPECTION SERVICES

5.3 MANUFACTURERS' FIELD SERVICES

5.4 PRODUCT REQUIREMENTS

5.5 CLOSEOUT PROCEDURES

SAFETY, HEALTH AND ENVIRONMENTAL PROTECTION

6.1 SAFETY AND HEALTH

6.2 GENERAL

6.3 HAZARDOUS MATERIAL

6.4 PROJECT EXECUTION

6.5 HAZARDOUS WASTE GENERATION/DISPOSAL

6.6 RECYCLING

6.7 PROHIBITED MATERIAL/ACTIONS

6.8 SPILLS AND CLEANUP

6.9 AIR CONSIDERATIONS

6.10 AFFIRMATIVE/GREEN PROCUREMENT/BIO-BASED/ENERGY

6.11 ASBESTOS/LEAD BASED PAINT

6.12 DRINKING WATER

6.13 EMS

6.14 HISTORICAL AND CULTURAL ARTIFACTS

6.15 NATURAL RESOURCES

6.16 NOISE

6.17 PESTICIDES/FERTILIZERS

6.18 STORM WATER PROTECTION

6.19 REQUEST FOR CE SERVICE/ACTION/CLEARANCE; AF FORMS 332/813

6.20 TANKS

6.21 LIMITS AND EXCEPTIONS

6.22 LEGAL AUTHORITY

NOMENCLATURE

1.1 ACRONYMS & ABBREVIATIONS

AF Air Force AFI Air Force Instruction AFM Air Force Manual AFUE Annual Fuel Utilization Efficiency AHU Air Handling Unit ATFP Anti-terrorism/Force Protection BCE Base Civil Engineer CAD Computer Assisted (or Aided) Design CAFB Columbus Air Force Base CDs Construction Documents CEPM Civil Engineering Project Manager CES Civil Engineering Squadron cfm cubic feet per minute CFR Code of Federal Regulations CHW Chilled Water CMI 14CES Construction Manager Inspector CO Contracting Officer COR Contracting Officer Representative Comm Communications CPM Contractor’s Project Manager CSS Contractor’s Site Superintendent DP Design Professional EMCS Energy Management & Control System EMI Electromagnetic Interference EPA Environmental Protection Agency ETL Engineering Technical Letter FAR Federal Acquisition Regulation FCU Fan Coil Unit FM Factory Mutual

FOD Foreign Object Debris fps feet per second

ft. foot or feet GFCI Government Furnished Contractor Installed gpm gallons per minute Hazmat Hazardous Materials HMW Hazardous Material or Waste HTW Hazardous and Toxic Waste HVAC Heating, Ventilating and Air Conditioning NEC National Electrical Code NTP Notice to Proceed O&M Operation and Maintenance OSP Originally Specified Product PDF Portable Document Format PE Professional Engineer Ph Phase (electrical) PM Project Manager psi pounds per square inch QCP Quality Control Plan RFP Request for Proposal SOW Statement of Work TI Technical Instruction TL Technical Letter TM Technical Manual UFC Unified Facilities Criteria UPS Uninterruptible Power Supply VAV Variable Air Volume V Volts W Watts

1.2 BASIC TERMS

The following table provides many of the meanings of words or phrases commonly used in this document.

All directives, informative, etc. statements are directed to the Contractor even if the term “contractor” or the contractor name is not included (e.g. “Provide a nail.” is equivalent to “The contractor shall provide a nail.” And “remove” is equivalent to “The Contractor shall remove”). Also, the Contractor shall ably and competently execute all directives including all directly or indirectly related tasks required to safely and legally perform the directive (e.g. “remove debris from CAFB” includes “safe and legal removal, disposal and obtaining all necessary permits, etc.)

A device, equipment or system referred to in the singular (e.g. “the pump”, or “the ___ system”) includes all related devices, elements and components required to Provide (see below in this table) that device, equipment, or system.

The Term Shall Mean (*=Shall in Addition Mean) Approved (by CAFB) *without waiving or suspending the full force of Contractor obligation to fulfill the CDs Aspect Distinct feature or element of the project CAFB Government contracting Authority on Columbus Air Force Base

Construction Documents

Drawings, specifications and their references including all Design Criteria and Design & Construction Requirements for this Project.

Contractor The Design-Build entity holding a current Government contract including all personnel in direct or indirect employ of same entity servicing same contract including partners, consultants, subcontractors, suppliers, and manufacturers.

Design Professional (Abbreviated: DP) Professionals including Architects, Engineers and Landscape Architects licensed to practice in one or more states of the U.S.

Day Calendar day unless noted otherwise.

DP Licensed Design Professional fully responsible for all professional design on this project.

Engineer DP For example (e.g.) One among many possible examples Government Columbus Air Force Base Contracting Officer Including [Includes] Including, but not limited to [Includes, but is not limited to] Provide Furnish and install complete, functional, and ready for use without added government action Provision Furnishing & installation complete, functional, and ready for use without added government action Will, must, shall & similar Terms are mandatory directives whereby ‘Term’ = ‘Term + to CAFB satisfaction’ Work The whole or any part, product, system or subsystem of this project Replace Demolish and dispose of existing element. Provide new element of equal or greater value.

Review Review and, if and when acceptable to the government, approval Subcontractor Subcontractor and all personnel in Subcontractor’s direct or indirect employ on any given

Project including suppliers and manufacturers

DESCRIPTION OF PROJECT

2.1 SUMMARY

The Contractor must provide all plant, labor, equipment, transportation, and tools required to complete the renovation of B230 to be converted into a consolidated Flying Training Squadron (FTS) facility. Work includes replacing interior finishes, upgrading electrical fixtures, demolishing and erecting interior partition walls and doors, mechanical and plumbing work, among others. Perform all work according to this Statement of Work (SOW), the Concept Design Drawings, and all related AF requirements and other codes and references.

2.2 BACKGROUND

Columbus AFB is one of three Specialized Undergraduate Pilot Training (SUPT) bases and one of three bases to perform Introduction to Fighter Fundamentals (IFF) for prospective fighter pilots. B230 is currently utilized for classroom and briefing space by the 48th FTS. B230 will soon be utilized by the 49th & 50th FTS, after divestment of the T-1 Jayhawk in Spring 2026, in preparation for the upcoming T-7A Red Hawk mission. The consolidation of TFS into B230 is essential to the flying training mission supporting 16,000+ sorties per year as part of Columbus AFB SUPT and IFF syllabus.

2.3 SCOPE OF PROJECT

2.3.1 Demolish existing flooring and cove base, including all adhesive. Repair floor and wall surfaces as required to prepare for installation of new flooring and cove base. Applies to the following spaces:

• Classroom 1, Classroom 2, Classroom 3, Room 5, Room 11, Room 17 + Corridor, Room 25, Room 29, Room 36, Room 37, Rooms 40/41, Room 43, Rooms 156/157/158/159, Fitness Room + 2 Adjacent Rooms, Step Desk.

2.3.2 Furnish and install new 20 mil, 5mm thick, LVT plank flooring and associated installation materials.

Furnish and install new transition strips at locations with differing floor types. LVT style and color shall match Shaw Contract’s Inlet Shade 26506 or approved equal. Confirm style and color match with the Base Architect.

Applies to the following spaces:

• Room 5, Room 11, Room 17 + Corridor, Room 25, Room 29, Room 36, Room 37 (Mother Room Portion), Room 43, Rooms 156/157/158/159, Step Desk.

2.3.3 Furnish and install new carpet flooring and associated installation materials. Furnish and install new transition strips at locations with differing floor types. Carpet style and color shall match Shaw Contract’s Collective V Tile Charcoal 38500 or approved equal. Confirm style and color match with the Base Architect.

Applies to the following spaces:

• Classroom 1, Classroom 2, Classroom 3, Fitness Room + 2 Adjacent Rooms.

2.3.4 Furnish and install new concrete solid stain, non-slip epoxy, and associated installation materials. Furnish and install new transition strips at locations with differing floor types. Concrete solid stain color shall match the color of Shaw Contract’s Inlet Shade 26506 or approved equal. Epoxy shall be low shine and clear, having no color. Confirm styles and colors with the Base Architect. Applies to the following spaces:

• Rooms 40/41.

2.3.5 Furnish and install new 4” vinyl wall base. Confirm style and color match with the Base Architect.

• Vinyl wall base style and color shall match Johnsonite’s 20 Charcoal WG or approved equal. Applies to the following spaces:

o Room 5, Room 11, Room 17 + Corridor, Room 25, Room 29, Room 36, Room 37 (Mother Room

Portion), Room 43, Rooms 156/157/158/159, Step Desk.

• Vinyl wall base style and color shall match Johnsonite’s 40 Black B or approved equal. Applies to the following spaces:

o Classroom 1, Classroom 2, Classroom 3, Fitness Room + 2 Adjacent Rooms.

2.3.6 Demolish the existing suspended ceiling grid system and tiles. Applies to the following spaces:

• Classroom 1, Classroom 2, Classroom 3, Room 5, Room 11, Room 17 + Corridor, Room 25, Room 29,

2.3.7 Furnish and install new tegular 2’-0” x 2’-0” suspended ceiling grid system and ceiling tiles. The new suspended ceiling shall maintain existing ceiling height. Grid system and tiles shall match and be white. Color to be approved by the Base Architect. Tiles are not to be vinyl coated. Applies to the following spaces:

• 5/8” acoustical ceiling tiles required: Classroom 1, Classroom 2, Classroom 3, Room 5, Room 11, Room 17

+ Corridor, Room 25, Room 29, Room 36, Room 37 (Mother Room Portion), Rooms 40/41, Room 43, Rooms 156/157/158/159, Fitness Room + 2 Adjacent Rooms, Step Desk.

• 5/8” moisture resistant ceiling tiles required: Room 37 (Men’s Room Extension).

2.3.8 Furnish and install all materials necessary to repair the existing interior walls. Areas requiring repair include, but are not limited to, water and moisture damage, holes, peels/cracks/chips, among others. Repair walls with materials that match existing. All repairs shall have an uninterrupted, flat wall surface transition with existing. Applies to the following spaces:

• Classroom 1, Classroom 2, Classroom 3, Room 5, Room 11, Room 17 + Corridor, Room 25, Room 29,

2.3.9 Paint new and existing interior walls. Paint color(s) shall be Sherwin Williams’ Accessible Beige or approved equal. Color should conform to base standards and be approved by the Base Architect. Interior walls will be painted to match the color selected by the Base Architect. At a minimum, painting should include one (1) coat of primer, two (2) coats of paint, sanding and prepping of all surfaces, and placing drop cloths on the floor.

Applies to the following spaces:

• Classroom 1, Classroom 2, Classroom 3, Room 5, Room 11, Room 17 + Corridor, Room 25, Room 29, Room 36, Room 37 (Mothers Room Portion), Rooms 40/41, Room 43, Rooms 156/157/158/159, Fitness Room + 2 Adjacent Rooms, Step Desk.

2.3.10 Repair or replace disturbed building components impacted by construction actions of this project, match existing.

2.3.11 Any repaired or replaced wall surfaces shall achieve level 4 finish.

2.3.12 All door hardware must be Best 7-pin core compatible.

2.3.13 Classroom 1 Specific Architectural Work:

• Demolish the existing interior partition wall protruding into the classroom from the south end. Repair the adjacent walls and floor with materials that match existing.

2.3.14 Classroom 2 Specific Architectural Work:

• Demolish the interior door, doorframe, and associated hardware of the briefing room.

• Demolish the existing interior partition walls separating Classroom 2 and the briefing room. Repair the adjacent walls and floor with materials that match existing.

• Furnish and install all materials required to construct the new interior partition walls for the new briefing room. The new briefing room shall be located at the opposite end of Classroom 2 to match Classrooms 1 and 3, see concept drawing for location. Materials include, but are not limited to, metal framing, insulation, 5/8” drywall, wall surface preparation materials, and paint, to achieve a level 4 finish. Design, furnish, and erect the new interior partition walls in accordance with NFPA 101.

• Furnish and install one (1) new 3’x7’ opaque solid core wood interior door that meets current ASHRAE standards, interior knock-down doorframes, associated door hardware including hinges, handles, and locksets (coordinate with Base Locksmith for requirements), kickplates, and any other necessary components for the new briefing room. Locks and hinges should be mortise. The new briefing room door shall be located to match Classrooms 1 and 3 doors, see concept drawing for location. Materials shall match with others throughout the unit for uniformity. Materials shall be prefinished by the manufacturer, including color, and be approved by the Base Architect.

2.3.15 Room 5 Specific Architectural Work:

• Demolish the interior door, doorframe, and associated hardware of the storage room.

• Demolish the existing interior partition wall separating the storage room and student lounge. Repair the adjacent walls and floor with materials that match existing.

2.3.16 Room 11 Specific Architectural Work:

• Demolish all interior doors, doorframes, and associated hardware. Repair the walls and floor as necessary to prepare for one (1) cased opening and infill of three (3) existing doors. See concept drawing for locations.

Materials used for repairs shall match existing.

• Furnish and install all materials required for the 3’x7’ cased opening in the existing door opening. Repaired wall surfaces shall achieve level 4 finish.

• Furnish and install all materials required to infill the three (3) existing door openings to match existing wall assemblies. Repaired wall surfaces shall achieve level 4 finish.

• Demolish an area centered on the wall between existing Room #11 and Lobby to prepare for one (1) 4’x7’ cased opening. See concept drawing for location. Consult with a licensed structural engineer prior to demolition. Repair the walls and floor as necessary. Materials used for repairs shall match existing. Repaired wall surfaces shall achieve level 4 finish. Furnish and install all materials required for the cased opening.

• Furnish and install all materials required to construct the new interior partition walls for ten (10) two-ship briefing rooms, one (1) storage closet, and new corridor. Materials include, but are not limited to, metal framing, insulation, 5/8” drywall, wall surface preparation materials, and paint, to achieve a level 4 finish.

The new corridor shall maintain 4’ width throughout, be centered on the cased openings, and comply with egress requirements. Design, furnish, and erect the new interior partition walls in accordance with NFPA 101.

• Furnish and install all new 3’x7’ opaque solid core wood interior doors that meet current ASHRAE standards, interior knock-down doorframes, associated door hardware including hinges, handles, and locksets (coordinate with Base Locksmith for requirements), kickplates, and any other necessary components for the two-ship briefing rooms and storage closet. Provide louvered panels at the bottoms of the 10 briefing rooms doors for a return air path. Locks and hinges should be mortise. Materials shall match with others throughout the unit for uniformity. Materials shall be prefinished by the manufacturer, including

2.3.17 Room 17 Specific Architectural Work:

• Demolish the interior door, doorframe, and associated hardware of Room 17.

• Demolish the existing interior partition walls on Room 17. Repair the adjacent walls and floor with materials that match existing.

• Furnish and install all materials required to construct the new interior partition walls for three (3) offices.

Materials include, but are not limited to, metal framing, insulation, 5/8” drywall, wall surface preparation materials, and paint, to achieve a level 4 finish. The new corridor outside these offices shall maintain 8’ width throughout and comply with egress requirements. Design, furnish, and erect the new interior partition walls in accordance with NFPA 101.

• Furnish and install all one (1) new 3’x7’ opaque solid core wood interior door for each office that meet current ASHRAE standards, interior knock-down doorframes, associated door hardware including hinges, handles, and locksets (coordinate with Base Locksmith for requirements), kickplates, and any other necessary components. Locks and hinges should be mortise. Materials shall match with others throughout the unit for uniformity. Materials shall be prefinished by the manufacturer, including color, and be approved by the Base Architect.

2.3.18 Room 25 Specific Architectural Work:

• Demolish the interior door, doorframe, and associated hardware. Repair the wall and floor as necessary to prepare for infill of the existing door. See concept drawing for locations. Materials used for repairs shall match existing.

• Furnish and install all materials required to infill the existing door opening to match existing wall assemblies. Repaired wall surfaces shall achieve level 4 finish.

• Demolish two (2) areas on the wall between existing Room 25 and corridor to prepare for two (2) 3’x7’ doors and doorframes. See concept drawing for locations. Consult with a licensed structural engineer prior to demolition. Repair the walls and floor as necessary. Materials used for repairs shall match existing. Repaired wall surfaces shall achieve level 4 finish.

• Furnish and install two (2) new 3’x7’ opaque solid core wood doors that meet current ASHRAE standards, interior knock-down doorframes, associated door hardware including hinges, handles, and locksets (coordinate with Base Locksmith for requirements), kickplates, and any other necessary components for existing Room 25. Locks and hinges should be mortise. Materials shall match with others throughout the unit for uniformity. Materials shall be prefinished by the manufacturer, including color, and be approved by the Base Architect.

• Furnish and install all materials required to construct the new interior partition walls for two (2) two-ship briefing rooms. Materials include, but are not limited to, metal framing, insulation, 5/8” drywall, wall surface preparation materials, and paint, to achieve a level 4 finish. The briefing rooms shall be of equal size. Design, furnish, and erect the new interior partition walls in accordance with NFPA 101.

2.3.19 Room 36 Specific Architectural Work:

• Demolish existing sink. Cap hot and cold-water lines to prepare for installation of one (1) new sink.

• Demolish existing base cabinets and shelving, countertops, wall mounted counters, and associated components.

• Furnish and install one (1) new stainless-steel undermount double compartment sink 10” deep with a stainless-steel manual, two handle faucet. Reuse existing plumbing components including rough-ins, stubs, hot and cold-water lines, among others to the maximum extent possible. Furnish and install all new plumbing components as required to supply the room with a complete and functional plumbing system.

Repair or replace disturbed wall and floor surfaces as result of construction actions from this project, match to existing. Repaired wall surfaces shall achieve level 4 finish.

• Furnish and install one (1) new recessed washer box with cold- and hot-water lines, shut-off valves for each water line, waste lines, and associated components required for fixture connection hookups. Reuse existing plumbing components rough-ins, stubs, hot and cold-water lines, among others to the maximum extent possible. Furnish and install all new plumbing components as required to supply the room with a complete and functional plumbing system. Repair or replace disturbed building components impacted by construction actions of this project, match to existing. Repaired wall surfaces shall achieve level 4 finish.

• Furnish and install one (1) dryer vent ducted to the outside with wall or ceiling cap and associated components. Furnish and install all new components as required to supply the room with a complete and functional dryer vent system. Repair or replace disturbed building components impacted by construction actions of this project, match to existing. Repaired wall surfaces shall achieve level 4 finish.

• Design, furnish and install all materials necessary to construct a new raised wood L-shape counter and linear counter, see concept drawing for locations. This includes, but is not limited to, 36” high x 24” deep base cabinets, doors, adjustable shelves, drawers, solid surface countertops with 4” backsplash, knobs, handles, soft-closing mechanisms, hardware, fasteners, and anything else required for complete and functional Life Support counters. The L-shape counter shall be designed with three (3) workstations. The counters and associated materials shall be prefinished by the manufacturer, including color. The counters shall be stained to match Sherwin-Williams’ Walnut MW439 or approved equal, with semi-gloss finish. The countertops shall be Bellavati’s Coppermill DFS1-404 or approved equal. Styles and colors shall be approved by the Base Architect.

• Design, furnish and install all materials necessary to construct wall cabinets mounted above the L-shape counter and linear counter, see concept drawing for locations. This includes, but is not limited to, 36” high x 12” deep wall cabinets, doors, adjustable shelves, knobs, handles, soft-closing mechanisms, concealed hinges, hardware, fasteners, and anything else required for complete and functional Life Support cabinets.

The cabinets and associated materials shall be prefinished by the manufacturer, including color. The cabinets shall be stained to match Sherwin-Williams’ Walnut MW439 or approved equal, with semi-gloss finish.

Styles and colors shall be approved by the Base Architect.

• Demolish existing wainscotting, wall panels, wall mounted shelves, and associated components. Repair walls with materials that match existing. All repairs shall have an uninterrupted, flat wall surface transition with existing.

2.3.20 Room 37 (Mothers Room Portion) Specific Architectural Work:

• Furnish and install all materials required to construct the new interior partition wall that separates the bathroom extension and Mother’s Room. See concept drawing for location. Materials include, but are not limited to, metal framing, insulation, 5/8” gypsum wallboard, 5/8” cementitious backerboard where wall tile is specified, wall surface preparation materials, and paint, to achieve a level 4 finish. Design, furnish, and erect the new interior partition walls in accordance with NFPA 101.

2.3.21 Room 43 Specific Architectural Work:

• Demolish all interior doors, doorframes, and associated hardware. Repair the walls and floor as necessary to prepare for one (1) cased opening and infill of two (2) existing doors. See concept drawing for locations.

Materials used for repairs shall match existing.

• Furnish and install all materials required for the 3’x7’ cased opening in the existing door opening. Repaired wall surfaces shall achieve level 4 finish.

• Furnish and install all materials required to infill the two (2) existing door openings to match existing wall assemblies. Repaired wall surfaces shall achieve level 4 finish.

• Furnish and install all materials required to construct the new interior partition walls for two (2) four-ship briefing rooms, two (2) flex-ship briefing rooms capable of seating eight occupants, one (1) storage closet, and new corridor. Materials include, but are not limited to, metal framing, insulation, 5/8” drywall, wall surface preparation materials, and paint, to achieve a level 4 finish. The new corridor shall maintain 4’ width throughout, be centered on the cased opening, and comply with egress requirements. Design, furnish, and erect the new interior partition walls in accordance with NFPA 101.

• Furnish and install all new 3’x7’ opaque solid core wood interior doors that meet current ASHRAE standards, interior knock-down doorframes, associated door hardware including hinges, handles, and locksets (coordinate with Base Locksmith for requirements), kickplates, and any other necessary components for the two-ship briefing rooms and storage closet. Provide louvered panels at the bottoms of the briefing room doors for a return air path. Locks and hinges should be mortise. Materials shall match with others throughout the unit for uniformity. Materials shall be prefinished by the manufacturer, including

2.3.22 Rooms 156/157/158/159 Specific Architectural Work:

• Demolish the interior double door, doorframe and associated hardware of Room 156. Repair the walls and floor as necessary to prepare for one (1) 6’x7’ double door and doorframe to be installed. See concept drawing for locations. Materials used for repairs shall match existing. Repaired wall surfaces shall achieve level 4 finish.

• Furnish and install all new 6’x7’ opaque solid core wood interior double door that meet current ASHRAE standards, interior knock-down doorframes, associated door hardware including hinges, handles, and locksets (coordinate with Base Locksmith for requirements), kickplates, and any other necessary components for existing Room 156. Locks and hinges should be mortise. Materials shall match with others throughout the unit for uniformity. Materials shall be prefinished by the manufacturer, including color, and be approved by the Base Architect.

• Demolish all the interior doors, doorframes, and associated hardware of Rooms 157 and 158. Repair the walls and floor as necessary to prepare for the infill of the existing doors. See concept drawing for locations.

Materials used for repairs shall match existing.

• Furnish and install all materials required to infill the existing door openings of Rooms 157 and 158 to match existing wall assemblies. Repaired wall surfaces shall achieve level 4 finish.

• Demolish the interior door, doorframe and associated hardware of Room #159. Demolish an area on the wall next to the door to prepare for one (1) 6’x7’ double door and doorframe to be installed. See concept drawing for location. Consult with a licensed structural engineer prior to demolition. Materials used for repairs shall match existing. Repaired wall surfaces shall achieve level 4 finish.

• Furnish and install all new 6’x7’ opaque solid core wood interior double door that meet current ASHRAE standards, interior knock-down doorframes, associated door hardware including hinges, handles, and locksets (coordinate with Base Locksmith for requirements), kickplates, and any other necessary components for existing Room 159. Locks and hinges should be mortise. Materials shall match with others throughout the unit for uniformity. Materials shall be prefinished by the manufacturer, including color, and be approved by the Base Architect.

• Demolish the existing interior partition walls to create the Equipment Locker Room. Repair the adjacent walls and floor with materials that match existing. Consult with a licensed structural engineer prior to demolition.

2.3.23 Fitness Room + 2 Adjacent Rooms Specific Architectural Work:

• Demolish the interior door, doorframe, and associated hardware of the center room. Repair the walls and floor as necessary to prepare for infill of the existing door. See concept drawing for locations Materials used for repairs shall match existing. Repaired wall surfaces shall achieve level 4 finish.

• Demolish the existing interior partition walls to create Classroom 4. Repair the adjacent walls and floor with materials that match existing. Consult with a licensed structural engineer prior to demolition.

2.3.24 Step Desk Specific Architectural Work:

• Demolish existing base cabinets, countertops, wall mounted counters, and associated components.

• Demolish existing raised floor and all associated components.

• Design, furnish and install all materials necessary to construct a new raised wood L-shape desk in the Step

Desk area, see concept drawing for location. This includes, but is not limited to, 34” high x 24” deep base cabinets, doors, adjustable shelves, drawers, solid surface countertops, knobs, handles, soft-closing mechanisms, concealed hinges, hardware, fasteners, and anything else required for a complete and functional step desk. The step desk shall be designed with four (4) workstations, have a standing height countertop no shorter than 4’ AFF run the entire length of the desk, and a section that complies with current ABA standards. The sides of the step desk that face the corridor shall be flat surface with no visible joints.

The corridor around the step desk shall maintain 8’ width throughout and comply with egress requirements.

The step desk and associated materials shall be prefinished by the manufacturer, including color. The step desk shall be stained to match Sherwin-Williams’ Walnut MW439, or approved equal, with semi-gloss finish. The countertops shall be Bellavati’s Coppermill DFS1-404, or approved equal. Styles and colors shall be approved by the Base Architect.

• Design, furnish and install all materials necessary to construct a new raised wood wall mounted counter in the Step Desk area, see concept drawing for location. This includes, but is not limited to, 18” high x 24” deep wall mounted counters, doors, adjustable shelves, solid surface countertop, knobs, handles, soft-closing mechanisms, concealed hinges, hardware, fasteners, and anything else required for a complete and functional counter. The counter shall be designed with four (4) workstations and have a standing height countertop no shorter than 4’ AFF. The counter and associated materials shall be prefinished by the manufacturer, including color. The counter shall be stained to match Sherwin-Williams’ Walnut MW439, or approved equal, with semi-gloss finish. The countertops shall be Bellavati’s Coppermill DFS1-404, or approved equal. Styles and colors shall be approved by the Base Architect.

• Demolish the interior door, doorframe, and associated hardware between existing corridor to Room #17 and the step desk.

• Demolish the existing interior partition wall separating existing Room #17 and the step desk. Consult with a licensed structural engineer prior to demolition. Repair the adjacent walls and floor with materials that match existing.

2.3.25 Men’s Restroom North Specific Architectural/Plumbing Work:

• Remove all components of the existing bathroom accessories and mirrors. Protect and store all components during demolition. Reinstall all components.

• Keep the existing floor drain, waste piping, and associated components in place.

• Demolish the existing lavatory, water closet, and urinals. All existing carriers shall be removed.

• Remove all water lines back to their main and cap. Remove all waste piping back to their main and cap.

Repair or replace disturbed building components impacted by construction actions of this project, match to existing. Repaired wall surfaces shall achieve level 4 finish.

• Demolish the existing stall partitions in their entirety.

• Demolish the existing porcelain wall tile and cementitious backerboard.

• Demolish the existing porcelain floor tile to prepare for new flooring. Prepare the floors as required, including removing existing glue adhesive, for installation of new porcelain floor tile.

• Demolish the existing lavatory wet wall to prepare for future lockers. Repair or replace disturbed building components impacted by construction actions of this project, match to existing. Repaired wall surfaces shall achieve level 4 finish.

• Furnish and install one (1) new shower with associated plumbing fixtures and components. Shower shall be of a white one-piece 36” square shower stall with shower kit including controls and fittings, as well as a centered drain. Shower shall have two (2) corner shelves, at a minimum. Shower head shall be ultralow flow (1.5 GPM). Contractor shall ensure the shower base is slip-resistant and has adequate slope to direct water towards the drain. Furnish and install all new piping and associated components necessary to connect the shower to existing hot- and cold-water and waste lines. Water lines shall be PP-RCT, manufacturer to be Aquatherm or approved equal. Water lines shall connect to new thermostatic mixing (anti-scald) valves.

Furnish and install wall shut off valves for the shower’s water lines.

• Furnish and install new stainless steel grab bars in the shower stall. Components shall be installed using best practices for location placement without hindering user mobility.

• Furnish and install one (1) new floor-mounted flush valve water closet with associated plumbing fixtures and components. Water closet shall be Zurn brand or approved equal. Flush handle shall be silver in color.

Furnish and install all new carriers and associated components. Furnish and install all new piping and associated components necessary to connect the water closets to existing water and waste lines. Water lines shall be PP-RCT, manufacturer to be Aquatherm or approved equal. Furnish and install wall shut off valves for the water closet’s water lines.

• Furnish and install a new wall-mounted open industrial bathroom vanity with one (1) white drop-in lavatory and associated plumbing fixtures and components. Vanity shall be Corian Quartz’s Antique Pearl or approved equal solid surface countertop with 4” integrated backsplash. Vanity shall be prefinished by the manufacturer, including color. Lavatory shall be KOHLER brand or approved equal. Faucet shall be Delta brand or approved equal, have two (2) handles for hot- and cold-water operation, and be silver in color. Furnish and install all new piping and associated components necessary to connect the lavatories to existing water and waste lines. Furnish and install wall shut-off valves for each lavatory’s water lines.

• Furnish and install all materials required to construct the new interior partition wall between the shower stall and water closet. Materials include, but are not limited to, metal framing, insulation, 5/8” cementitious backerboard, wall surface preparation materials, and paint, to achieve a level 4 finish. Design, furnish, and erect the new interior partition wall in accordance with NFPA 101.

• Furnish and install new 12” x 12” porcelain floor tile and associated installation materials. Furnish and install new transition strips at locations with differing floor types. The tile shall match Daltile’s Volume 1.0 Thunder VL62 or approved equal. Confirm color and dimensions match with the Base Architect. Grout color shall match Bostik Delorean Gray H160 or approved equal. Furnish and install new Schluter DILEX- EHK cove-shaped profile or approved equal for inside wall corners and floor/wall transitions. Transitions shall be brushed stainless steel, confirm color with the Base Architect

• Furnish and install new 5/8” cementitious backerboard where wall tile is specified, furnish mounting/fastening hardware for installation. Furnish all materials necessary to prepare the cementitious backerboard as required for installation of new wall tiles.

• Furnish and install from the floor to 6’ high new 12” x 12” porcelain wall tile and associated installation materials. The tile shall match Daltile’s Volume 1.0 Degrees Silver VL71 or approved equal. Confirm color and dimensions match with the Base Architect. Grout color shall match Bostik Delorean Gray H160 or approved equal. Furnish and install new Schluter DILEX-EHK cove-shaped profile or approved equal for inside wall corners and floor/wall transitions. Transitions shall be brushed stainless steel, confirm color with the Base Architect.

• Furnish and install new 5/8” GWB where cementitious backerboard is not, furnish mounting/fastening hardware for installation.

• Furnish all materials necessary to prepare the gypsum wall boards to achieve a level 4 finish. Ensure the newly surfaced walls are installed to have an uninterrupted, flat wall surface.

• Furnish and install all materials necessary for painting. Paint all walls, except where new wall tile is to be installed, to match color to Sherwin-Williams’ Accessible Beige SW7036 or approved equal. Confirm color with the Base Architect. At a minimum, painting should include one (1) coat of primer, two (2) coats of paint with satin/egg-shell finish, sanding and prepping of all surfaces, and placing drop cloths on the floor.

• Furnish and install new shower and stall partitions, associated hardware, and mounting components. These stalls do not need to achieve ABA compliance. Color of the stall partitions shall be prefinished by the manufacturer and approved by the Base Architect.

• Any damage to the new floor and wall tiles caused by the Contractor while mounting stall partitions and bathroom and plumbing fixtures and accessories will be fixed or replaced by the Contractor, at the Contractor’s expense.

2.3.26 Room 37 (Men’s Restroom Extension) Specific Architectural/Plumbing Work:

• Remove the recessed paper towel dispenser and surface mounted waste receptacles from the men’s restroom. Reinstall the components on wall located between the bathroom door and lavatory. Repair or replace disturbed building components impacted by construction actions of this project, match to existing.

Repaired wall surfaces shall achieve level 4 finish.

• Demolish an area centered on the wall between existing Room 37 and Men’s Restroom to prepare for one

(1) 4’x7’ cased opening. See concept drawing for location. Consult with a licensed structural engineer prior to demolition. Repair the walls and floor as necessary. Materials used for repairs shall match existing.

Repaired wall surfaces shall achieve level 4 finish.

• Furnish and install all materials required for the 3’x7’ cased opening in the existing door opening.

• Furnish and install all materials required to construct the new interior partition walls for the wet wall. See concept drawing for location. Materials include, but are not limited to, metal framing, insulation, 5/8” cementitious backerboard where wall tile is specified, wall surface preparation materials, and paint, to achieve a level 4 finish. Design, furnish, and erect the new interior partition walls in accordance with

NFPA 101.

• Furnish and install one (1) new floor drain, waste piping, and associated components in the bathroom extension. Repair or replace disturbed building components impacted by construction actions of this project, match to existing.

• Furnish and install two (2) new showers with associated plumbing fixtures and components. Showers shall be of a white one-piece 36” square shower stall with shower kit including controls and fittings, as well as a centered drain. Showers shall have two (2) corner shelves each, at a minimum. Shower heads shall be ultralow flow (1.5 GPM). Contractor shall ensure the shower bases are slip-resistant and has adequate slope to direct water towards the drain. Furnish and install all new piping and associated components necessary to connect the showers to existing hot- and cold-water and waste lines. Water lines shall be PP-RCT, manufacturer to be Aquatherm or approved equal. Water lines shall connect to new thermostatic mixing (anti-scald) valves. Furnish and install wall shut off valves for the showers’ water lines.

• Furnish and install new stainless steel grab bars in the shower stalls. Components shall be installed using best practices for location placement without hindering user mobility.

• Furnish and install two (2) new floor-mounted water closets with associated plumbing fixtures and components. Water closets shall be Zurn brand or approved equal. Flush handles shall be silver in color.

Furnish and install all new carriers and associated components. Furnish and install all new piping and associated components necessary to connect the water closets to existing water and waste lines. Water lines shall be PP-RCT, manufacturer to be Aquatherm or approved equal. Furnish and install wall shut off valves for the water closets’ water lines.

• Furnish and install new 6” ceramic base and 12” x 12” non-slip ceramic floor tile and associated installation materials in the bathroom extension. Furnish and install new transition strips at locations with differing floor types. The base and tile’s style, installation pattern, and color shall match existing. Grout color shall match existing. Confirm styles and colors with the Base Architect.

• Furnish and install new “6” x 6” ceramic wall tile, 4’ wainscotting, and associated installation materials in the bathroom extension. The wall tile and wainscotting shall match existing. Confirm color and dimensions match with the Base Architect. Grout color shall match existing. Confirm styles and colors with the Base Architect.

• Furnish and install new shower and stall partitions, associated hardware, and mounting components. These stalls do not need to achieve ABA compliance. Color of the stall partitions shall be prefinished by the manufacturer and approved by the Base Architect.

• Furnish and install one (1) new toilet tissue dispenser in each stall. Components shall be installed using best practices for location placement.

• Any damage to the new floor and wall tiles caused by the Contractor while mounting stall partitions and bathroom and plumbing fixtures and accessories will be fixed or replaced by the Contractor, at the

2.3.27 Demolish existing light fixtures and fixture whips back to the nearest junction box. Furnish and install new 2’x2’ flat panel LED light fixtures with new fixture whips. Provide all new material including, but not limited to, conduit, conductors, junction boxes, white light switches, and white dimmers to supply the new room layout with lighting. Recess mount the light fixtures in the new suspended ceiling system. Light fixtures shall comply with ASHRAE 90.1 power and lighting standards and with base, local, and national emergency lighting codes. Light fixtures shall have necessary seismic support. Place new light fixtures in locations necessary for optimal lighting qualities for essential daily functions and occupant comfort. Light fixtures shall be placed in locations that ensure minimal disruptions (i.e. relocating, demolishing, performance, etc.) to new and existing HVAC, fire detection and alarms, and electrical systems. Design, furnish, and install new white ceiling occupancy sensors or wall switch sensors and accompanying power pack relays. Components shall be compatible and connect with the new lighting circuits and light switches of each room. Furnish and install emergency exit signs and egress lighting in accordance with NFPA 101. Extend emergency exit signs and egress lighting to include the project’s construction areas. Design and approval to be completed by Electrical P.E.

Contractor shall test and modify the system as required. Applies to the following spaces:

• Classroom 1, Classroom 2, Classroom 3, Room 5, Room 11, Room 17 + Corridor, Room 25, Room 29,

2.3.28 Demolish existing lighting fixtures within both North and South Mechanical Rooms. Install new overhead LED lighting fixtures.

2.3.29 Demolish existing power outlets and receptacles at locations impacted by construction actions of this project. Test before demolition to ensure power is disconnected. Keep existing conductors. Cap, pull, coil, and tie existing conductors up overhead (above suspended ceiling system) for future use. Keep existing junction boxes, conduit, and runways in place, unless locations conflict with construction actions of this project.

2.3.30 Reuse existing electrical components to the maximum extent possible. Extend the system as required for the new room layout. Furnish all new components required for extension. New components shall be placed in locations that ensure minimal disruptions (e.g. relocating, demolishing, performance, etc.) to new and existing communication and electrical systems. Furnish and install new receptacles and outlets in existing locations.

Modified rooms shall receive duplex receptacles spaced appropriately. Components shall match and be white.

Components shall be compatible and reconnect with existing conductors. Contractor shall test and modify the system as required. Applies to the following spaces:

• Classroom 1, Classroom 2, Classroom 3, Room 5, Room 11, Room 17 + Corridor, Room 25, Room 29, Room 36, Room 37, Rooms 40/41, Room 43, Rooms 156/157/158/159, Fitness Room + 2 Adjacent Rooms, Step Desk.

• Room 36 – In addition to the requirements of 2.3.30, install counter height duplex GFCI power outlets and receptacles appropriately spaced along the new counters. The room shall receive one (1) fully functional dedicated 240V 30A dryer circuit with GFCI protection, and one (1) GFCI washer receptacle. The dedicated dryer circuit shall use a 4-prong NEMA Type 14-30 receptacle. See concept drawings for locations.

2.3.31 Demolish existing communication locations impacted by construction actions of this project. Test before demolition to ensure power is disconnected. Keep existing conductors. Cap, pull, coil, and tie existing conductors up overhead (above suspended ceiling system) for future use. Keep existing junction boxes, conduit, and runways in place, unless locations conflict with construction actions of this project.

2.3.32 Reuse existing communication components to the maximum extent possible. Extend the system as required for the new room layouts. Furnish all new components, except for conductors, required for extension.

Base Communications shall install new conductors. New components shall be placed in locations that ensure minimal disruptions (e.g. relocating, demolishing, performance, etc.) to new and existing communication and electrical systems. Demolish and remove existing communication faceplates and jack. Furnish and install new faceplates and jacks in existing locations. Components shall match and be white. Components shall be compatible and reconnect with existing conductors. Contractor shall test and modify the system as required.

Applies to the following rooms:

• Classroom 1, Classroom 2, Classroom 3, Room 5, Room 11, Room 17 + Corridor, Room 25, Room 29, Room 36, Room 37, Rooms 40/41, Room 43, Rooms 156/157/158/159, Fitness Room + 2 Adjacent Rooms, Step Desk.

• Classroom 2 Specific - The new briefing room shall receive one (1) duplex telephone jack and two (2) duplex LAN jacks, at a minimum. Contractor shall ensure that the new interior partition wall that faces towards Classroom 02 will receive one (1) duplex telephone jack and one (1) duplex LAN jack, at a minimum.

• Room 5 Specific - The room shall receive two (2) duplex telephone jacks and three (3) duplex LAN jacks, at a minimum.

• Room 11 Specific - Each two-ship briefing room shall receive one (1) duplex telephone jack and two (2) duplex LAN jacks, at a minimum. Components shall match and be white.

• Room 17 Specific- Each office shall receive two (2) duplex telephone jack and two (2) duplex LAN jacks, at a minimum.

• Room 25 Specific - Each briefing room shall receive one (1) duplex telephone jack and two (2) duplex LAN jacks, at a minimum.

• Room 36 Specific - The room shall receive three (3) counter height duplex telephone jacks and three (3) counter height duplex LAN jacks, at a minimum, spaced along the new counters. See concept drawing for locations.

• Room 43 Specific - Each briefing room shall receive one (1) duplex telephone jack and two (2) duplex LAN jacks, at a minimum.

• Fitness room + 2 Adjoining Rooms Specific - The room shall receive four (4) duplex telephone jacks and eight (8) duplex LAN jacks, at a minimum.

• Step Desk Specific - The step desk shall receive two (2) duplex telephone jacks and two (2) duplex LAN jacks, at a minimum. The wall mounted counter shall receive two (2) duplex LAN jacks, at a minimum.

2.3.33 Relocate existing detectors, strobes and alarms, and mass notifications that obstruct locations of the new interior partition walls, suspended ceiling system, and electrical and HVAC components. Extend items to include the new room layout. Furnish and install items in accordance with NFPA 101 and Air Force Occupational Safety and Health Standards 91-118, reusing existing components to the maximum extent possible and reprogram fire control panels accordingly (if applicable). If these items are required in additional areas and/or existing items cannot be relocated to extend in these additional areas, furnish and install new detectors, strobes and alarms, and mass notifications to match those existing within the project’s construction area. If this occurs, furnish and install conduit, wiring, associated components, and anything else required. Primary and secondary power for the smoke detectors must be provided from the fire alarm control panel. The facility’s fire alarm system must always remain operational throughout this project.

2.3.34 Contractor shall coordinate communication work with the Government and Base Communication Officer (BCO) to achieve designs necessary for future implementation of a complete and functional communication system in the unit. Work shall follow UFC 3-580-01 Telecommunications Interior Infrastructure Planning and Design, and any other necessary telecommunication requirements determined by federal, state, and local regulations.

2.3.35 If any existing…