SCOPE OF WORK SUMMARY: Superior National Forest – Tofte District Garage and Cabin Gutters
This is a Scope of Work (SOW) document dated 2026 for seamless rain gutter installation services at the Tofte Ranger District Office within the Superior National Forest in Tofte, Minnesota. The contractor shall provide all labor, materials, equipment, supervision, and supplies necessary to install new gutters on five district buildings to disperse roof runoff away from building foundations. The project performance period is 90 days after contract award, with work conducted Monday-Friday between 8:00 a.m. and 4:30 p.m., excluding federal holidays. The location is the Tofte Ranger District Office at 7355 W MN-61, Tofte, MN 55615, which is accessible via paved or gravel driveways and parking lots maintained clear of snow during winter months.
The work scope includes installing new seamless oxford brown-colored aluminum gutters on five buildings: District Office (30 linear feet), Bunkhouse #1 (68 linear feet), Bunkhouse #2 (93 linear feet), Ranger Dwelling (96 linear feet), and Fire Garage (147 linear feet), totaling 434 linear feet. Gutter specifications require 5-inch aluminum seamless gutters with 0.032-inch thickness, supports installed at maximum 24-inch on-center spacing, a minimum slope of 1 inch in 40 feet to downspouts, end caps sealed watertight, and 3-inch by 4-inch downspouts with extensions minimizing water at least 10 feet from buildings. Splash shields are required on valleys for three buildings. The contractor must provide certified payroll and a Contract Release Form prior to final invoice processing. Payment shall be rendered as a lump sum for Task T1 (complete gutter installation), with invoices submitted through the IPP System. A site visit is highly recommended and can be arranged through James Anderson at the contact information provided.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Q and A_12445526Q0068.xlsx | XLSX spreadsheet | |
| Q and A_12445526Q0068.xlsx | XLSX spreadsheet | |
| Q and A_12445526Q0068.xlsx | XLSX spreadsheet | |
| Att 01_Schedule of Items_260515.docx | DOCX document | |
| Att 03_Wage Rates_260102.pdf | ||
| Sol_12445526Q0068.pdf | ||
| HOW TO FOLLOW PROJECTS ON SAM FOR EMAIL ALERTS.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Superior National Forest – Tofte-Garage and Cabin Gutters
Superior National Forest Tofte District Garage and Cabin
Gutters Scope of Work (SOW)
Dated: 2026
Background The Tofte Ranger District within the Superior National Forests has a need for new seamless rain gutter installations at 5 buildings at its district office. The purpose of this contract is to install new gutters to disperse roof runoff away from the building foundations.
Photo of Tofte Fire Garage
GENERAL REQUIREMENTS
1.0 Description of Services:
The contractor shall provide all management, supervision, labor, personnel, transportation, materials, equipment, and supplies, except as otherwise specified, necessary to provide services at the Tofte District Office located in Tofte, MN. All work shall be performed in accordance with this statement of work and all federal, state, and local laws and regulations.
2.0 Location and Description:
The project is located within the Superior National Forest at the Tofte District Office in Tofte, MN. The Tofte District Office is located at the following addresses:
Tofte Ranger District
7355 W MN-61
Tofte, MN 55615
2.1 Accessibility:
The sites are accessible by paved or gravel driveways and parking lots. The driveway and parking lots are routinely cleared of snow during the winter months.
3.0 Performance Period:
This project is expected to be completed 90 days after the award of the contract.
4.0 Prework Conference:
Prior to commencement of work, the Contracting Officer (CO) or the Contracting Officer Representative (COR) will schedule a meeting with the contractor to discuss the contract terms, work requirements and schedule. At the conference, the Contractor shall designate, in writing, the name and phone number of the Contractor’s on-site representative and their contract responsibilities and authority.
5.0 Contractor Representative:
Provide an onsite contract representative who will oversee the performance of the work specified in this contract. Designate in writing to the CO, the name of the contract representative and an alternate(s) who shall have the authority to authority to act for the Contractor on all contract matters relating to daily operation of this contract. Notify the CO/COR at least 10 work days in advance of any subsequent change of personnel in this position. Replacement personnel shall have the same level or better experience as the person being replaced.
6.0 Government-Furnished Items:
Not applicable- Contractor shall be responsible for all materials, supplies and services.
7.0 Hours of Operation:
The contractor may work Monday-Friday between the hours of 8 a.m. and 4:30 p.m.
8.0 Federal Holidays:
No work shall be performed on a Federal holiday.
9.0 Bio-Based Cleaning Products:
Not applicable
10.0 Qualifications Of Contractor Or Employees:
The Contractor and his/her employees shall be capable and experienced in the type of work mentioned below in section 14.0 Tasks. The on-site supervisor shall have experience and demonstrated ability in the tasks mentioned in section 14.0 Tasks. The Contractor shall provide a list of employees authorized to work under this contract.
11.0 Safety and General Requirements:
11.1 Safety
The Contractor shall comply with all Federal and State safety requirements for the type of work to be performed. Refer to the Occupation Safety and Health Standards (OSHA) for details of these and other safety requirements.
11.2 General
The Contractor shall take all precautions necessary to minimize and restore all construction impacts. All existing work and conditions impacted or modified by the contractor shall be replaced with like kind at the contractor’s expense.
11.2.1 Damages
All cutting, patching and repairs on systems shall be coordinated with COR at the weekly construction meeting in advance of the work. The Contractor is responsible to fix, and repair affected areas on un-approved work to the original condition or better.
11.2.2 Housekeeping
Keep project neat, orderly, and in a safe condition at all times. At the end of the work week a more thorough cleanup and policing shall be performed. All debris shall be removed and properly disposed.
11.2.3 Smoking
Smoking inside Forest Service buildings is prohibited, cigarette butts shall not be discarded on the ground.
12.0 Work Items:
SPECIAL NOTE: MANY OF THESE BUILDINGS ARE CONSIDERED HISTORIC
STRUCTURES. THE COLOR OF THE GUTTERS MUST MATCH THE COLOR OF THE
BUILDINGS AS CLOSELY AS POSSIBLE.
Tofte District:
Work shall consist of installing new seamless oxford brown-colored gutters on 5 district buildings. All downspouts shall be supplied and fitted with extensions to extend water at least 10ft from the building.
District Office: 30 L.F. with downspout
Bunkhouse #1: 68 L.F with downspouts, splash shields on valleys Bunkhouse #2: 93 L.F with downspouts, splash shields on valleys
Ranger Dwelling: 96 L.F with downspouts Fire Garage: 147 L.F. with downspouts, splash shields on valleys
Seamless gutters are to be installed with all endcaps, supports, downspouts, and all associated hardware.
Gutter Specifications:
• 5” aluminum seamless gutters 0.032 thickness
• Gutter supports shall be installed at no more than 24” on center
• Slope gutters evenly to downspouts with slope no less than 1” in 40’
• Provide end caps at gutter ends and seal watertight per manufacturer's instructions
• Install and seal watertight outlet tubes at all downspout locations
Downspout Specifications:
• Downspouts to be 3”x4”
• Install downspouts, provide elbows and offsets, and secure downspouts to wall construction using downspout supports that are spaced per manufacturer's requirements. Maximum distance of downspout supports from top, or bottom of downspout shall be 2 feet.
13.0 Submittals
• Product Data: Submit manufacturer's current technical literature for each type of product being used.
• Select color chart for selection by CO or COR.
14.0 Tasks:
Costs associated with preparation, materials, clean-up, and disposal shall be included in the following tasks.
T1: Install new seamless gutters and accessories on 5 Tofte District buildings.
14.0 Payment and Site Visit
Payment:
The quantities shall be paid for as lump sum quantities or by other methods of measure as listed in the SCHEDULE OF ITEMS. Such payment shall be considered full compensation for constructing the complete project in accordance with the plans and specifications. Invoices must be inputted into the IPP System.
Additional Documents required to be prior to final invoice processing are:
Certified Payroll
Contract Release Form
Final payment will not be processed until both documents have been received by the CO.
Site Visit:
A site visit is highly recommended and can be arranged by contacting:
James Anderson 1393 Highway 169 Ely, MN 55731 Office:218-365-2044 Cell: 218-504-9506 James.b.anderson@usda.gov mailto:James.b.anderson@usda.gov
Photos
Tofte Bunkhouse #1 Front Tofte Bunkhouse #1 Back
Tofte Bunkhouse #2 Front Tofte Bunkhouse #2 Back
Tofte Ranger Dwelling Front Tofte Ranger Dwelling Back
Tofte Fire Garage Front Tofte Fire Garage Back
| Superior National Forest |
| Tofte District Garage and Cabin Gutters |
| Scope of Work (SOW) |
| Background |
| GENERAL REQUIREMENTS |
| 3.0 Performance Period: |
| 6.0 Government-Furnished Items: |
| 11.0 Safety and General Requirements: |
| 11.1 Safety |
| The Contractor shall comply with all Federal and State safety requirements for the type of work to be performed. Refer to the Occupation Safety and Health Standards (OSHA) for details of these and other safety requirements. |
| 11.2 General |
| The Contractor shall take all precautions necessary to minimize and restore all construction impacts. All existing work and conditions impacted or modified by the contractor shall be replaced with like kind at the contractor’s expense. |
| 11.2.1 Damages |
| All cutting, patching and repairs on systems shall be coordinated with COR at the weekly construction meeting in advance of the work. The Contractor is responsible to fix, and repair affected areas on un-approved work to the original condition or bet... |
| 11.2.2 Housekeeping |
| Keep project neat, orderly, and in a safe condition at all times. At the end of the work week a more thorough cleanup and policing shall be performed. All debris shall be removed and properly disposed. |
| 11.2.3 Smoking |
| Smoking inside Forest Service buildings is prohibited, cigarette butts shall not be discarded on the ground. |
| 12.0 Work Items: |
| SPECIAL NOTE: mANY OF THESE BUILDINGS ARE CONSIDERED HISTORIC STRUCTURES. THE COLOR OF THE GUTTERS MUST MATCH THE COLOR OF THE BUILDINGS AS CLOSELY AS POSSIBLE. |
| Costs associated with preparation, materials, clean-up, and disposal shall be included in the following tasks. |
| T1: Install new seamless gutters and accessories on 5 Tofte District buildings. |