This is a Statement of Work and Specifications for the supply and delivery of one Securall B2400XFR2 8'3" H x 14' W x 8' D Chemical Storage Building (or equal) to the ATON Buoy Yard at U.S. Coast Guard Base New Orleans, 1790 Saturn Blvd, New Orleans, LA 70129. No installation labor is required from the vendor. The chemical storage building must include specific components: a 60" W x 80" H double door with 36" active leaf, 393-gallon sump capacity, explosion relief panels, Intertek-tested 2-hour fire-rated walls and 1.5-hour fire-rated roof, an OP-100A load center with 12-space panel and 100A main breaker (NEMA 3R, 120/240V), two LED explosion-proof light fixtures with Class 1 Division 2 rating, two explosion-proof 15A, 120V receptacles (Class 1 Division 1 & 2), an explosion-proof exhaust system (335 CFM with indicator light and audible alarm), and 30 linear feet of 14" W shelves with 2" lip sides arranged in three tiers along left and right walls.

The contractor must submit all required information within 14 calendar days of contract award, with the Coast Guard providing 7 calendar days for review. A firm delivery date must be provided within 14 calendar days after award. Work shall commence within 14 calendar days of approval and be completed within 30 calendar days. Deliveries must occur between 8:00 AM and 4:00 PM, Monday through Friday (excluding federal holidays), to minimize interference with facility operations. The contractor bears full responsibility for work site safety, environmental compliance (including RCRA requirements for hazardous waste), storm drain protection, and material storage per manufacturer specifications. Materials must be delivered in original, unopened packages clearly marked with manufacturer information. All chemicals require pre-approval with Safety Data Sheets, and a one-year warranty is required for all materials at no additional cost to the Coast Guard.

View the file

Other files

File Type Posted
Commercial Supplies Services Clauses Provisions FAC 2023-01.doc DOC document
SF18 REQUEST FOR QUOTES.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Work & Specifications

Supply ATON HAZMAT Storage Building

Located at U.S. Coast Guard Base New Orleans 1790 Saturn Blvd New Orleans, La.

Aug 2025

Commanding Officer United States Coast Guard Base New Orleans, LA Facilities Engineering Department New Orleans, LA 70129

Carlton Ackiss Assistant Facilities Engineering Officer Base New Orleans, LA

PART 1: GENERAL

1. INTENT: The Coast Guard requires the supply and delivery of one (1) 8’3” H x 14’ W x 8’ D Chemical Storage Building, with associated components, to ATON Buoy Yard at Base New Orleans. No labor will be required from the vendor.

2. SCOPE OF WORK: Contractor shall furnish and deliver one (1) Securall B2400XFR2 8’3” H x 14’ W x 8’ D Chemical Storage Building or equal, and associated components. No alterations outside of the Statement of Work criteria are authorized without permission from the Contracting Officer (KO) or Contracting Officers Representative (COR)

3. CONTINUITY OF FACILITIES OPERATION: Schedule deliveries to minimize interference with the facility’s normal operations. Perform all deliveries between the hours of 8:00 AM and 4:00 PM, Monday through Friday (federal holidays excluded), unless otherwise approved by the Contracting Officer or Contracting officer’s representative.

4. GOVERNMENT FURNISHED MATERIALS: None

5. GOVERNMENT FACILITIES AND UTILITIES: None

6. SAFETY: The Contractor is wholly responsible for work site safety. The Contractor shall implement a safety program that protects the lives and health of personnel in the construction area, prevents damage to property, and avoids work interruptions. To accomplish this end, the Contractor shall provide appropriate safety barricades, signs, signal lights, etc. as well as complying with and abiding by all federal safety regulations as published by the Occupational Health and Safety Administration, 29 CFR 1910 (series), 29 CFR 1926 (series), State and Local safety laws, rules and regulations. Any operation defined as “Hot Work” as per OSHA/NFPA requires a permit to be issued. In the event of Hot Work, the Contractor will notify the COR with dates and times Hot Work will be performed. Contractor is to give at least 48 hours notification. This includes welding, cutting, brazing, grinding or any work that could produce sparks or heat and may initiate a fire.

7. ENVIRONMENTAL COMPLIANCE: Any waste generated because of the project shall either be recycled or be disposed of IAW the Resource Conservation and Recovery Act (RCRA). Any Hazardous Waste shall be manifested off site with Base New Orleans listed as the Generator and signatory. Any hazardous waste shall be analyzed, characterized, stored and disposed of IAW RCRA and all applicable federal, state (i.e. DOT) and local laws and ordinances. All solid waste/trash shall be removed from site and not disposed of in onsite dumpsters. Waste and recycling areas are reserved for RCF Tenants and shall not be used by Contractors at any time. All work will be performed IAW the BASE New Orleans Spill Prevention Control and Countermeasures Plan. All chemicals required for this project shall be preapproved by the contract POC along with SDS’s. All solid waste shall be removed from the RCF after each working day. All extra chemicals and products shall be removed from the site upon work completion, as the Emergency Planning and Community Right-To-Know Act requires Coast Guard maintains an inventory of all Hazardous Materials located at the site. A laydown area as required and an Erosion and Sediment Control Plan, shall be preapproved by the COR as needed. Nothing shall be discharged to a storm drain at any time during the project. All storm drains within range of a potential discharge shall be covered/sealed during installation and kept covered until the work has been completed and the system has been deemed fully operational and compliant with all applicable CG policies/plans/permits/laws/ordinances. All storm drains and waterways within range of a potential discharge shall be covered/sealed or protected by silt fence.

8. SITE VISIT: Site visits are not required for this requirement. All questions regarding technical requirements can be sent to the Point of Contact.

· Point of Contact (POC) Mike Ackiss Assistant Facilities Engineering Officer Carlton.M.Ackiss@uscg.mil

(504) 239-4937

9. MATERIALS AND LOCATIONS:

a) Materials shall be delivered to the jobsite in their original unopened packages, clearly marked with the manufacturer’s name, brand name, and description of contents. Storage shall be in accordance with manufacturer’s recommendations in a clean, dry, well-ventilated area. Stored materials shall be protected from sunlight and kept away from excessive heat.

b) Delivery Location 1790 Saturn Blvd New Orleans LA, 70129

PART 2 PERFORMANCE STANDARDS

1. PERFORMANCE REQUIREMENTS: Contractor shall furnish equipment as outline below. All associated equipment shall be approved and designed to work with stated model number, or equal.

a) One (1) Securall 8’3”H x 14’W x 8’D Chemical Storage Building or equal, with below specifications

· 60”W x 80”H Double door with 36” Active leaf

· 393 Gal sump capacity

· Explosion relief panels

· Intertek tested, 2-hour fire rated walls

· Intertek tested, 1.5-hour fire rated roof

· OP-100A Load Center

· 12 Space

· 100A main breaker

· NEMA 3R 120/240V

· Two (2) LED explosion-proof light fixtures w/ switch, Class 1 Division 2

· Two (2) explosion proof 15A, 120V, Class 1 Division 1 & 2 receptacles

· Explosion proof exhaust system

· 335 CFM w/ indicator light

· Emergency shut-off switch

· Brass-body exhaust flow switch w/ audible alarm

· 30’ x 14”W shelves w/ 2” lip sides

· 3 tiers of 5’ shelving along left and right walls

b) Deliver to site.

2. CONTRACT TIMELINE: The Contractor shall provide all required information and complete this contract within this time schedule, unless approved by the Contracting Officer or their representative. Any delays on materials or labor issues that will impede the completion of the contract shall be documented with the Contracting Officer or their representative.

a) Provide all required submittals to the Contracting Officer or Contracting Officers Representative within 14 calendar days after contract award.

b) The U.S. Coast Guard will have 7 calendar days to review the submittals and respond to Contractor.

c) Contractor shall provide projected delivery schedule during proposal and provide a firm delivery date within 14 calendar days after the contract has been awarded.

d) The Contractor, upon receiving notification that the U.S. Coast Guard has approved the submittals and having received the Contractors firm delivery date schedule, will have 14 Calendar days to begin work on the project & 30 Calendar days to complete. The Contractor shall notify the Contracting Officer of any long lead time delivery of equipment, so that the Contracting Officer can modify the delivery date of the contract.

3. SUBMITTALS: Once awarded, the following list of submittals required at time of delivery and defines the specific minimum requirements for this contract.

c) Manufactures Technical Publications and Guides

d) Warranty Information

4. WARRANTY: Contractor shall provide a one-year warranty for all materials. All warranty claims by the Coast Guard shall be honored by the vendor at no additional cost to the Coast Guard.