Atch 4 - FSSS Specs.pdf

PDF 533 KB Posted

Attached to
Sheep Gulch and West Table Creek Pavement Repairs
Solicitation number
1240LT24R0014
Issued by

About this file

This document appears to be technical specifications for the Sheep Gulch and West Table Asphalt Preventative Maintenance project. The key details are:

The work consists of applying an emulsified asphalt slurry seal mix on the pavement surfaces and sealing and filling cracks in the asphalt pavement at the Sheep Gulch and West Table boating sites in the Bridger Teton National Forest in Wyoming. Major work items include asphalt crack sealing and slurry sealing, as well as installing new concrete wheel stops and pavement markings. The project has both base items and optional items. The technical specifications provide detailed requirements for the materials, equipment, surface preparation, application, and acceptance procedures for the slurry seal and crack sealing work.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SHEEP GULCH & WEST TABLE ASPHALT PREVENTATIVE MAINTENANCE - FSSS

Table of Contents Preface

101 - Terms¸ Format¸ and Definitions

101.01 Meaning of Terms

101.03 Abbreviations

101.04 Definitions

102 - Bid¸ Award¸ and Execution of Contract

Delete Section 102

103 - Scope of Work

Delete Subsections 103.02, 103.03, 103.04, 103.05

104 - Control of Work

Delete Subsections 104.01, 104.02, 104.04

104.06 Use of Roads by Contractor

105 - Control of Material

105.05 Use of Material Found in the Work

106 - Acceptance of Work

106.01 Conformity with Contract Requirements

106.02 Visual Inspection

107 - Legal Relations and Responsibility to the Public

Delete Subsection 107.05

108 - Prosecution and Progress

Delete Section 108

109 - Measurement and Payment

Delete Subsections 109.06, 109.07, 109.08, 109.09

109.01 Measurement of Work

109.02 Measurement Terms and Definitions

155 - Schedules for Construction Contracts

Delete Section 155

410 – Slurry Seal

414 – ASPHALT PAVEMENT CRACK SEALING AND FILLING

SHEEP GULCH & WEST TABLE ASPHALT PREVENTATIVE MAINTENANCE – FSSS 1

Preface Preface_wo_04_26_2021

Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-14 for construction of National Forest System Roads.

SHEEP GULCH & WEST TABLE ASPHALT PREVENTATIVE MAINTENANCE – FSSS 2

101 - Terms¸ Format¸ and Definitions 101.01_National_11_9_2016

Add the following paragraph to Subsection 101.01:

101.01 Meaning of Terms.

Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.

101.03_National_11_9_2016

Add the following to Subsection 101.03:

101.03 Abbreviations.

(a) Acronyms.

AGAR — Agriculture Acquisition Regulations

AFPA — American Forest and Paper Association

FSAR — Forest Service Acquisition Regulations

MSHA — Mine Safety and Health Administration

NESC — National Electrical Safety Code

WCLIB — West Coast Lumber Inspection Bureau

(f) Miscellaneous unit abbreviations.

MP — milepost location ppm — parts per million volume

STA station location

101.04_National_1_22_2020

Make the following changes to Subsection 101.04:

101.04 Definitions.

Delete these definitions and replace the following:

Bid Schedule — The Schedule of Items.

SHEEP GULCH & WEST TABLE ASPHALT PREVENTATIVE MAINTENANCE – FSSS 3

Bridge — A structure, including supports, erected over a depression or an obstruction such as water along a road, a trail, or a railway and having a deck for carrying traffic or other loads.

Contractor — The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “Purchaser”.

Culvert — Any structure with a bottom, regardless of fill depth, depth of invert burial, or presence of horizontal driving surface, or any bottomless (natural channel) structure with footings that will not have wheel loads in direct contact with the top of the structure.

Drawings — (Public Works Contracts) Design sheets or fabrication, erection, or construction details submitted to the CO by the Contractor according to FAR Clause 52.236-21 Specifications and Drawings for Construction. Also refers to submissions and submittals.

Notice to Proceed — (Public Works Contracts) Written notice to the Contractor to begin the contract work.

Right-of-Way — A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Solicitation—(Public Works Contracts) The complete assembly of documents (whether attached or incorporated by reference) furnished to prospective bidders.

Add the following definitions:

Adjustment in Contract Price — “Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change — “Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.

Forest Service — The United States of America, acting through the Forest Service, U.S. Department of Agriculture.

Neat Line — A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road — Temporary construction access built along the route of the project.

Purchaser — The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse — A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order — An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Shop Drawings — (Timber and Stewardship Contracts) Referred to as “Drawings” in FP-14, include drawings, diagrams, layouts, schematics, descriptive literature, illustrations, lists or tables, performance and test data, and similar materials furnished by Purchaser to explain in detail specific portions of the work required by the contract.

Utilization Standards —

The minimum size and percent soundness of trees described in Public Works contract specifications or Timber Sale and

IRTC contract provisions to determine merchantable timber.

SHEEP GULCH & WEST TABLE ASPHALT PREVENTATIVE MAINTENANCE – FSSS 4

Add Figure 101-1—Illustration of road structure terms:

Figure 101-1—Illustration of road structure terms.

SHEEP GULCH & WEST TABLE ASPHALT PREVENTATIVE MAINTENANCE – FSSS 5

102 - Bid¸ Award¸ and Execution of Contract 102.00_National_11_9_2016

Delete Section 102 in its entirety.

Delete Section 102.

SHEEP GULCH & WEST TABLE ASPHALT PREVENTATIVE MAINTENANCE – FSSS 6

103 - Scope of Work 103.00_National_11_9_2016

Delete all of Section 103 except Subsection 103.01 Intent of Contract.

Delete Subsections 103.02, 103.03, 103.04, 103.05.

SHEEP GULCH & WEST TABLE ASPHALT PREVENTATIVE MAINTENANCE – FSSS 7

104 - Control of Work 104.00_National_11_9_2016

Delete Subsections 104.01, 104.02, and 104.04.

Delete Subsections 104.01, 104.02, 104.04.

104.06_National_11_9_2016

Add the following to Subsection 104.06:

104.06 Use of Roads by Contractor.

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

SHEEP GULCH & WEST TABLE ASPHALT PREVENTATIVE MAINTENANCE – FSSS 8

105 - Control of Material 105.05_National_6_29_2020

105.05 Use of Material Found in the Work.

Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:

Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. Place excess material safely at government-approved location, at no additional cost to government.

SHEEP GULCH & WEST TABLE ASPHALT PREVENTATIVE MAINTENANCE – FSSS 9

106 - Acceptance of Work 106.01_National_7_18_2017

Delete Subsection 106.01 and replace with the following:

106.01 Conformity with Contract Requirements.

Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.

References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.

Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.

Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.

Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.

When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.

The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the

Government tests work, copies of test reports are furnished to the Contractor upon request. Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the

Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of

Government test results for process control.

Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to 106.05 inclusive. The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.

Remove, repair, or replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted. Removing, repairing, or replacing work; providing temporary traffic control; and any other related work to accomplish conformity will be at no cost to the Government.

(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO.

If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:

1. Sampling method;

2. Number of samples;

3. Sample transport;

4. Test procedures;

5. Testing laboratories;

6. Reporting;

7. Estimated time and costs; and

SHEEP GULCH & WEST TABLE ASPHALT PREVENTATIVE MAINTENANCE – FSSS 10

8. Validation process.

If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.

The CO will review the proposed resolution protocol and may modify it before final approval and execution.

The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol. If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.

(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the

Contractor may submit a written request to:

1. Have the work accepted at a reduced price; or

2. Be given permission to perform corrective measures to bring the work into conformity.

The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.

106.02_National_11_9_2016

Delete Subsection 106.02 and replace with the following:

106.02 Visual Inspection.

Acceptance is based on visual inspection of the work for compliance with the specific contract requirements. Use prevailing industry standards in the absence of specific contract requirements or tolerances.

SHEEP GULCH & WEST TABLE ASPHALT PREVENTATIVE MAINTENANCE – FSSS 11

107 - Legal Relations and Responsibility to the Public 107.05_National_7_18_2017

Delete Subsection 107.05.

Delete Subsection 107.05.

SHEEP GULCH & WEST TABLE ASPHALT PREVENTATIVE MAINTENANCE – FSSS 12

108 - Prosecution and Progress 108.00_National_11_9_2016

Delete Section 108 in its entirety.

Delete Section 108.

SHEEP GULCH & WEST TABLE ASPHALT PREVENTATIVE MAINTENANCE – FSSS 13

109 - Measurement and Payment 109.00_National_11_9_2016

Delete Subsections 109.06, 109.07, 109.08, and 109.09:

Delete Subsections 109.06, 109.07, 109.08, 109.09.

109.01_National_2_22_2019

Delete the third paragraph and Table 109-1 of Subsection 109.01 and replace with the following:

109.01 Measurement of Work.

Take measurements as described in Subsection 109.02 unless otherwise modified by the Measurement Subsection of the section controlling the work being performed. Table 109-1 indicates the accuracy required for quantities of the various pay units used in the Schedule of Items. Use this guide to determine the decimal placement in the final payment.

Table 109-1

Decimal Accuracy of Quantities for Final Payment

Pay Item Level of Precision

Linear Foot 1

Exception--Timber, Steel, and concrete Piles 0.1

Station 0.1

Mile 0.01

Square Foot 0.1

Square Yard 0.1

Each 1

Acre 0.01

Gallon 1

M-Gals. 0.1

Cubic Yard 1

Exception--Structure Excavation; Sheathing

Materials; Bedding, Bed Course, and Backfill

Materials; Gabions;

0.1

Exception--Concrete; Masonry 0.01

Pound 1

Ton 0.1

Exception--Calcium Chloride;

Sodium Chloride; Hydrated Lime;

Bituminous Materials; Pavements;

Bed Course Materials

0.01

Hour 0.1

MFBM 0.01

Station Yard 1

Cubic Yard Mile 1

Ton Mile 1

SHEEP GULCH & WEST TABLE ASPHALT PREVENTATIVE MAINTENANCE – FSSS 14

109.02_National_11_9_2016

Add the following sentence to Subsection 109.02(b):

109.02 Measurement Terms and Definitions.

(b) Contract quantity.

Contract quantities will be adjusted only when there are errors in the original design of 15% or more.

SHEEP GULCH & WEST TABLE ASPHALT PREVENTATIVE MAINTENANCE – FSSS 15

155 - Schedules for Construction Contracts 155.00_National_11_9_2016

Delete Section 155 in its entirety.

Delete Section 155.

SHEEP GULCH & WEST TABLE ASPHALT PREVENTATIVE MAINTENANCE – FSSS 16

410 – Slurry Seal

Delete Section 410 in its entirety and replace with the following.

Section 410. — SLURRY SEAL

Description

410.01 This work consists of applying an emulsified asphalt slurry seal mix on a pavement surface.

Material

410.02 Conform to the following Subsections:

Emulsified asphalt 702.02

Mineral filler 725.05

Slurry seal aggregate 703.10(a)

Water 725.01(c)

Construction Requirements

410.03 Qualifications. See Subsection 407.03.

410.04 Composition of Mix (JMF). Submit a written JMF for asphalt slurry seal which conforms to ISSA A105, Recommended Performance Guideline for Emulsified Asphalt Slurry Seal for approval at least 30 days before production. Include the following:

(a) Aggregate gradation values. Percent passing for each sieve size for the aggregate blend;

(b) Emulsified asphalt content. Residual asphalt content, as a percent by mass of dry aggregate;

(c) Aggregate samples. 80-pound (35-kilogram) sample of each aggregate;

(d) Emulsified asphalt sample. 1-gallon (4-liter) sample with a production certification conforming to

Subsection 106.03(a); and

(e) Mineral filler samples. 10-pound (5-kilogram) sample of each proposed mineral filler.

410.05 Equipment.

(a) Mixing equipment. Conform to the requirements of ISSA A105.

(b) Mechanical-type single squeegee spreader box.

(1) Attaches to the mixer;

(2) Flexible squeegee in contact with the pavement surface to prevent loss of material;

(3) Adjustable to ensure a uniform spread over varying grades and crowns;

(4) Adjustable in width with a flexible strike-off; and

SHEEP GULCH & WEST TABLE ASPHALT PREVENTATIVE MAINTENANCE – FSSS 17

(5) Augers for uniform flow to edges.

(c) Sweeper. See Subsection 409.05(c)

(d) Auxiliary equipment. See Subsection 409.05(e).

Other equipment of proven performance may be used in addition to or instead of this equipment when approved by the CO.

410.06 Surface Preparation. See Subsection 406.04(a).

410.07 Weather Limitations. See Subsection 409.07.

410.08 Calibration. Calibrate each mixing unit according to ISSA A105 in the presence of the CO.

410.09 Production Start-Up Procedures. See Subsection 409.09.

410.10 Application. Mix the material according to ISSA A105. Fog the surface with water in front of the spreader.

Blend the additives with the aggregate. Pre-wet the aggregate in the pugmill before mixing with the emulsified asphalt.

Mix the surfacing material a maximum of 4 minutes. Ensure the mix is of uniform consistency as it leaves the mixer and conforms to the approved JMF. Adjust mineral filler and emulsified asphalt content during construction when approved by the CO to adjust for variations in field conditions.

Clean the spreader box before the start of each work shift.

Carry sufficient mix in the spreader to completely cover the surface. Spread the mix with a mechanical-type single squeegee spreader box. In areas not accessible to the spreader box, use hand squeegees to work the mix.

Remove streaks and transverse ripples as defined by ISSA A105 from the finished surface.

Provide straight lines along curbs and shoulders and do not allow runoff on these areas. Provide straight and neat starting and ending joints by masking surfaces at the start, end, and other locations as directed by the CO.

For transverse joints, use a butt joint. Use building paper placed over previously placed slurry seal or other suitable method to avoid double placement of slurry seal. Remove ridges or bumps in the finished surface.

For longitudinal joints, place joints on lane lines. Use half passes and odd-width passes only in turnouts and parking areas. Do not use half passes for the last pass in paved areas. Overlap longitudinal joints no more than 3 inches (75 millimeters). Limit the elevation difference at joints to less than ¼ inch (6 millimeters).

Allow treated areas to cure completely before opening to traffic. Cure is complete when clear water can be pressed out of the mix with a piece of paper without discoloring the paper.

Remove and dispose of material spills and associated debris at the end of each shift according to

Subsection 203.05(a) and (d).

410.11 Acceptance. See Table 410-1 for sampling, testing, and acceptance requirements.

SHEEP GULCH & WEST TABLE ASPHALT PREVENTATIVE MAINTENANCE – FSSS 18

Emulsified asphalt will be evaluated under Subsections 106.03 and 106.04. Furnish a production certification with each load of emulsified asphalt.

Slurry seal aggregate will be evaluated under Subsections 106.02 and 106.04. Mineral filler will be evaluated under Subsections 106.02 an 106.03.

Construction of the slurry seal will be evaluated under Subsections 106.02 and 106.04.

Measurement

410.12 Measure the Section 410 pay items listed in the bid schedule according to Subsection 109.02 for each day’s production.

Payment

410.13 The accepted quantities will be paid at the contract price per unit of measurement for the Section 410 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section.

See Subsection 109.05.

SHEEP GULCH & WEST TABLE ASPHALT PREVENTATIVE MAINTENANCE – FSSS 19

Table 410-1

Sampling, Testing, and Acceptance Requirements Material or

Product

(Subsection)

Type of

Acceptance

(Subsection)

Characteristic Category Test Methods

Specifications

Sampling

Frequency

Point of

Sampling

Split

Sample

Reporting

Time

Remarks

Source

Aggregate for surface mixture (1)

Measured and tested for conformance

(106.04 & 105)

Quality − Subsection

703.10

1 per material type

Source of material

Yes Before producing

Process control

(153.03)

Gradation − AASHTO

T 27 & T 11

2 per day per stockpile

Crusher belt

(during production)

No 24 hours

Not required when using a pre-crushed commercial source

Emulsified

Asphalt (2)

Measured and tested for conformance

(106.04)

Quality − Subsection

702.02

1 per material type

Point of shipment or delivery

Yes, 2 1-quart

(1-liter) samples

Before incorporating into work

SHEEP GULCH & WEST TABLE ASPHALT PREVENTATIVE MAINTENANCE – FSSS 20

Table 410-1 (continued)

Sampling, Testing, and Acceptance

Requirements Material or

Product

(Subsection)

Type of

Acceptance

(Subsection)

Characteristic Category Test Methods

Specifications

Sampling

Frequency

Point of

Sampling

Split

Sample

Reporting

Time

Remarks

Production

Aggregate for surface mixture (1)

Measured and tested for conformance

(106.04)

Gradation.

See Table

703-8 for applicable sieves

− AASHTO

T 27 & T 11

1 per

50,000 yd2

(40,000 m2)

Stockpile Yes 24 hours

Emulsified asphalt (2)

" Quality − Subsection

702.02

1 per day Point of shipment or delivery

Yes, 2 1-quart

(1-liter) samples

− Tested by

Government

Process control

(153.03)

Placement temperature

− − Minimum

1 per distributor truck

Distributor truck

No Before incorporating into work

(1) Applies to each aggregate grade furnished.

(2) Applies to each asphalt material furnished.

SHEEP GULCH & WEST TABLE ASPHALT PREVENTATIVE MAINTENANCE – FSSS

414 – ASPHALT PAVEMENT CRACK SEALING AND FILLING

Delete Section 414 in its entirety and replace with the following.

Section 414 — ASPHALT PAVEMENT CRACK

SEALING

Description

414.01 This work consists of cleaning, sealing, and filling cracks in asphalt pavement surfaces.

Material

414.02 Conform to the following Section and Subsection:

Asphalt concrete 403

Joint sealants and crack fillers (hot applied) 712.01(a)

Construction Requirements

414.03 Equipment. Furnish equipment with the following capabilities:

(a) Air lance. A hot compressed air lance capable of providing clean, oil-free compressed air at a volume of 100 cubic feet (2.8 cubic meters) per minute, a pressure of 120 pounds per square inch (830 kilopascals), and a temperature of 2000

°F (1100 °C).

(b) Application wand. A wand attached to a heated hose attached to a heated material chamber that maintains material temperature within manufacturer’s tolerances. Supply proper wand tips for desired application.

(c) Heating kettle. An indirect-heating double boiler capable of constant and effective agitation. Fill the space between the inner and outer shells with oil or other heat transfer medium. Provide an accurate and calibrated thermometer with a range from 200 to 600 °F in 5 °F graduations (90 to 320 °C in 2 °C graduations) located so the material temperature can be safely checked.

(d) Squeegee or screed. A hand-held squeegee or screed of appropriate configuration for filling cracks flush with the surface, underfilling cracks to recess below the surface, or overfilling cracks to an overband shape.

(e) Compressor. A compressor capable of producing oil- and water-free air at a minimum rate of 100 cubic feet (2.8 cubic meters) per minute with a minimum continuous line pressure of 125 pounds per square inch (860 kilopascals).

414.04 Cleaning. Prevent debris from entering waterways, travel lanes open to public traffic, or areas designated not to be disturbed. Remove dirt, dust, and other deleterious material from the crack walls and cavity using a stream of air or other approved methods.

Blow or brush dry material off the pavement surface.

414.05 Sealing and Filling. Dry the crack surfaces with the hot air lance before sealing or filling. Do not seal or fill cracks when the pavement surface temperature is below 35 °F

(2 °C) and weather conditions are rainy or foggy.

(a) Sealing (cracks ¼ to 1 ½ inches (6 to 38 millimeters) wide). Submit a copy of and adhere to the manufacturer’s recommendations for heating and applying the hot applied crack material. Heat the material to pouring temperature in a heating kettle and continuously agitate the material.

Discard sealant when:

(1) Heated above the safe heating temperature recommended by the manufacturer;

(2) Held at pouring temperature for more than 12 hours;

(3) Reheated more than once; or

(4) Not consistent or uniform in appearance.

Warm and dry the crack surfaces using a hot-compressed air lance if the pavement temperature is lower than 50 °F (10 °C) or moisture is present. Keep the lance moving to prevent burning the pavement surface. Place and finish the material within

5 minutes after heating the pavement surface with the lance.

Use an application wand to place material in each crack from the bottom up. Insulate the wand to maintain pouring temperature while placing material. Return the wand to the heating kettle immediately after sealing each crack. Use a squeegee or screed to strike off the material.

Do not allow traffic on sealed cracks until the sealant has cured or is treated with debonding material recommended by the manufacturer and approved by the CO.

414.06 Resealing Cracks. Reseal cracks exhibiting adhesion failure, damage, incomplete filling, foreign objects in the sealant, or otherwise rejected by the CO.

414.07 Acceptance. Material for asphalt pavement crack sealing or filling will be evaluated under Subsections 106.02 and 106.03.

Asphalt pavement crack sealing and filling will be evaluated under Subsections 106.02 and 106.04.

Measurement

414.08 Measure the Section 414 pay items listed in the bid schedule according to

Subsection 109.02.

Payment

414.10 The accepted quantities will be paid at the contract price per unit of measurement for the Section 414 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.