This is a price schedule template document for the National Park Service (NPS) Denver Service Center containing three sample contract pricing formats for federal construction projects.
The document provides three distinct price schedule examples: (1) a lump-sum format for the Nicodemus National Historic Site (Solicitation 140P6326Q0020) project to refinish wood flooring in Township Hall, priced as a single line item; (2) a Design-Bid-Build (DBB) format for Yellowstone National Park's Johnstonian Visitors Center project (Solicitation N2011080811) with base line items for construction components (visitors center, water line, sanitary sewer line, and rock excavation) plus two option line items for geothermal wells and photovoltaic systems; and (3) a Design-Build (DB) format for Yosemite Valley featuring design and construction as separate lump-sum base line items with one option for a photovoltaic system. All templates specify that offerors must submit pricing for base line items at minimum, with unit prices and extended total prices required for unit-priced items and total prices only for lump-sum items. The templates direct that in case of calculation errors, unit price governs for extended prices and the total of corrected amounts governs for summation errors, with all totals and extended prices rounded to whole dollars. Measurement and payment information is referenced in Division 01 Specifications sections.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amd_0002_Atch_1_Questions-Answers_0002.pdf | ||
| Sol_140P6326Q0020_Amd_0002.pdf | ||
| Sol_140P6326Q0020_Amd_0001.pdf | ||
| Atch_1_SOW.pdf | ||
| Atch_2_DOL_Wage_Determination_KS20260044_5_18_26.pdf | ||
| Atch_4_Experience_Questionnaire.xls | XLS spreadsheet | |
| Sol_140P6326Q0020.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Schedule Template
| Contract Price Schedule Template | |||||
| National Park Service (NPS) - Denver Service Center (DSC) | 3-13-18 | |||||
| Solicitation Number: | 140P6326Q0020 | ||||
| PARK : | NICO Nicodemus National Historic Site | ||||
| Project Title: | Refinishing Wood Floor In Township Hall | ||||
| Notice: Offerors are required to submit an offer that conforms to the solicitation documents with pricing for Base line items. | |||||
| Failure to do so may render the quote unacceptable. | |||||
| Round totals and extended prices to whole dollars. | |||||
| Contract Line Item Number (CLIN) | Contract Line Item (CLI) Title | Quantity | Unit of Measure | Unit Price | Total Price |
| 1 | Refinishing Wood Floor In Township Hall | 1 | LS | $0.00 | |
| TOTAL PROPOSED PRICE | $0.00 | ||||
| All measurement and payment information is included in Division 01 Specifications Section 01 10 00. |
Design-Bid-Build (DBB) Sample
| Contract Price Schedule - Design-Bid-Build (DBB) SAMPLE | |||||
| National Park Service (NPS) - Denver Service Center (DSC) | 3-13-18 | |||||
| Solicitation Number: | N2011080811 | ||||
| PARK - PMIS: | YELL 012345 | ||||
| (Project Management Information System) | |||||
| Developed Area: | Old Faithful | ||||
| Project Title: | Johnstonian Visitors Center | ||||
| Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all | |||||
| option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced | |||||
| line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related | |||||
| item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts | |||||
| govern. Round totals and extended prices to whole dollars. | |||||
| Contract Line Item Number (CLIN) | Contract Line Item (CLI) Title | Quantity | Unit of Measure | Unit Price | Total Price |
| 1 | Visitors Center | 1 | Lump Sum | $0.00 | |
| 2 | Water Line | 400 | Lineal Feet | - 0 | |
| 3 | Sanitary Sewer Line | 200 | Lineal Feet | - 0 | |
| 4 | Rock Excavation | 150 | Cubic Yards | - 0 | |
| TOTAL BASE PRICE (Contract Line Item Number 1 through 4) --------------------------------------------------------------------------------- | $0.00 | ||||
| 5 | OPTION A, Geothermal Wells | 1 | Lump Sum | - 0 | |
| 6 | OPTION B, Photovoltaic System | 1 | Lump Sum | - 0 | |
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 5 and 6) ------------------------------------------------------------------- | $0.00 | ||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 1 through 6) ---------------------------- | $0.00 | ||||
| All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items. |
Design-Build (DB) Sample
| Contract Price Schedule - Design-Build (DB) SAMPLE | |||||
| National Park Service (NPS) - Denver Service Center (DSC) | 3-13-18 | |||||
| Solicitation Number: | N2011080811 | ||||
| PARK - PMIS: | YELL 012345 | ||||
| (Project Management Information System) | |||||
| Developed Area: | Yosemite Valley | ||||
| Project Title: | Design and Build a New Structure | ||||
| Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all | |||||
| option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced | |||||
| line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related | |||||
| item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts | |||||
| govern. Round totals and extended prices to whole dollars. | |||||
| Contract Line Item Number (CLIN) | Contract Line Item (CLI) Title | Quantity | Unit of Measure | Unit Price | Total Price |
| 1 | Design | 1 | Lump Sum | $0.00 | |
| 2 | Construction | 1 | Lump Sum | - 0 | |
| TOTAL BASE PRICE (Contract Line Item Number 1 and 2) --------------------------------------------------------------------------------------- | $0.00 | ||||
| 3 | OPTION A, Photovoltaic System | 1 | Lump Sum | - 0 | |
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 3) ---------------------------------------------------------------------------- | $0.00 | ||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 1 through 3) ---------------------------- | $0.00 | ||||
| All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items. |
File details come from the government source that posted it. Updated .