This document contains the minutes from a pre-proposal site visit and consolidated question and answer session for solicitation number FA483023R0001 from the Department of the Air Force Air Combat Command. The solicitation is for a SABER multiple award contract to provide general construction services at Moody Air Force Base. Key details include that the government plans to award a seed project task order for legitimate construction work at Moody AFB in Fiscal Year 2024 using cost estimates generated through the eGordian Construction Task Catalog software. Offerors must submit any additional questions by 14 calendar days before the revised proposal due date, which will be extended through Amendment 0001 due to changes replacing all references to e4Clicks/RSMeans with eGordian. The evaluation process may involve evaluating proposals in order of lowest to highest total evaluated price to determine if the lowest priced proposal meets all requirements. Past performance must fall within the last 5 years to demonstrate current construction capabilities.

View the file

Other files for this federal contract opportunity

Other files attached to SABER, newest first.
File Type Posted
SABER Pre-Proposal Conference Minutes.pdf PDF
Atch 3_SABER Pre-Prop Conf Slides.pdf PDF
Atch 1_Pre-Prop_Site Visit Attend Sheet.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4830-23-R-0001

Pre-Proposal Conference/Site Visit

Attachment 2 to Meeting Minutes

Consolidated Q&A 1 (Site Visit)

Question Solicitation Reference Question/Comment Government Response

(Govt Use Only)

Resulted in

Change of SOW or

Drawings?

(Govt Use

Only)

Change

Reference

(Govt Use

Only)

1 Seed Project SOW Can the Government supply As Built Drawings for the

B326 Seed Project?

The Government is unable to provide helpful or usable as-built drawings for the seed project. There are too many different as-built drawings for B 326, dating back to 1981. The Government considers that providing these old as-built drawings would add no value. Please build your tech proposal based only on the current floor plans with dimensions that were supplied in the RFP.

No N/A

RFP FA483023R0001 -

IMPORTANT NOTICE TO

OFFERORS (pg. 1)

Conflict in Pricing Book Catalogs. Page 1 of the 1442, Important Notice states- …during source selection e4Clicks/RS Means will be used as specified in L-6.3, Coefficient Rate Proposal. However…. the

Government will transition to utilizing the upgraded eGordian software following contract award.

As these Price Catalogs are two distinct Catalogs how will the contractor accurately calculate the Coefficient

Price Proposal? IE- A coefficient developed through e4Clicks/RSMeans will not correlate directly to eGordian/CTC. Suggest either staying with e4Clicks

/RSMeans for the life of the contract OR switching to eGordian/CTC for the basis of the Coefficient Rate

Proposal.

The Notice on Block 10 of SF 1442 will be deleted in its entirety via Amendment 0001. Since now the

Government has the definite language regarding the eGordian and CTC, that special notice is no longer valid. All verbiage referencing “e4Clicks”, “Unit

Price Book”, or “RSMeans based cost proposal” will be removed from the RFP (e.g., SF 1442, Section B, Section L&M, SABER Specs, SABER Ordering

Guide, etc.) and they will be replaced with specific eGordian reference, providing all instructions on how to use eGordian service and Construction Task

Catalog (CTC) to build your proposal. Please keep an eye on SAM.gov for Amendment 0001 to see all the changes marked. We anticipate releasing Amendment

0001 on or about 21 July with extended proposal due date.

Yes

Summary of Changes will be released with

Amendment 0001 to make it easier to identify the changes made throughout multiple documents.

RFP FA483023R0001 -

IMPORTANT NOTICE TO

OFFERORS (pg. 1)

Because e4Clicks will no longer be used during the performance period of the SABER contract, how will we bid? Will the cost estimate still be based off e4clicks or eGordian?

eGordian is a fee-based cost estimating software and the selected SABER contractor will add the 1.95% of the total contract value as the fee on each task order cost proposal. For source selection purposes, the Government will provide temporary access to eGordian’s CTC at free of fee. Please look out for

Amendment 0001 posting on SAM.gov for specific instructions.

Yes Throughout Amendment 0001

RFP FA483023R0001 - L-4.3.1

Subfactor1: Execution of Moody

AFB Seed Project (pg. 66)

Will the seed project be a legitimate firm-fixed price task order?

Yes, the Government plans to award the SABER seed project as a legitimate task order. The Government is anticipating award of the SABER seed project in

FY24 as opposed to FY23. The contractor will be expected to generate a cost-estimate based on the

CTC. Overall, the seed project is a tangible task order which the Government intends to execute as a task order shortly after the basic SABER contract award is made.

Attachment 2 to Meeting Minutes

Consolidated Q&A 1 (Site Visit)

Question Solicitation Reference Question/Comment Government Response

(Govt Use Only)

Resulted in

Change of SOW or

Drawings?

(Govt Use

Only)

Change

Reference

(Govt Use

Only)

RFP FA483023R0001 - L-3.3

QUESTIONS (pg. 65) When do questions have to be submitted by?

Offers may submit questions using the Q&A form, RFP Attachment 9, at any point in time. However, please submit questions NLT 14 calendar days before the proposal due date. The content of such questions may drive changes to the RFP thereby resulting in amendment(s). Additionally, this will allow the

Government time to research and answer questions in a more accurate manner.

RFP FA483023R0001 - L-3.2

Organization/Number of

Copies/Page Limits: TABLE 1 -

Proposal Organization (pg. 65)

Why were the number of pages for the cost estimate not specified on the RFP?

With the technical narrative and all technical subfactors, the Government has set a combined limit of 70 pages (number of drawings are not included in the page limit). The offeror is responsible for determining how many pages to allocate to their cost-estimate. However, with the utilization of the CTC eGordian, offerors should expect a uniform number of allocated pages for the cost estimate. The Government believes the 70-page limit is sufficient and reasonable even with the usage of CTC. If it’s determined the page limit needs to be changed, the Government will accomplish an amendment to officially change the page limit.

RFP FA483023R0001 -

IMPORTANT NOTICE TO

OFFERORS (pg. 1)

What if eGordian’s Construction Task Catalog (CTC)/software leads to a significant increase is the cost estimate? In other words, what if it takes up more pages than expected?

Please see the answer provided in Question #6. No N/A

RFP FA483023R0001 - M-1.3.2

Evaluation Process (pg. 78)

Is it true that you may only evaluate one proposal and award without discussions?

Yes, if the proposal with the lowest TEP meets all of the Government’s criteria in accordance with FAR

52.215-1(f)(4). Please see the detailed evaluation processes stated in RFP Section M-1.3.1.

RFP FA483023R0001 - M-1.3.2

Evaluation Process (pg. 78)

So, will you ever evaluate past the first proposal even if it meets all the Government criteria?

Please see the answer provided in Question #8. No N/A

RFP FA483023R0001 - L-6.3.3

Initial Total Evaluated Price (TEP)

(pg. 70)

Don’t you think that it is unfair for the Government to not evaluate each proposal? We (the offerors) put a lot of time, money, and effort into generating these proposals.

Upon receiving all proposals submitted by the proposal due date and time, all offeror’s proposals will be ranked from lowest TEP to highest TEP in-order-to establish the order of proposal evaluation.

This is a common practice in DoD contracting and allowed by FAR 52.215-1(f)(4) for the purpose of efficiency. If the first proposal evaluated happens to

Attachment 2 to Meeting Minutes

Consolidated Q&A 1 (Site Visit)

Question Solicitation Reference Question/Comment Government Response

(Govt Use Only)

Resulted in

Change of SOW or

Drawings?

(Govt Use

Only)

Change

Reference

(Govt Use

Only) receive an “Acceptable” rating for the technical factor, a “substantial Confidence” rating for the past performance factor, and their proposed coefficient is determined reasonable and is determined to be responsible IAW FAR 9.104-1, the Source Selection

Authority (SSA) may determine that further evaluation is not necessary and make the award to that offeror. Please read RFP Section M-1.3.2, Evaluation

Process, very carefully.

RFP FA483023R0001 - M-1.3.2

Evaluation Process (pg. 78) and

RFP FA483023R0001 - L-6.3.3

Initial Total Evaluated Price (TEP)

(pg. 70)

How are you sorting proposals/which one will be evaluated first?

Please see the answer provided in Question #10. No N/A

RFP FA483023R0001 - L-3.2

Organization/Number of

Copies/Page Limits: TABLE 1 -

Proposal Organization (pg. 65)

Are we submitting a DVD/CD?

Yes. Please see RFP Section L-3.2, Table 1 for

Proposal Organization.

No N/A

RFP FA483023R0001 - M.4.1.1

Recency Assessment (pg. 83)

Does past performance have to fall only within the past 5 years?

Yes. Please see RFP Section M.4.1.1, Recency Assessment.

RFP FA483023R0001 - M.4.1.1

Recency Assessment (pg. 83)

Why is past performance limited to only 5 years and not 15 years like usual?

The Government must be able to determine the offeror is still able to perform according to current construction standards today. Construction projects performed 15 years ago may be obsolete or not relevant currently/today.

RFP FA483023R0001 -

IMPORTANT NOTICE TO

OFFERORS (pg. 1)

How are we utilizing eGordian for the Price and other Contracting Considerations factor?

The eGordian software and CTC will be used for building the cost estimate for the SABER seed project under Technical subfactor 1(c) and to build your coefficient to be evaluated under Price factor. The

Government will be evaluating the cost estimate to determine technical acceptability, i.e., the Government will use the offeror’s estimate in-order-to determine how accurate the offeror is in generating the cost estimate.

RFP FA483023R0001 -

IMPORTANT NOTICE TO

OFFERORS (pg. 1)

Why eGordian?

eGordian owns RS Means/e4clicks and is sunsetting that software within the next two years.

Attachment 2 to Meeting Minutes

Consolidated Q&A 1 (Site Visit)

Question Solicitation Reference Question/Comment Government Response

(Govt Use Only)

Resulted in

Change of SOW or

Drawings?

(Govt Use

Only)

Change

Reference

(Govt Use

Only)

RFP FA483023R0001 -

INSTRUCTION TO OFFEROR(S)

(pg. 1)

What changes will be reflected in Amendment 0001?

One change that the Government anticipates is the inclusion of the moratorium issued by the Small Business Administration (SBA). Offerors will no longer need to have a bona fide branch office in the

Region IV area. Additionally, all e4Clicks/RSMeans references will be removed from SF 1442, Section

L&M, and other RFP attachments. A complete

Summary of Changes will be published with Amendment 0001 that will make easier for the offerors to identify all the changes in multiple documents. The Government anticipates releasing Amendment 0001 on or about 21 July 23. Please keep your eye on SAM.gov for Amendment 0001.

N/A N/A

RFP FA483023R0001 -

INSTRUCTION TO OFFEROR(S)

(pg. 1)

It was stated that we are to wait until there is an amendment with the eGordian CTC for Moody AFB so that we can price the seed project. Does the 23 CONS plan on extending the proposal submission date to accommodate this release?

Amendment 0001 will provide reasonable proposal submission date extension due to numerous eGordian related changes throughout the RFP documents.

Yes Amendment 0001