Atch 2 - Blackrock RD RD Parking Lot Rpr SOW.pdf
PDF 122 KB Posted
- Attached to
- GAOA Blackrock RD Parking Lot Rpr
- Solicitation number
- 1240LT24Q0014
- Issued by
-
Department of Agriculture Forest Service
About this file
This document provides the statement of work for the GAOA Blackrock Ranger District Parking Lot Repairs federal contract opportunity. The project includes asphalt crack sealing, slurry sealing, and pavement markings at the Blackrock District Office and Work Center in Teton County, Wyoming. Optional items are the removal and replacement of an existing concrete sidewalk and full depth asphalt patching. The anticipated period of performance is 30 calendar days following the notice to proceed, with all work to be completed by September 30, 2024. The solicitation number is 1240LT24Q0014 and interested parties must direct any questions to the contact provided by March 8, 2024. Site conditions, traffic control requirements, work areas, and inspection procedures are also outlined.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section C - Description/Specifications/Statement of Work
GENERAL SPECIFICATIONS
GAOA - BT – Blackrock Ranger District Parking Lot Repairs
1.1 SCOPE OF CONTRACT
A. The Blackrock Ranger District Parking Lot Repairs project includes base bid items of asphalt crack sealing and slurry sealing all asphalt pavements at the Blackrock District Office and work Center. This also includes white pavement markings and one ADA style pavement marking.
B. Optional bid items include removal of existing concrete sidewalk and replacement with new reinforced cement concrete and full depth asphalt pavement patching (3” depth, Type
II).
1.2 PROJECT LOCATION
A. The project is located on the Bridger-Teton National Forest on the Blackrock Ranger District, Teton County, Wyoming. The site is accessed via U.S. Highway 26 and is located approximately 38 miles northeast of Jackson, Wyoming. The Blackrock Ranger District Office is on the south side of U.S. Highway 26 and the Blackrock Work Center is on the north side of U.S. Highway 26.
1.3 SITE INFORMATION AND LIMITATIONS
A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:
1. The Contractor must coordinate must minimize closures and impacts to Forest Service facilities and operations. The contractor must coordinate and schedule any closures or interruption to Forest Service operations with Forest Service contracting officer representative (COR). The contractor is responsible for appropriate traffic control signing.
2. All construction equipment shall be pressure washed before entering National Forest System lands. The removal of mud and debris from treds, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.
1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING
A. A traffic control plan must be submitted to the COR for approval. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices
(MUTCD).
1.5 WORK CAMPS, STAGING AND STORAGE AREAS
A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage work trailers on site.
B. Overnight camping may be allowed on site with prior approval.
1.6 INSPECTION OF WORKSITE
A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
1.7 PERIOD OF PERFORMANCE
A. 30 Calendar days after Notice to Proceed
1.8 CONTRACT TIME
A. Anticipate work to begin May 31,2024 but may be sooner depending on weather. All work must be completed prior to Setptember 30, 2024.
1.9 SPECIFICATIONS
A. Follow FP-14 https://flh.fhwa.dot.gov/resources/specs/fp-14/fp14.pdf
END OF SECTION
| 1.1 SCOPE OF CONTRACT |
| 1.2 PROJECT LOCATION |
| 1.3 SITE INFORMATION AND LIMITATIONS |
| 1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING |
| 1.5 WORK CAMPS, STAGING AND STORAGE AREAS |
| 1.6 INSPECTION OF WORKSITE |
| 1.7 PERIOD OF PERFORMANCE |
| 1.8 CONTRACT TIME |
| 1.9 SPECIFICATIONS |
| END OF SECTION |