This is a Statement of Work (SOW) for the Wind Cave National Park Road 404 and 405 Gravel Resurfacing project located in Hot Springs, South Dakota. The project involves resurfacing two roads serving critical infrastructure: Road 404 (Well/Lagoon Road, approximately 1.8 miles long) and Road 405 (Campground/Water Tank Road, approximately 1.6 miles long). The work includes road realignment, new gravel surfacing, storm water culvert improvements, and low water crossing upgrades.

The project is being executed by the National Park Service Midwest Region with a total performance period of 180 calendar days from the Notice to Proceed. The scope encompasses comprehensive road rehabilitation, including site clearing, earthwork, crushed stone surfacing, storm drainage system improvements, and landscape restoration. Specific requirements include preparing the subgrade, installing geotextile filter fabric, placing crushed stone in multiple compacted lifts, implementing native grass seeding for disturbed areas, and installing storm drainage culverts and flared end sections. The work will be performed under a single contract with strict quality control, safety, and environmental protection standards.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WINDCAVE NATIONAL PARK

South Dakota

Road 404 and 405 Gravel Resurfacing

WICA

PMIS NO. 245889 & 246063

PROJECT SPECIFICATIONS

(Construction Documents)

NATIONAL PARK SERVICE

MIDWEST REGION

JANUARY 2025

This page intentionally left blank.

WICA - 245889 & 246063 00 01 10 - 1

Table of Contents

TABLE OF CONTENTS 1

DIVISION 00 — PROCUREMENT AND CONTRACTING REQUIREMENTS 2

00 01 07 - SEALS AND SIGNATURES

DIVISION 01 — GENERAL REQUIREMENTS 4

01 10 00 - SHORT FORM GENERAL REQUIREMENTS V2023-11-11

DIVISION 31 — EARTHWORK 6

31 10 00 - SITE CLEARING

31 20 01 - SHORT-FORM - EARTH MOVING

31 22 19 - FINISH GRADING

31 23 33 - UTILITIES - TRENCHING AND BACKFILLING

31 37 00 - RIPRAP

DIVISION 32 — EXTERIOR IMPROVEMENTS 12

32 15 40 - CRUSHED STONE SURFACING

32 92 00 - SEEDING, SODDING AND LANDSCAPING

DIVISION 33 — UTILITIES 15

33 40 00 - STORM DRAINAGE SYSTEM

WICA - 245889 & 246063 00 01 07 - 1

SEALS AND SIGNATURES

00 01 07 - SEALS AND SIGNATURES

I hereby certify that the portion of the Specifications described below was prepared by me or under my direct supervision and that I am a duly registered Professional Engineer under the laws of the State of South

Dakota.

Christopher Bailey 01/30/2025

Pages or Specifications divisions or sections covered by this seal:

Divisions: All

Sections: All

END OF SEALS AND SIGNATURES

D I V I S I O N 0 0

PROCUREMENT AND CONTRACTING

REQUIREMENTS

D I V I S I O N 0 1

GENERAL REQUIREMENTS

WICA - 245889 & 246063 01 10 00 - 1

SHORT FORM GENERAL REQUIREMENTS V2023-11-11

SECTION 01 10 00 - DIVISION 1 SHORT FORM GENERAL REQUIREMENTS

PART 1 – GENERAL

ITEM 1 - DESCRIPTION OF WORK

1.1 Background: These two roads serve as the maintenance personnel’s access route to the water tank, lagoons, and water supply well at Wind Cave National Park near the Visitor’s Center. The existing condition of these roads has deteriorated, and they are in need of upgrades to maintain access to this critical infrastructure. This project will rework the grade of the roads as needed, upgrade the gravel surface to a consistent width throughout, and upgrade the storm sewer culvert crossings & low water crossings on the roads.

1.2 Work Covered by the Contract Documents:

A. Project Location: Wind Cave National Park, 26611 US Highway 385, Hot Springs, SD 57747.

B. Work consists of:

1. Work includes resurfacing of Road 404 (Well/Lagoon Road) (approximately 1.8 miles long) and

Road 405 (Campground/Water Tank Road) (approximately 1.6 miles long). Realignment, resurfacing with new gravel surfacing, storm water culverts, and low water crossings are included in the scope of work.

C. All work will be performed under a single contract.

D. Period of performance: Work shall be completed within 180 calendar days of the start date provided on the Notice to Proceed.

1. Clarification: The Notice to Proceed will be issued with a period of performance that is all inclusive of supply lead times, material deliveries, decommissioning, installation, anticipated average weather days for location, final commissioning, and acceptance of completed work. The contractor will be expected to provide a project schedule with adequate critical path details to ensure all work is completed within the stated calendar days from issuance of the Notice to

Proceed. If weather impacts project beyond typical average weather patterns, contractor shall provide documentation in request for additional days. If there are weather related environmental factors affecting the construction period where unexpected adverse weather conditions may delay progress. The Contracting Officer will work with the Contractor to adjust the POP at no additional cost to the Government.

1.3 Existing Condition Protections:

A. Preservation of Historical and Archeological Fabric:

i. The Historic and Archeological Data Preservation Act of 1974, provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.

ii. IF, in connection with operations under this contract, the Contractor, subcontractors, or employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts, the Contractor shall immediately suspend all operations in the vicinity of the discovery and notify the Contracting Officer immediately, when safe to do so, and follow up in writing within 2 days, giving the location and nature of the findings. No objects of cultural resource value may be removed. Contracting Officer will contact other entities as required.

WICA - 245889 & 246063 01 10 00 - 2

iii. Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with Changes clause.

iv. The Contractor will be responsible for protecting the cultural resources within and adjacent to the project area from damage. In addition, the Contractor will be liable for all damage to the cultural resources caused by their actions or the actions of their agents or representatives. The

Contractor shall immediately notify the Contracting Officer or their representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.

v. The Contractor agrees to include this language within all subcontracts.

B. Protection of Landscaping and Surrounding Structures: All Ground Disturbance at this project shall have oversite by an Owner provided Archeologist. Coordinate schedules as required. The Contractor shall take all necessary measures to provide protection for all trees, fencing, walks and other landscape features and surrounding structures near the work site as noted with the contract. Any such surrounding features damaged, scarred or broken as a result of the Contractor’s operations at the site outside of agreed upon documented extents, shall be treated, repaired or replaced in kind to the satisfaction of the

Contracting Officer at no additional expense to the Government.

ITEM 2 – PROTECTING EXISTING UTILITIES

2.1 Protecting Existing Utilities: Notify Contracting Officer (CO), Contracting Officer’s Representative

(COR) and utility companies as required to request location services prior to and to coordinate any excavation/digging operations, and/or for demolition if within Scope of Work.

2.2 Contractor shall be responsible for locating and preventing damage to known utilities on site or indoors. If contractor damage occurs, alert CO and COR as soon as safely possible, and repair utility at no additional expense to the Government. If damage occurs to an unknown utility, contact CO and COR as soon as safely possible.

2.3 Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated below:

A. Notify CO and COR not less than two business days in advance of proposed utility interruptions.

B. Hours for Utility Shutdowns: Shutdowns shall not exceed 2 to 3 hours. Temporary provisions will be needed by the Contractor for periods longer than stated allowance or if required for critical systems as determined by COR.

ITEM 3 - CONTRACTOR’S USE OF PREMISES

3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.

https://www.nps.gov/wica/learn/management/superintendent-s-compendium.htm

C. Communications: Contractor shall provide the Contracting Officer and COR with methods of communications including land and/or cell phone numbers (note some areas of work have limited service coverage), email and in case of emergency 24-hour contact options for duration of time operations.

D. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

WICA - 245889 & 246063 01 10 00 - 3

E. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.

F. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public.

3.2 On-site work hours: Work shall be generally performed during normal business working hours of 7 a.m. to

5 p.m., Monday through Friday, except when otherwise indicated.

A. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.

The following Federal holidays are observed by the National Park Service:

New Year Day

Martin Luther King, Jr’s Birthday

Washington’s Birthday

Memorial Day

Juneteenth National Independence Day

Independence Day

Labor Day

Columbus Day

Veterans Day

Thanksgiving Day

Christmas Day

B. Note: Any of the above holidays falling on a Saturday will be observed on the preceding Friday;

holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal Holidays (opm.gov).

3.3 Contractor Use of Site:

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to construction area as shown on site plan within the work limits shown and the staging area near the NPS boneyard off of Road 405. Do not disturb portions of Project site beyond areas in which the Work is indicated.

B. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.

C. Do Not disturb site outside of noted disturbance area, including earthwork and clearing of vegetation, limit disturbance to:

1. 10 feet beyond gravel surfacing and storm sewer/low water crossings.

D. Utilities:

1. General: Cost or use charges for temporary facilities shall be included in the Contract Sum as required.

2. Water Service: Water from existing water system is not available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Use resources wisely and minimize waste of water. Coordinate with COR for possible water use within the park.

https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022

WICA - 245889 & 246063 01 10 00 - 4

3. Electric Power Service: Electric power from existing system is not available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Power may or may not meet your construction power tool requirements, provide generators if questionable. Use power in a resourceful manner and avoid excess power waste.

4. Waste Operation:

a. Toilets: Contractor must provide toilets for contractor personnel, sufficiently lighted and ventilated toilet facilities in weatherproof, sight proof, handicap accessible (if required), sturdy enclosures with privacy locks. Coordinate with COR for approved location if not shown on attached site plan.

b. Waste Removal / Recycling: Contractor is responsible for removing all waste created by the project. Contractor shall recycle to the highest degree possible and empty dumpsters as necessary to avoid debris on site. Locate as shown on site plan or coordinated with COR.

A. Security and Protection facilities:

B. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

C. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds.

Ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area. Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required.

D. Tree and Plant Protection: N/A.

E. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting

Officer Representative and remove agreed-on roots and branches that interfere with construction.

F. Do not fasten ropes, cables, or guys to trees.

G. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

H. Pest Control: Follow best practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at project completion. Perform control operations lawfully, using environmentally safe materials.

I. Hot Work Permit: N/A.

J. Storage - Staging Areas:

A. Confine Storage of materials and equipment to the project staging area noted on the plans/aerial.

Specific storage units shall be provided by the Contractor and exact location within staging area may be discussed at the preconstruction briefing. All storage units provided by the Contractor shall be in a clean and acceptable condition to the COR. Security of the materials and equipment on site is the

Contractor’s responsibility.

WICA - 245889 & 246063 01 10 00 - 5

3.5 Preservation of Natural Features: No cutting allowed in the area noted on the plans as sensitive area.

3.6 Hauling Restrictions: Contractor shall verify and be responsible for the path accessing the site and obtaining / maintaining all local, county, state and federal permits/licenses associated with hauling/road requirements and dumping of materials associated with the project.

3.7 Housekeeping:

A. Keep project neat, orderly, and in a safe condition at all times.

1. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters.

2. Address Recycling: Government goal is to salvage and recycle as much nonhazardous construction waste as possible. Use sustainable methods to extent possible during this project, recycling material as is probable with local means. Maintain accurate documentary records for submittal of all recycled materials used including fly ash and slag cement.

3.9 Photo Documentation:

A. Contractor must provide existing condition, progress, and completion photos. All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed.

Shall be in JPEG digital form and submitted preferably electronically by email or optional via CD-R

Archival Gold or DVD-R Archival Gold media with printed labels and 8 mega pixels minimum within

7 days from time of taken or as approved by COR.

B. Existing Condition Images:

1. Before starting construction, take color, dated, digital images of project site and adjacent property/roads/etc. that may be impacted by construction activity/traffic. Include existing items to remain or be salvaged from different vantage points and with context for location identification.

C. Construction Progress Images:

1. Document all sub-surface work/ trenches etc. prior to backfill with photos covering enough overall field view to show location and then zoom in for details. (Locations and dimensions shall also be noted on as built drawing set.).

2. Maintain organized index for photos with date, description, etc.

3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.

D. Completion Images:

1. Document all completed work within scope of work.

2. Maintain organized index for photos with date, description, etc.

3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.

3.10 Fire and Life Safety:

K. As a minimum, conduct one weekly 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the CO and COR within one day after the meeting and document the meetings on the daily reports.

WICA - 245889 & 246063 01 10 00 - 6

L. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and

Demolition Operations). Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.

M. Store and handle hazardous materials in accordance with manufacturers and OSHA 29CFR1926 Subpart

D requirements 1926 | Occupational Safety and Health Administration (osha.gov). Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.

1. Immediately report all spills of hazardous materials to the CO, COR, and park.

2. Maintain a spill emergency response kit.

3. Train employees how to respond to a spill and use the emergency response kit.

3.11 Noise and Acoustics Management:

N. Contractor shall not have personal radios or other media sources and they shall not be broadcast within

NPS property.

ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION

4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract.

Contractor shall coordinate and incorporate long lead and delivery time items within the schedule.

ITEM 5 - EXAMINATION OF THE SITE

5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids.

Contractors will be accountable for understanding existing conditions. No cost changes for items visible during site visit will be allowed.

ITEM 6 - ABBREVIATIONS

6.1 The list of abbreviations, standards and organizations which may be used in/referred within the

Construction Specifications or Special Provisions, may be found linked from the listed page below. On the home page, follow the link under “Contracting and Procurement” labeled “NPS Reference Standards.”

https://www.nps.gov/orgs/1671/do-business-with-us.htm

ITEM 7 - ACCIDENT PREVENTION

7.1 Description: The work of this section consists of establishing and implementing an effective accident prevention program (APP) and providing a safe environment for all personnel and visitors.

7.2 Submittals:

A. Accident Prevention (Safety) Plan (APP): Submit a site-specific accident prevention (safety) plan.

The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:

1. Name and qualifications of responsible supervisor to carry out the program.

2. First aid and rescue procedures.

3. Training, both initial and continuing.

4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase, with a Job

Hazard Analysis (JHA)/Job Safety Analysis (JSA), etc. A sample JHA template may be provided upon request.

https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.nps.gov/orgs/1671/do-business-with-us.htm

WICA - 245889 & 246063 01 10 00 - 7

5. Planning for possible emergency situations, such as cave-ins, earthquake, explosions, fires, floods, power outages, wildlife encounters, slides, snowstorms, thunderstorms, and windstorms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.

6. Contractor to identify nearest location of medical facility for emergencies.

7. Recognition that works will be performed in remote areas with limited communication or cell phone coverage if applicable.

8. Supplemental hazard specific plans may be required IAW 29 CFR 1926 or 1910.

B. Meeting and Inspection Reports: Safety Meetings: As a minimum, conduct 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite. Submit a report of safety meetings and inspections to CO and COR within one day after the meeting and document the meetings on the daily reports.

7.3 Qualification of Employees:

A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.

B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.

7.4 Accident Reporting: The Contractor shall report all accidents to the CO and COR as soon as safely possible and assist the CO and COR and other officials as required in the investigation of the accident.

7.5 First Aid Facilities: Provide access to facilities for the number of employees and appropriate to the hazards associated with the types of ongoing construction work at the site.

7.6 Emergency Instructions: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.

7.7 Personal Protective Equipment (PPE): It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.

A. PPE must meet requirements of applicable ANSI standards. Selection shall conform to OSHA 29CFR

1926 Subpart E.

B. A hard hat use area shall be designated by the Contractor. The hard hat area shall be posted by the

Contractor in a manner satisfactory to the Contracting Officer.

C. All PPE will be serviceable at all times. At a minimum, maintain four sets of PPE including hard hats and all other Accident Prevention Plan required equipment.

7.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate, if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state, and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.

A. If a spill, leak, or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the local 911 Emergency Response, COR and or the National Park Service Emergency

Dispatch.

WICA - 245889 & 246063 01 10 00 - 8

ITEM 8 - PRECONSTRUCTION CONFERENCE

8.1 If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed. See Item 9.1C below.

ITEM 9 - SUBMITTALS

9.1 General Contracting Submittal Procedures:

A. General: Prepare and submit submittals required by individual Technical Specification Sections.

Types of submittals are indicated in individual specific sections.

1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using National

Park Service form CM-16 form. The form will be provided by the Contracting Officer. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Submit completed CM-16 forms to the CO and the COR.

B. Submittal List: Administrative required submittals are listed below in 9.1.C and does not include technical section submittal requirements included in each technical section.

C. Preconstruction Conference Submittal: Satisfactory evidence of liability insurance coverage and workman’s compensation, and any applicable bonds, must be submitted within 10 calendar days of

Notice of Award. The following items are to be submitted prior to the Preconstruction Conference or as specified at the CO’s discretion. The timeline for the documents to be submitted will be addressed at the pre-construction conference for those items that were not received and approved prior. Notice to

Proceed may not be issued, and the Contracting Officer will consider other contractual remedies if not resolved as directed. Work shall not commence until written Notice to Proceed has been issued.

Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference:

1. Letter designating Project Superintendent.

2. Construction Schedule. (Must include shop drawings, procurement time including long lead time items, mobilization, trade work progression and completion at minimum.)

3. A comprehensive breakdown of the Schedule of Values.

4. Accident Prevention (Safety) Plan (see section 7 of this document).

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).

7. Quality Control Plan.

8. Waste Management Plan.

9. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP) Submitted to AHJ (Authority

Having Jurisdiction).

10. List of Required Construction Permits. Include the following information for each permit:

a. Name of Permit.

b. The Agency(ies) with Jurisdiction issuing the permit.

c. Information required from the Government to complete the permit application.

9.2 Project Submittal Process (Shop Drawings, Product Data, and Samples): Contracting Officer will provide sample cover sheet and a list of required submittals is included in each technical specification or attached at the end of this document.

A. Shop Drawings: Indicate all coordinating materials and work impacting the installation coordination, connection details, anchorage requirements, hardware locations, and installation details and locations.

WICA - 245889 & 246063 01 10 00 - 9

1. Submit Shop Drawings according to Part 9.1 of this section to include one digital file (.PDF or

.TIF) and two full size hardcopy documents to COR.

B. Product Data: Provide component construction and specification data sheets, anchorage requirements and any other product specific data.

1. Submit Product Data according to Part 9.1 of this Section to include one digital file (.PDF or .TIF) to COR.

C. Samples: Submit 2 color samples 4” x 6” minimum in size for all product color selections. Paint samples shall be actual paint finish drawdown for all project colors.

1. Submit Samples CM-16 Transmittal Form according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and physical samples of actual material to COR.

D. For submittals specified above, forward submittals to Contracting Officer and COR at least 15 days before need for approval (depends on length of project).

E. After approving submittals, Contracting Officer and/or COR will return one copy to the Contractor. If submittals are not approved, Contracting Officer will return all copies to Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.

9.3 Approved Equals: All brand names noted are subject to ‘or equal’ products. If an item in this solicitation is identified as “brand name or equal” or lists more than 1 manufacturer, the description of the proposed item must reflect the characteristics and level of quality that will satisfy the Government’s needs as demonstrated by the salient physical, functional, or performance characteristics that “equal” products must meet and/or exceed that as specified in the solicitation or relevant specification. Contractor shall incorporate and be responsible for all collateral costs due to the or equal proposed as required to provide a complete project.

A. For each item proposed as an “approved equal,” submit supporting data, including:

1. Drawings and samples as appropriate.

2. Comparison of the characteristics of the proposed item with that specified and with the salient characteristics provided.

3. Changes required in other elements of the work because of the substitution.

4. Name, address, and telephone number of vendor.

5. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists. Describe availability of maintenance service, and state source of replacement materials.

B. A request for approval constitutes a representation that General Contractor:

1. Has investigated and shall provide documentation in request showing that the proposed item is equal or superior in all respects to the salient characteristics specified.

2. Will meet or exceed warranties for the proposed item specified.

3. Has determined that the proposed item is compatible with interfacing items.

4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.

5. Waives all claims for additional expenses that may be incurred as a result of the substitution.

C. Approved Equals will be evaluated and approved/disapproved during the submittal process.

WICA - 245889 & 246063 01 10 00 - 10

9.4 Schedule of Values: Submit the Schedule of Values a minimum of one week prior to the Preconstruction

Conference for COR review. Schedule of Values shall include defined work line items with cost break downs including labor, material, and equipment for COR approval.

9.5 Progress Reporting: The initial Construction Schedule and Schedule of Values are required a minimum of one week prior to the Preconstruction Conference. After the Notice to Proceed is issued and after on-site work begins, progress will be documented via daily logs and by providing an updated Construction

Schedule and Schedule of Values when requested, but minimally with each pay application. Submit digital copy electronically (PDF preferred) of all required documents. Construction Schedules are normally in bar chart form and indicate estimated starting and completion dates for each part of the work. For a pay application to be reviewed and processed in a timely manner, the following information must either be submitted prior to or accompany submission of the pay application:

A. Daily/weekly progress reports during construction as part of the administration process.

B. Updated Schedule of Values: Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The Schedule of Values will form the basis for payment. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification.

The total costs for the component work activities shall equal the contract price for that lump-sum item.

The Contracting Officer may request data to verify accuracy of dollar values. A sample Schedule of

Values format may be provided upon request.

ITEM 10 – TEMPORARY SERVICES

10.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this Contract.

ITEM 11 - PROJECT CLOSEOUT

11.1 Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures working toward Final Acceptance.

11.2 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. Move attic stock to location coordinated with COR. At time of final inspection, project shall be thoroughly clean and ready for intended use. Inspector holds the right to reschedule if project is not ready for inspection.

11.3 Completion and Final Inspection: Contractor shall submit written certification of project completion and request a final inspection to the Contracting Officer and COR. The Contracting Officer or designee will make an inspection within 10 days of receipt of request or at a mutually agreeable time.

A. If the work is determined to be complete following the final inspection with minor comments, the COR will prepare and provide the Contractor a Punch List noting outstanding items to be addressed.

B. If the work is not determined to be complete following the final inspection, the Contracting Officer will notify Contractor in writing, stating reasons. Contractor, after completing the work according to the Contract Documents, shall resubmit completion and request a new final inspection. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.

C. Contractor shall complete the Punch List within 30 calendar days, or a time directed by the CO.

D. Once Contractor completes all items of work on the Punch List and all contractually required items are accepted, Contracting Officer will issue Letter of Final Acceptance of Work and request the final pay application.

WICA - 245889 & 246063 01 10 00 - 11

E. If the Contractor fails to complete the work within the time frame, the Contracting Officer may correct the work with an appropriate reduction in contract price or charge for re-inspection costs in accordance with the Inspection of Construction contract clause.

F. Disposition of any permits and warranties required by the specifications in this section.

11.4 Final Acceptance of the Work: After all punch list deficiencies have been corrected, a Letter of Final

Acceptance will be issued. A Release of Claims document must be executed and submitted to the

Contracting Officer before final payment can occur.

11.5 Warranties:

A. Construction Warranty shall be based on date of final acceptance of the work and remain in effect for one year.

B. Provide all manufacturer warranty information of products installed organized by Division. All contact information, extent of coverage and conditions shall be clearly noted as well as date of overall final acceptance.

C. Information shall include operation and maintenance manuals for each warranted product.

ITEM 12 - DEFINITION OF CONTRACT LINE ITEMS

12.1 Summary

A. The intent of this Section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut off points where one item ends, and another begins.

B. If no contract line item exists for a portion of the work, include the costs in a related item.

12.2 List of Contract Line Items

A. Contract Line Item No 001 – Road 404 Gravel Resurfacing.

1. This item consists of the Gravel resurfacing of Road 404 including minor grading & realignment as needed, new gravel surfacing, storm sewer improvements, and low water crossing improvements.

B. Contract Line Item No 002 – Road 405 Gravel Resurfacing.

1. This item consists of the Gravel resurfacing of Road 405 including minor grading & realignment as needed, new gravel surfacing, storm sewer improvements, and low water crossing improvements.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXCUTION (NOT USED)

END OF SECTION

D I V I S I O N 3 1

EARTHWORK

WICA - 245889 & 246063 31 10 00 - 1

SITE CLEARING

SECTION 31 10 00 - SITE CLEARING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Site clearing Work, including:

a. General provisions for site clearing Work.

b. Preparation for site clearing Work.

c. Clearing and grubbing.

d. Tree protection, selective removals, and selective trimming.

e. Disposal and cleaning.

f. Stripping and stockpiling of topsoil.

B. Related Requirements: Include but are not necessarily limited to:

1. Section 31 20 01 - Earth Moving.

2. Section 31 23 33 - Trenching and Backfilling.

1.2 REFERENCES

A. Terminology:

1. Terms indicated below are not defined terms indicated with initial capital letters but, when used in this Section, have the meanings indicated below:

a. “Arborist” means Subcontractor retained to perform Work requiring a specialist in trees, shrubs, brush, other vegetation of the types existing at the Site, and possessing not less than the required qualifications indicated in this Section.

b. “Clearing and grubbing” means removing and disposing of all: (1) trees, brush, and other vegetation, logs, and similar items (“clearing”); and (2) stumps, roots, logs, rubbish, and debris on or in the soil (“grubbing”) after Clearing. Clearing and grubbing includes grinding and removing of stumps. When clearing and grubbing, topsoil stripping and stockpiling, and required demolition Work is complete, the

Site will be ready for grading and other new construction.

c. “Demolition” means removal, whether in whole or in part, of existing human-made construction, such as removal of buildings, structures, and building systems; site work (such as pavement, curbs, sidewalks, gutters) and the like; Underground

Facilities; and other existing construction.

d. “Selective removal” means removal of specific trees, shrubs, brush, and other vegetation, whether as shown or indicated in the Contract Documents or as directed at the Site by COR.

e. “Selective trimming” means removal of selected parts of trees, shrubs, brush, and other vegetation, performed by arborist, for the purpose of either: (1) allowing installation of new construction adjacent to or through the tree, shrub, brush, or vegetation, or )2) removing damaged or unhealthy growth, to allow balance of the subject tree, shrub, brush, or vegetation to continue normal, healthy growth.

WICA - 245889 & 246063 31 10 00 - 2

f. “Site clearing” means all the Work required by this Section and related Drawings.

g. “Topsoil” means existing material at the Site, visible after clearing and grubbing, to be stripped, when such material is friable, clay loam, surface soil present in depth of not less than four inches. Topsoil shall be free of subsoil, clay lumps, stones, and other objects over two-inch diameter and other objectionable material.

Topsoil required for planting and landscaping Work in the Specifications of

Division 32 may differ from the meaning indicated in this Section.

B. Reference Standards:

1. ASTM International (ASTM):

a. C700, Standard Specification for Vitrified Clay Pipe, Extra Strength, Standard

Strength, and Perforated.

b. D448, Standard Classification for Sizes of Aggregate for Road and Bridge

Construction.

2. American National Standards Institute (ANSI):

a. A300, Standard for Tree Care Operations – Tree, Shrub, and Other Woody Plant

Maintenance – Standard Practices.

3. International Society of Arboriculture (ISA):

a. Container Rootball Shaving.

b. Crown Correction.

c. Balled and Burlapped Root Correction.

d. Container Root Correction.

e. High Branched Crown Observation.

f. Low Branched Crown Observation.

g. Multiple Low Branches Crown Observation.

h. Balled and Burlapped Root Observation.

i. Container Root Observation - Tree.

j. Protection Maintenance.

1.3 QUALITY ASSURANCE

PART 2 - PRODUCTS

2.1 MATERIALS

A. Tree Wound Dressing:

1. Provide tree wound dressing, waterproof, adhesive and elastic with an antiseptic, free from kerosene, coal tar, creosote, and other material injurious to life of tree or other plant.

B. For other materials needed for site clearing Work, such as stone, topsoil, or other, comply with requirements of the Contract Documents.

WICA - 245889 & 246063 31 10 00 - 3

PART 3 - EXECUTION

3.1 SITE CLEARING – GENERAL

A. Limits of Site Clearing Work:

1. Limits of site clearing Work are shown and indicated on the Drawings.

2. Perform site clearing Work for all Work areas unless otherwise shown or indicated in the

Contract Documents. Do not perform site clearing Work outside the limits of the areas required for new construction.

B. General Provisions for Site Clearing:

1. Contractor shall provide all labor, materials, equipment, tools, services, and incidentals necessary and required to perform site clearing Work in accordance with the Contract

Documents.

2. Perform site clearing Work to avoid creating nuisances, pollution, and preventable adverse effects on the environment.

3. Comply with Division 01, and this Section’s Article, “Tree Protection, Selective

Removals, and Selective Trimming”.

4. Excavation required for site clearing shall comply with Section 31 20 01 - Earth Moving

Section 31 23 33 - Trenching and Backfilling.

5. Requirements of Authorities Having Jurisdiction:

a. Perform site clearing Work in accordance with Laws and Regulations.

b. Obtain, pay for, and comply with permits required for site clearing Work. Obtain from Authorities Having Jurisdiction and furnish copy of each permit as a

Submittal.

6. Traffic Control:

a. Where site clearing Work is along or adjacent to travelled ways subject to public traffic, comply with Division 01 and Drawings.

b. Establish such controls prior to and maintain in place throughout site clearing

Work that has potential to affect traffic.

7. Site clearing Work shall comply with ANSI A300 and applicable ISA standards indicated in this Section’s “References” Article, unless the Contract Documents indicate more-stringent requirements.

3.2 PREPARATION

A. Permits and Approvals:

1. Do not commence site clearing Work until necessary permits and approvals are obtained and copies furnished to COR as Submittals.

B. Delineation of Limits of Site Clearing Work Areas:

1. Locate and clearly flag at the Site:

a. Limits of site clearing Work.

WICA - 245889 & 246063 31 10 00 - 4

b. Trees, shrubs, vegetation, and other materials to remain within limits of site clearing Work.

c. Trees, shrubs, and other vegetation to be selectively trimmed.

d. Trees, shrubs, and vegetation to be selectively removed.

2. Flagging:

a. Flagging shall be high-visibility type. Where necessary, provide lath or stakes driven into the ground, with flagging, to clearly delineate limits.

b. Provide different-colored flagging for each type of delineation required by this

Article.

c. Promptly replace lost, moved, or destroyed flagging until COR concurs that flagging is no longer needed.

3. Review with COR:

a. Before starting site clearing Work, other than flagging, review at the Site with

COR.

b. Make corrections as necessary.

c. Review all trees, 6-inch diameter (measured one foot above ground) and larger, to be removed or selectively trimmed.

d. Review with COR at the Site trees and shrubs to be selectively trimmed, to reach mutual agreement on extent of selective trimming required.

C. Protection: Establish protection of trees, shrubs, and vegetation to remain, in accordance with this Section’s Article, “Tree Protection, Selective Removals, and Selective Trimming”, and other applicable provisions of the Contract Documents.

D. Temporary Erosion and Sediment Controls:

1. Provide applicable temporary erosion and sediment controls before commencing clearing and grubbing and topsoil stripping Work.

2. Comply with temporary erosion and sediment control requirements.

3. Continue providing temporary erosion and sediment controls as clearing and grubbing and topsoil stripping and stockpiling Work progresses into previously uncleared, ungrubbed areas of the Site.

3.3 CLEARING AND GRUBBING

A. Clearing and Grubbing – General:

1. Remove and dispose of all materials constituting clearing and grubbing Work within limits shown and indicated in the Contract Documents.

2. After grubbing Work is complete, properly fill holes resulting from grubbing before commencing site grading Work.

B. Trees and Shrubs Improperly Destroyed or Damaged:

1. Refer to this Section’s Article, “Tree Protection, Selective Removals, and Selective

Trimming”.

C. Trees and Shrubs to Remain:

WICA - 245889 & 246063 31 10 00 - 5

1. Trees and shrubs to remain shall be protected, and trimmed where necessary or required, in accordance with this Section’s Article, “Tree Protection, Selective Removals, and

Selective Trimming.”

3.4 TREE PROTECTION, SELECTIVE REMOVALS, AND SELECTIVE TRIMMING

A. General Provisions for Tree Protection, Selective Removals, and Selective Trimming:

1. Provide temporary fencing, barricades, or guarding measures, as recommended by arborist, outside drip line of trees and shrubs to remain.

2. Protect root systems from damage caused by noxious materials, storm water runoff, site clearing, planting and landscaping, other Work, and storage of materials and equipment.

Protect root systems from flooding, erosion, and excessive wetting resulting from dewatering of excavations, drainage of tanks, and other construction activities.

3. Fires are not allowed under or adjacent to trees, shrubs, and other vegetation to remain.

4. Do not store matter resulting from site clearing or demolition, topsoil, or other excavated material within drip line of trees and shrubs to remain. Vehicles are not allowed within drip line. Restrict foot, vehicle and equipment traffic to prevent compaction of soil over root systems. Where such activities are unavoidable, and only as acceptable to COR, provide temporary, continuous, heavy-duty wood planking effectively fastened together and capable of distributing loads from such activities. Temporary planking shall be underlaid by layer of filter fabric covered with two-inch layer of gravel.

5. Cut branches and roots, when necessary, with sharp pruning instruments; do not break or chop. Fully paint cuts 1/2-inch and larger in size with tree wound dressing.

B. Excavation and Protection of Trees and Shrubs:

1. Excavate within drip line of trees only where shown.

2. Where trenching for utilities is required within drip line, tunnel under or around main lateral feeder roots by drilling, auger boring, pipe jacking, or digging by hand under supervision of arborist. Do not cut main lateral roots or tap roots; cut smaller roots, which interfere with installation of the Work.

3. Where excavation for the Work is required within drip line of trees or shrubs, hand excavate to minimize damage to root systems. Perform excavation under supervision of arborist. Provide temporary shoring or other protective support systems at excavations, to minimize sloping and benching of excavations. Use narrow tine spading forks and comb excavated material to expose roots.

4. Relocate roots in backfill areas wherever possible. If large, main lateral roots are encountered, expose beyond excavation limits as required to bend and relocate without breaking. If encountered immediately adjacent to location of construction and relocation is not practical, cut roots approximately three inches back from construction.

5. Do not allow exposed roots to dry out before permanent backfill is provided; provide temporary earth cover. Water and maintain in moist condition and temporarily support and protect from damage until permanently relocated and covered with earth.

C. Grade Adjustments and Tree Protection:

1. Maintain existing grade within drip line of trees, unless otherwise shown or indicated.

2. Lowering of Preconstruction Grade:

WICA - 245889 & 246063 31 10 00 - 6

a. Where required finish grade is below preconstruction grade around trees and shrubs, grade beyond drip line. Maintain preconstruction grade within drip line of trees and shrubs.

b. Prune tree and shrub roots exposed during grade lowering, or provide permanent protections as recommended by arborist. Do not cut main or lateral roots or tap-roots; cut only smaller roots.

c. Compensate for loss of roots and prune branches to stimulate root growth.

d. Provide extended service through completion of the Contract correction period as recommended by arborist.

3. Minor Fills:

a. Where preconstruction grade is six inches or less below elevation of finish grade shown, fill with topsoil complying with quality requirements of Specifications for finish grading and landscaping.

b. Place in single layer and do not compact.

c. Hand-grade to required finish elevations.

D. Tree and Shrub Pruning (Selective Trimming):

1. Perform pruning and selective trimming under the supervision of arborist.

2. Remove branches from trees and shrubs to remain only after COR’s concurrence, only to extent necessary to clear location of permanent construction, using branch removal methods in accordance with ANSI A300 and applicable ISA standards indicated in this

Section’s “References” Article.

3. Extend pruning operation to restore natural shape of entire tree or shrub where pruning is approved by COR.

4. Prune branches to balance loss to root system caused by damage or cutting of root system.

5. Chip branches removed from trees and shrubs. Stockpile and spread chips as directed by

COR.

E. Selective Trimming:

1. In addition to pruning (as required above), perform other selective trimming under direction of arborist.

2. Comply with ANSI A300 and applicable ISA standards indicated in this Section’s

“References” Article.

3. Where shown or indicated, and as directed by COR with arborist’s recommendation, carefully remove larger branches, when necessary, using appropriate methods.

4. Repair cut branches in accordance with this Section.

5. During selective trimming, avoid damaging healthy (to remain) elements of trees and shrubs.

6. Dispose of trimmings as indicated in this Section’s “Disposal and Cleaning” Article.

F. Selective Removals:

1. Perform selective removals under direction of arborist.

2. Comply with ANSI A300 and applicable ISA standards indicated in this Section’s

“References” Article.

3. Fully remove trees and shrubs shown or indicated for selective removal.

4. Remove stumps to…

This is the start of the file's text. The full file is on GovTribe.