Gulf Islands National Seashore Gulf Breeze Fl.
STATEMENT OF WORK:
Perform Tram Operations in the Ft Pickens Area.
DATED:
04/05/23
NATIONAL PARK SERVICE
INTERIOR REGION 2 SOUTH ATLANTIC GULF
CONTRACTING OFFICE WEST
FORT PICKENS TRAM OPERATIONS
SOL # 140P5223Q0027
SOW Format
1. Background
2. Objectives
3. Place of performance
4. Period of performance
5. Scope
6. Tasks
7. Deliverables
8. Government-Furnished Property (GFP)
9. Safety
10. Security Considerations
11. Travel
12. Special Material Requirements
13. Other Unique Requirements and Considerations
14. Quality Assurance Requirement
15. Project Personnel
1. BACKGROUND
This contract is to provide visitor tram operations within the Ft Pickens area.
2. OBJECTIVES:
The scope of this work will include operating the visitor tram engine and cart in the Ft Pickens area of Gulf Islands National Seashore.
3. PLACE OF PERFORMANCE:
The work will be performed at:
Ft Pickens area of the national seashore.
4. PERIOD OF PERFORMANCE:
All tasks and deliverables for this contract must be completed within 30 days after Notice to proceed. Days listed herein refer to calendar days. The primary and approved work schedule is Tuesday and Wednesdays between the hours of 9 am to 1 pm and Saturdays between the hours of 9 am and 5 pm. Any days or hours outside the primary work schedule must be requested 48 hours in advance and approved by the COR.
5. SCOPE:
All tasks will provide an operator to provide visitor tram operations on the indicated days/times of operation. Stops will include Ft Pickens passenger ferry dock, Ft Pickens Campground Store parking lot, Langdon Beach (Saturdays only) and Battery Worth (Tuesday and Wednesday only). Trams will be stored in Battery Langdon. NPS staff will provide training necessary for proper operations.
6. TASKS:
Under this contract, the contractor shall complete the following tasks and requirements:
• Provide a CDL licensed operator each day of the schedule
• Perform visible inspections of the trams involving NPS staff if repairs are needed.
7. DELIVERABLES:
• Provide visitor tram operations three days per week following the proposed schedule.
• Perform inspections of tram vehicles and engines and involve NPS staff if repairs are necessary.
• Adhere to all NPS safety requirements for tram operations.
8. GOVERNMENT-FURNISHED PROPERTY, MATERIAL, EQUIPMENT, OR INFORMATION
(GFP, GFM, GFE, OR GFI):
• NPS owned electric trams.
9. SAFETY:
This contractor is to follow at a minimum all OHSA rules and procedures. Contractor must:
1. Provide a safe and healthful workplace for all employees while on NPS site.
2. Provide a safety plan outlining your safety program specific to this site.
3. Provide a level of public safety commensurate with exposure at NPS worksite.
4. Comply in rectifying all unsafe or unhealthful conditions called to his attention by the contracting officer representative.
5. Allow for informal and formal, announced and unannounced safety inspections by the COTR and the appropriate safety officer at the worksite.
6. Submit an acceptable documented safety plan before beginning work.
10. SECURITY:
N/A.
11. TRAVEL:
Contractor shall be responsible for all travel related expenses for this project, including mobilization of equipment, tools, materials, manpower, lodging, meals, and per diem.
12. SPECIAL MATERIAL REQUIREMENTS:
N/A.
13. OTHER UNIQUE REQUIREMENTS:
• CDL licensing requirements
14. QUALITY ASSURANCE REQUIREMENT:
The government will periodically evaluate the contractor’s performance in accordance with the statement of work. All new equipment must conform to the manufacturer’s instructions and guidelines for installation and start-up.
While performing work, the contractor shall comply with the latest applicable versions of the following:
• NFPA 101 (National Fire Protection Association's Life Safety Code)
• Federal, State and Local Building Codes, Standards and Policies
• Occupational Safety and Health Administration (OSHA) requirements
15. PROJECT PERSONNEL:
Contracting Officer:
Andre Ward West MABO 1801 Gulf Breeze Parkway Gulf Breeze Fl.
Telephone: 850-934-2614-O-850-232-4630-C Email: andre_ward@nps.gov
Proposed COR:
RW Jenkins
GUIS
1801 Gulf Breeze Parkway Gulf Breeze Fl.
Telephone: 850-934-2610 Email: r_w_jenkins@nps.gov
| 1. Background |
| 2. Objectives: |
| 3. Place of Performance: |
| 4. Period of Performance: |
| 5. Scope: |
| 6. Tasks: |
| 7. Deliverables: |
| 8. Government-Furnished Property, Material, Equipment, or Information (GFP, GFM, GFE, or GFI): |
| 9. SAFETY: |
| 10. Security: |
| 11. Travel: |
| 12. Special Material Requirements: |
| 13. Other Unique Requirements: |
| 14. Quality ASSURANCE Requirement: |
| 15. Project Personnel: |