SCOPE OF WORK
TITLE: Remove Replace Various Signs, CCSFS
PROJECT NUMBER: DBEH 22-1621
DATE: 06-Aug-2021
REVISION: 01
Primary Points of Contact
TITLE NAME Telephone
Number
Email Address
45 CES Project
Manager (PM) Eulice Curington 467-2945 eulice.curington.1.ctr@spaceforce
.mil
45 CES
Alternate PM Timothy Nutter 853-0920 timothy.nutter.1@spaceforce.mil
Facility
Manager N/A
1.0 Project Scope
The purpose of this scope of work is to provide a general overview of work to be accomplished to remove/replace signs for various locations on CCSFS to reflect changes from United States
Air Force to United States Space Force. The contractor is to provide the design, fabrication and installation of three hundred sixty (360) new various signs, as per the Unified Facility Criteria
(UFC) 3-120-01 and USSF Logo Guidelines – 6.29.20 for type, font & color scheme. The contractor is to remove and dispose of three hundred sixty (360) existing various signs.
1.1 Provide three hundred sixty (360) various new signs:
1.1.1 One hundred ninety two (192) facility number signs, ten (10) facility nomenclature signs, thirty eight (38) facility road signs, and twenty (20) “Launch Shelter” signs, at the following locations:
Facility Signs
Facility No. BIG Grid Facility Number Facility Nomenclature Facility Road
Launch Shelter
01068 L1 2 1 0 0
91923 L1 2 0 0 0
90313 L1 1 0 0 0
90312 L1 1 0 0 0
90314 L1 1 0 0 0
90328 L1 0 1 0 0
90320 L1 0 1 0 0
90318 L1 1 0 0 0
85306 L1 1 0 0 0
85307 L1 1 0 0 0
85308 L1 1 0 0 0
81730 K1 3 0 0 0
85010 K1 1 0 0 0
85110 K1 2 0 0 0
85125 K1 4 0 0 1
85126 K1 1 0 0 0
FA252122QA016
PROJECT NUMBER: DBEH 22-1621
DATE: 06-Aug-2021
REVISION: 01
Facility Signs
Facility No. BIG Grid Facility Number Facility Nomenclature Facility Road
Launch Shelter
81550 K1 1 0 1 1
81571 K1 1 0 0 0
81570 K1 1 0 0 0
81551 K1 1 0 0 0
81557 K1 1 0 0 0
81565 K1 2 0 0 0
81573 K1 2 0 0 0
81559 K1 1 0 0 0
81900 K1 1 0 0 2
81902 K1 2 0 0 0
78150 J1 2 0 1 0
72910 I1 2 0 0 1
01048 I1 2 0 0 0
66505 H1 2 0 1 0
50166 H2 1 0 1 0
50216 H2 2 0 0 0
50210 H2 2 0 0 0
50211 H2 0 1 0 0
27220 H2 0 0 1 2
50012 H2 4 0 1 0
50013 H2 1 0 0 0
39762 H2 1 0 1 0
39776 H2 1 0 0 0
39774 H2 1 0 0 0
39773 H2 1 0 0 0
39768 H2 1 0 0 0
44200 G1 2 0 1 0
44205 G1 2 0 0 0
44211 G1 1 0 0 0
10905 G2 1 0 1 0
01663 G2 1 0 1 0
34500 G2 2 0 0 0
60701 !A 3 0 1 1
60705 IA 2 1 1 1
60723 IA 2 0 0 0
01794 IA 2 0 0 0
60302 IA 1 0 0 0
60306 IA 2 0 0 0
60305 IA 1 0 0 0
54938 IA 3 0 1 0
54800 IA 1 0 1 0
01728 IA 4 0 1 0
PROJECT NUMBER: DBEH 22-1621
Facility Signs
Facility No. BIG Grid Facility Number Facility Nomenclature Facility Road
Launch Shelter
54928 IA 2 0 0 0
54927 IA 2 0 0 0
54939 IA 0 1 0 0
01739 IA 2 0 1 1
54935 IA 2 0 0 0
01744 IA 2 0 1 1
49535 IA 2 0 0 0
01759 IA 2 0 0 0
54816 IA 1 0 0 0
54814 IA 1 0 0 0
49536 IA 2 0 0 0
01723 IA 2 0 1 0
01704 IA 5 0 1 1
60600 IA 4 0 1 0
60740 IA 2 0 1 1
60748 IA 2 0 0 0
60709 IA 3 0 1 0
01708 IA 3 0 1 1
01711 IA 2 0 1 0
01714 IA 1 0 0 0
01722 IA 4 0 1 1
49634 IA 2 0 1 0
44401 IA 1 0 0 0
44410 IA 1 0 1 1
44414 IA 1 0 0 0
01641 IA 2 0 1 1
01645 IA 2 0 2 1
44440 IA 2 0 0 0
01646 IA 2 0 0 0
44524 IA 1 0 0 0
49750 IA 1 0 1 1
01621 IA 3 0 1 0
01619 IA 2 0 1 0
49841 IA 3 0 0 0
01625 IA 2 1 0 1
01604 IA 5 0 1 0
01603 IA 2 0 0 0
01605 IA 2 1 1 0
01607 IA 2 0 0 0
01637 IA 2 0 0 0
49760 IA 1 0 0 0
44600 IA 3 1 0 0
PROJECT NUMBER: DBEH 22-1621
DATE: 06-Aug-2021
REVISION: 01
Facility Signs
Facility No. BIG Grid Facility Number Facility Nomenclature Facility Road
Launch Shelter
44633 IA 1 0 0 0
44645 IA 2 0 1 0
49915 IA 4 0 1 0
49941 IA 2 0 0 0
01610 IA 2 0 0 0
55383 IA 2 0 0 0
55384 IA 1 0 0 0
15730 F2 2 0 1 0
01664 F2 0 1 0 0
1.1.2 Seventy two (72) street signs:
Street Name No. Signs
Phillips Pkwy 27
Poseidon Ave 2
S. Patrol Rd 2
Pier Rd 2
Lighthouse Rd 7
Mission Control Rd 4
Flight Control Rd 3
Skid Strip Rd 3
Mercury/Gemini Rd 2
Central Control Rd 3
Armory Rd 1
ICBM Rd 2
Titan III Rd 1
Test Rd 1
MSA #5 Rd. 3
Industry Rd. 4
Scrub Jay Rd. 1
Hangar Rd 2
SAB Rd 2
1.1.3 Twenty eight (28) miscellaneous signs:
Sign Location Sign Type QTY
South Gate; St Rd 401; Westbound, Facing Eastbound
Road Sign; "Work Safely Today, And, Be Back Tomorrow" 1
PROJECT NUMBER: DBEH 22-1621
Sign Location Sign Type QTY
South Gate; W of 1068 Road Sign; "Cars Keep Left…" 1
South Gate; E of 91923 Road Sign; "Military Port" "Space Florida" x2 3
South Gate; Badge Check Station; 90320 Wall Sign; "Hands on Badge Check" 2
Phillips Pkwy; Northbound; S of S Patrol Rd Road Sign; "Military Port" 1
MOC; Parking Lot Parking Bumpers; "O-6" 4
MOC; Parking Lot Parking Sign; " GOV Parking" 2
Phillips Pkwy; Southbound; N of 81701 Road Sign; "NOTU Headquarters" "SLC 25, 29" 1
Phillips Pkwy; Northbound; S of Pier Rd Road Sign; "NOTU Headquarters" "SLC 25, 29" 1
Phillips Pkwy; Northbound; S of Lighthouse Rd
Road Sign; "Air Force Museum, 1.5 mil" 1
Phillips Pkwy; Next to 78150 Road Sign; "Museum Visitors, Exit Route" 1
Phillips Pkwy; Northbound; E of 60701 Road Sign; "Kennedy Space Center, CCAFS Airfield, etc." 1
Skid Strip Rd; Eastbound; Entrance to Airfield
Road Sign/Facility Sign; "CCAFS" 1
Central Control Rd; Eastbound; Armory Rd. "Road Sign; "Weather Station, CCAFS Landfill" 1
Command & Control; Perimeter Fence Fence Sign; "Former Waste Disposal Site…" 1
Phillips Pkwy; Southbound; @ FSA 1 Facility Road Sign; "FSA 1" 1
Phillips Pkwy; Northbound; MSA 5 Rd. Facility Road Sign; "MSA 5" 1
LCX 37 Facility Road Sign; "CX 37…" 1
NASA Causeway; West of Boundary Gate Road Sign; "45th SW Regulations…" 1
Industry Rd; Eastbound; East of NASA Boundary
Road Sign; "Attention, Commercial Deliveries…" 1
Phillips Pkwy; Northbound; Near Hangar K Road Sign; "A.F. Launch Viewing; Kennedy Space Center" 1
1.2 Background
1.2.1 Patrick Air Force Base, Cape Canaveral Air Force Station and all outlying annexes and associated installations have been designated to fall under the United States
Space Force, thus all signs must be re-designated to reflect the change
1.3 Special Instructions
1.3.1 All sign types (facility number, facility road, etc.) must be uniform in appearance and constructed of like material to existing signage, except in regards to color as outlined in USSF Logo Guidelines – 6.29.20
1.3.2 All verbiage on new signs must mirror verbiage on existing signs, except in the case of reference to USAF organizations. Contractor will work closely with government representative to determine new organizational naming conventions (i.e. 45 OG, 45
CES, etc) prior to sign construction.
PROJECT NUMBER: DBEH 22-1621
1.3.3 Delta and/or organizational insignia will no longer be included on any sign
1.3.4 Coordinate with government representative for verbiage on new “Launch Shelter” signs, as it may differ between facilities.
1.3.5 Some work to be performed will require contractor to access restricted areas within
CCSFS. Coordinate with government representative if security escort is required.
1.3.6 Regarding facility road signs & any miscellaneous signs that require a frame independent of a facility, frame must be replaced with black aluminum in the same location and installation method as existing. Coordinate all digging activities with government representative as contractor will require an AF103 & dig permit.
1.3.7 Prior to disposal of any signs, contractor will coordinate with the Project Manager to determine if any signs will be retained by the government for historical record.
2.0 Applicable Documents:
2.1 Department of Defense’s Quality Service Manual version 5.1 (DoD QSM 5.1)
2.2 UFC 3-120.01, Design: Sign Standards, With Change 3
2.3 USSF Logo Guidelines – 6.29.20
3.0 Requirements
4.0 Project Management
4.0 Deliverables
4.0.1 Material Submittals
4.0.2 Project Schedule
4.1 Project Schedule and Milestones
4.1.1 Period of Performance:
5.0 Service Summary
PROJECT NUMBER: DBEH 22-1621
6.0 GOVERNMENT FURNISHED PROPERTY AND SERVICES
6.0 Government Furnished Property. None.
6.1 Government Furnished Supplies and Equipment. None.
7.0 GENERAL INFORMATION
7.0 Hours of Operation. The contractor shall perform the services required under this contract during the following hours. The contractor is not required to perform services on Federal Holidays. All work to be performed off-site
7.1 Normal Base Hours. Base hours of operation are 0700 to 1700 hrs. Monday through
Friday. The Contractor may find it necessary to deviate from the normal base hours of operation, to ensure timely completion of work under this PWS at no additional cost to the government. All work to be performed off-site
7.2 Federal Holidays.
New Year’s Day
Martin Luther King Day
Washington’s Birthday
Memorial Day
Juneteenth
Independence Day
Labor Day
Columbus Day
Veteran’s Day
Thanksgiving Day
Christmas Day
If these holidays fall on Saturday, the preceding Friday will be observed. If these holidays fall on Sunday, the following Monday will be observed. If a holiday falls on a scheduled service day, the Contractor will be responsible for rescheduling services for the first day post the holiday observance. All work to be performed off-site
7.3 Base Closures. Work scheduled but not accomplished because of base closure due to weather, exercises, or actual alert, will be accomplished as soon as possible after reopening the base. All work to be performed off-site
7.4 Contractor/Employee Base Pass and Identification, Special Clearances and
PROJECT NUMBER: DBEH 22-1621
Vehicle Passes. The contractor shall comply with all requirements and procedures
IAW AFFAR 5353.242-9000, Contractor Access to Air Force Installations. All documentation shall be submitted at the pre-performance conference. All work to be performed off-site
7.5 Traffic Laws. The Contractor and its employees shall comply with base traffic regulations. All work to be performed off-site
7.6 Weapons, Firearms, and Ammunition. Contractor employees are prohibited from possessing weapons, firearms, or ammunition, on themselves or within their
Contractor-owned or privately owned vehicle while on Patrick Air Force Base. All work to be performed off-site
7.7 For Official Use Only (FOUO). The Contractor shall comply with DoD 5400-7-R, Chapter 4, DoD Freedom of Information Act (FOIA) Program requirements. This regulation sets policy and procedures for the disclosure of records to the public and for marking, handling, transmitting, and safeguarding FOUO material.
7.8 Schedules. The Contractor shall submit a project schedule of milestones to the
Contractor Officer within ten-business days of notice to proceed.
7.9 Safety Requirements and Reports. The contractor shall perform work in a safe manner as required by OSHA Safety and Health Requirements. Provide a verbal report to the CO as soon as possible of each occurrence of damage to Government property or an accident resulting in death, injury, occupational disease, or adverse environmental impact. Provide a completed copy of required Accident Investigation
Reports to the CO within five calendar days of each occurrence.