This document includes a draft statement of work and pre-solicitation notice for an indoor playground project at Misawa Air Base in Japan. The Department of the Air Force requires the installation of age-separated play zones for children 6-23 months, 2-4 years, and 5-12 years, to include flooring, climbers, structures, and equipment meeting National Program for Playground Safety standards. A site visit will be held on August 26th, with responses due by August 19th. The North American Industry Classification code is 423910 and Product Service Code is 7830. The point of contact is Ms. Tamaki Hunt and SSgt Joshue Madilar at email addresses provided.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 1 – Statement of Work
STATEMENT OF WORK (SOW)
FOR
Install Indoor Playground
BLDG. 1006, MISAWA AIR BASE, JAPAN
August 2022
STATEMENT OF WORK
TABLE OF CONTENTS
SECTION PAGE
1 DESCRIPTION 2
2 GENERAL INFORMATION 2
3 APPENDICES 9
1. DESCRIPTION
The contractor shall provide all management, tools, supplies, equipment, and labor necessary to install an indoor playground and equipment at building 1006 Bay 2, Misawa Air Base, in separated age-specific zones for 6-23 months, 2-4 years and 5-12 years to NPPS and CSPS standards or JPFA equivalent standards.
1.1 BASIC REQUIREMENTS
The contractor is to install purchased items at building 1006 in requested locations.
1.2 INSTALLATION REQUIREMENTS
The contractor shall ensure that items are installed as the end user wishes and are fastened properly so that they will not tip over, fall or injure customers and will remain in place for child play. Items must also be installed as to not damage facility surfaces and structure. Furthermore, the items must clear ceiling sprinkler deflectors as stated in the regulation below. Installation may not take place until current facility items and equipment are relocated by the requiring activity.
DAFMAN 91-203 Para. 2.4.5. Stacking Materials. Refer to Air Force Joint Manual (AFJMAN) 23-210, Joint Service Manual (JSM) For Storage and Materials Handling, for guidance on stacking materials. When materials are stacked to a height less than 15 feet, maintain an 18-inch clearance below ceiling sprinkler deflectors. If the stack is over 15 feet in height, increase the clearance to 36 inches (when only joists, rafters, beams and roof trusses exist, without a ceiling constructed below, a 36 inches clearance will also be required. (T-1) Position all stacks of materials to ensure an 18-inch clearance around light or heating fixtures, or follow the manufacturer‘s instructions, regardless of height.
1.3 OPERATION TEST
Upon completion of the install, the contractor must check the equipment to ensure that it is installed safely as cited in par 1.2.
2. GENERAL INFORMATION
2.1 QUALITY CONTROL
The contractor is responsible for ensuring that the items and services meet the requirements of the contract. Any in-process inspection by the Government shall be conducted in a manner consistent with commercial practice.
2.2 SECURITY REQUIREMENTS
2.2.1 Security and base access requirements are contained in clause 5352.242-9000 “Contractor Access to Air Force Installations.” Contractor employees will be required to obtain and display identification badges. Anticipate delays in getting commercial vehicles on base and allow time for commercial vehicles to reach their destination by driving designated routes at posted speed limits throughout the base. Procedures for commercial vehicle access to the base are subject to change without prior notice. The services to be performed by the contractor during the period of this contract shall at all times and places be subject to review by an authorized representative(s) such as the Site Security Manager(s).
2.2.2 ID Passes, Badges and Vehicle Stickers: The contractor is responsible to obtain such clearances and/or passes as required for his/her employees to enter military installations on Misawa AB prior to start to work. The contractor shall be responsible for all passes issued to his/her employees under this contract. Applications shall be coordinated through the Contracting Officer or designated representative. At the time of application, Security Forces may conduct a background check on employees. Upon termination of employment, the contractor shall be responsible for returning identification cards and base passes to Security Forces within 24 hours.
2.2.3. Entry Authorization Listing (EAL): The contractor may be requested to provide the required information on EAL for entry to Misawa AB restricted areas prior to start of work.
2.3 PHYSICAL SECURITY
The contractor shall be responsible for safeguarding all government property provided for contractor use. At the close of each work period, government facilities, property, and materials shall be secured. The installation contractor will be escorted during installation. The escort shall open / secure locked boxes.
2.4 HOURS OF OPERATION
2.4.1 Normal Hours of Operation. The contractor shall perform the services required under this contract during the following hours: MON-FRI 0730-1630, except federal holidays. The contractor may work, with prior approval of the Contracting Officer and Site Security Manager, extended hours to ensure timely completion of work at no additional cost to the government.
2.4.1.1 Recognized Holidays. The contractor is not required to provide service on the following days:
New Year's Day 1 January Martin Luther King's Birthday Third Monday in January President's Day Third Monday in February Memorial Day Last Monday in May
Juneteenth Day 20 Jun Independence Day 4 July Labor Day First Monday in September Columbus Day Second Monday in October Veterans' Day 11 November Thanksgiving Day Fourth Thursday in November Christmas Day 25 December
If the holiday falls on Saturday, it is observed on Friday. If the holiday falls on a Sunday, it is observed on Monday.
2.5 CONSERVATION OF UTILITIES
The contractor shall instruct employees in utilities conservation practices. The contractor shall be responsible for operating under conditions which prevent the waste of utilities which include the following:
2.5.1 Lights shall be used only in areas where and when work is actually being performed.
2.5.2 Mechanical equipment controls for heating, ventilation, and air conditioning systems shall not be adjusted by the contractor or by contractor employees unless authorized.
2.5.3 Water faucets or valves shall be turned off after the required use has been accomplished.
2.5.4 Government telephones shall be used only for official government business.
2.6 RECORDS
The contractor shall be responsible for creating, maintaining, and disposing of only those government required records that are specifically cited in this SOW. If requested by the Government, the contractor shall provide the original record or a reproducible copy of any such record within five working days of receipt of the request.
2.7 ENVIRONMENTAL CONTROLS
2.7.1 Compliance with Laws and Regulations. The contractor shall be knowledgeable of and comply with all applicable Japan Environmental Governing Standards (JEGS), and requirements regarding environmental protection. In the event environmental laws/regulations change during the term of this contract, the contractor is required to comply as such laws come into effect. If there is an increase or decrease in cost as a result of the change, the contractor shall inform the Contracting Officer pursuant to notice requirements and negotiate a modification to the contract.
2.7.2 Notification of Environmental Spills. If the contractor spills or releases any substance contained in 40 CFR 302 into the environment, the contractor or its agent shall immediately report the incident to Misawa AB Fire Dept at 911. The liability for the spill or release of such substances rests solely with the contractor and its agent.
2.7.3 Material Storage and Use. The contractor shall follow manufacturer’s guidelines and professional recommendations for control of humidity, temperature, cleanliness, and materials handling. This includes hazardous materials.
2.7.4 The walls in Bay 2 at 1006 contain asbestos and items may not be installed on/in the walls requiring puncturing the material and thus abatement.
2.8 GOVERNMENT OBSERVATIONS
Government personnel, other than Contracting Officers (COs) may from time to time, with CO coordination, observe contractor operations. However, these personnel may not interfere with contractor performance or make any changes to the contract.
2.9 SAFETY REQUIREMENTS
In performing work under this contract, the contractor shall:
2.9.1 Conform to the safety requirements contained in the contract for all activities related to the accomplishment of the work including the National Program for Playground Safety Regulations, U.S Consumer Product Safety Commission ATSM International or equivalent Japan Parks Facilities Association standards.
2.9.2 Perform work in a safe manner as required by OSHA 2206, General Industry, Occupational Safety and Health Standards (29 CFR 1910) and Japan Environmental Governing Standards (JEGS) by US Force Japan.
2.9.3 Develop and provide at the start of the orientation period or the start of the first operational performance period (if there is no orientation period) a safety plan for the protection of government facilities and property and to provide a safe work environment for contractor personnel.
2.9.4 Provide protection to government property to prevent damage during the period of time the property is under the control or in possession of the contractor.
2.9.5 Include a clause in all subcontracts to require subcontractors to comply with the safety provisions of this contract as applicable.
2.9.6 Record and report promptly (within one hour) to the contracting officer or designated Government Representative (GR), all available facts relating to each instance of damage to government property or injury to either contractor or government personnel.
2.9.7 In the event of an accident/mishap, take reasonable and prudent action to establish control of the accident/mishap scene, prevent further damage to persons or property, and preserve evidence until released by the accident/mishap investigative authority through the contracting officer.
2.9.8 If the government elects to conduct an investigation of the accident/mishap, the contractor shall cooperate fully and assist government personnel in the conduct of investigation until the investigation is completed.
2.9.9 Include a clause in each applicable subcontract requiring the subcontractor's cooperation and assistance in accident reporting and investigation.
2.10. CONTRACTOR PERSONNEL
2.10.1 Contract Manager and/or Contract Employee: the contractor shall provide a contract manager/employee who shall be responsible for the performance of the services. The names of the contract manager/employee shall be provided to the CO in writing prior to the beginning of the performance period. The contract manager/employee must be U.S. SECRET-cleared and able to read, write, speak, and understand English.
2.10.2 The contract manager/employee of contact shall be available during normal duty hours within two (2) hours to meet on the installation with government personnel to discuss problems. After normal duty hours the manager/employee shall be available within four (4) hours.
2.10.3 The contractor shall not employ persons for work on this contract if such employee is identified to the contractor by the CO as a potential threat to the health, safety, security, general wellbeing or operational mission of the installation and its population.
2,10.4 Contractor personnel shall present a neat appearance and be easily recognized as contractor employees. This may be accomplished by wearing distinctive clothing bearing the name of the company or by wearing appropriate badges, which contain the company name and employee name in English.
2.10.5 The contractor shall not employ any person who is an employee of the U.S. Government if employing that person would create a conflict of interest. Additionally, the contractor shall not employ any person who is an employee of the Department of the Air Force, either military or civilian, unless such person seeks and receives approval according to DOD 5500-7-R Joint Ethics Regulation. The contractor shall not employ any person who is an employee of the Department of the Air Force if such employment would be contrary to the policies in AFI 64- 106.
2.10.6 The contractor is cautioned that off-duty active military personnel hired under this contract may be subject to permanent change of station, change in duty hours or deployment.
Military Reservists and National Guard members may be subject to recall to active duty. The abrupt absence of these personnel could adversely affect the contractor’s ability to perform;
however, their absence at any time shall not constitute an excuse for nonperformance under this contract.
2.11 JAPANESE ROAD LAWS
2.11.1 The contractor should have an international driver’s license and shall comply with Japanese Road Laws while on US Military installations to specifically include: Article 43 The Road Law (Japan) (prohibited acts relative to roads). No person shall commit the following described acts:
2.11.1.1 Damaging the road, causing roads to be littered with debris, polluting the roads with debris or fallout from motor vehicles or otherwise defacing roads unreasonably or without due cause.
2.11.1.2 Article 43-2 (Measures to be taken to prevent cargo or things loaded on motor vehicles from falling out)
2.11.2 The agency managing a road may when there is reasonable cause for him to feel that items or cargo being carried in or on a motor vehicle may fall out and damage, pollute, or otherwise deface the road in such manner as to hinder or obstruct the traffic, order the operator of the vehicle in question to take steps or measures necessary to prevent occurrence of such hindrance by stopping operation of the vehicle, or correcting the method of loading or traveling or operation of the vehicle.
2.12 REQUIRED INSURANCE by JAPANESE LAW
2.12.1 The Contractor shall procure and maintain during the entire period of his performance under this contract the following minimum insurance on each vehicle used by the Contractor at the work site.
2.12.2 Type: Automobile Property Damage Insurance Amount: ¥3,000,000 or Dollar equivalent Bodily Injury Insurance Amount: ¥30,000,000 or Dollar equivalent.
2.12.3 All vehicles must be properly inspected/insured in accordance with Japanese Compulsory Insurance (JCI) requirements.2.13
2.12.4 Prior to the commencement of work hereunder, the Contractor shall furnish to the Contracting Officer a certificate or written statement of the above required insurance. The policies evidencing required insurance shall contain an endorsement to the effect that cancellation or any material change in the policies adversely affecting the interests of the U.S.
Government in such insurance shall not be effective for such period as may be prescribed by the laws of the state in which this contract is to be performed and in no event less than thirty (30) days after written notice thereof to the Contracting Officer.
2.13 RESTRICTION OF MOVEMENT (ROM) REQUIREMENT
Contractor(s) from outside of Japan shall comply with the current Misawa AB ROM requirements. To prevent potential COVID-19 transmission, the 35 FW commander has taken measures and implemented ROM procedures for visitors from outside of Japan, who arrive in Japan within 14 days or less prior to accessing Misawa Air Base. Therefore, visitors to Misawa Air Base must follow the latest directive as provided in the 35 FW Crisis Action Team Directive (CATD). The Directive is available at https://www.misawa.af.mil/COVID-19-Information/.
2.14 MEDICAL INSURANCE FOR VISITORS
All visitors to Misawa Air Base other than Japanese national will be required to obtain health insurance coverage for medical care and aeromedical transport while in Japan, and submit a copy of the insurance, photocopy of passport and vehicle information (Japanese compulsory inspection, liability insurance, international driver’s license, etc.) if driving, to the Government for the request of the base pass.
2.15 LOGISTICAL SUPPORT
DFARS Clause 252.225-7976 "Contractor Personnel Performing in Japan." (DEVIATION 2018- O0019) applies to this contract. Applicable references include USFJ Instruction 64-100, the full text of this clause, and USFJ Form 27.
2.15.1 In summary, this requires contractors desiring to acquire status under Article 1(b) of the Status of Forces Agreement (SOFA) between Japan and the United States as members of the civilian component, to be registered via the Synchronized Pre-Deployment and Operational Tracker (SPOT), in addition to any contractor personnel performing work under this contract in Japan. Link:
https://spot.dmdc.mil/privacy.aspx
2.15.2 A Letter of Authorization (LOA) is required to be completed by the contractor in SPOT for each person performing work under this contract. This LOA MUST be completed (via approval from a base CO) prior to the departure of SOFA-covered contractor personnel. Consequences of not completing the LOA include being turned around by Japanese customs upon arrival into the country.
2.15.3 Depending on the scope of the contract, logistical support MAY be authorized by the installation commander, for items mentioned below (see DFARS Clause 252.225-7976(b)(4) for more information):
(A) Base Exchange, including exchange service stations, theaters, and commissary
(B) Emergency medical care, on a reimbursable basis
(C) Postal support, as authorized by military postal regulations
(D) Local recreation services
2.15.4 Depending on the scope of the contract, logistical support may be authorized by the installation commander, for items mentioned below (see DFARS Clause 252.225-7976(b)(4) for more information):
2.15.5 Logistical support measures will be determined prior to the award of the contract.
2.15.6 Contractors need to input employee information into SPOT for the working of the LOA, IMMEDIATELY AFTER the award of the contract.
2.15.7 A required USFM Form 27, "Contractor Employee Acknowledgement" form must also be completed by the contractor, when applicable.
2.15.8 Please contact the CO for this requirement for more information.
3. APPENDICES
A. Project Location, Route and Floor Plan for Installation (Misawa AB, Japan) B. Defined Requirement
APPENDIX A
1. Project location and route (Misawa AB, Japan) from Main Gate
2. Floor plan
APPENDIX B
Defined Requirement of Indoor Playground, Bldg 1006, Misawa Air Base, Japan
Overview: Provide play zones as required for Misawa Air Base youth with a variety of themes to spark imagination in children and provide indoor activity in cold or rainy weather. The NAFI requests designs follow required National Program for Playground Safety Regulations, U.S Consumer Product Safety Commission ATSM International or equivalent Japan Parks Facilities Association standards. Each zone should house play areas suited to the intellectual abilities, physical capabilities and safety necessities for the age group concerned. The NAFI had no preference as to themes other than those that are appropriate to each age group. For parental oversight, parent and child seating should be provided throughout other than height of fall areas.
Zones should be separated with sloped thresholds. Colors may vary. Company must design, ship and install to the following:
Design Requests
Entrance Zone
1. Stroller Parking: space for minimum of 4 strollers to park at entrance area. Flooring at entrance can remain existing concrete. Optional: Paint on floor to suggest parking area
2. Shoe Cupboard: 7-8 shoe cupboards with a minimum of 4 shelves each to house children and adult shoes prior to play. Preferred height not exceed 4 feet. Width can vary to provide need.
Material preferred: wood, natural or painted, color can vary. Wood should be either naturally rot- and insect-resistant or should be treated to avoid such deterioration. CPSC, Sect 2.5.5.
6-23 Months Zone
1. Gel mat flooring, or similar material, 2 inches in height, tiles or one piece. Must be free of hazardous chemical or materials, must be adhered so that peeling/flaking will not occur.
Material must be shock absorbing.
2. 3-4 different structures/areas of play. This may include but is not limited to interactive play tables, stacking modules, bead mazes, soft crawl and climb sets, 2-4 Years Zone
1. PVC cushion flooring/similar material, 2 inches in height, tiles or one piece.
2. 3-4 different play structures/activities as space allows to include but not limited to play houses, car/animal play structures, tunnels, table play sets, sitting areas, bouncing/rocking play, intellectual play such has puzzle walls or boards.
5-12 Years Zone
1. Gel mat flooring, 2 inch in main area, 3 inch height of fall area, tiles or one piece, see specifics below.
2. No less than 8 foot high climber with 3 inch high flooring surrounding and sloped threshold to main space.
3. Standing platforms, interactive play, large movable intellectual puzzles such as blocks, balance and coordination equipment. Additional structures/ play items as space provides to include but not limited to monkey bars, additional climbing structures.
General Installation Requirements
a) Footing for climber must be poured in place to sub base as per manufacturer installation guidelines for the height of structure and sub base material (concrete). Other footing must be affixed to concrete at appropriate depth per manufacturer installation guidelines.
b) The matting around the climber (requested 8 feet tall) must be 3 feet in depth with shock absorbing properties as noted on the CPSC recommendations chart below for height of fall requirements. National Program for Playground Safety, S.A.F.E. Play Areas, Fall Surfacing, Pg. 110. Max climber height for this facility at the top of the climber is 2299cm or 9.8091 feet, Gmax <200 HIC≦1.000.
c) The use zone at the exit of the slide shall be the vertical distance of the slide plus 4 feet (1.2 meters) but not to exceed beyond 14 feet (4.3 meters) For a slide of 6 feet (1.8 meters) = use zone is 10 feet (3 meters) For a slide of 8 feet (2.4 meters) = use zone is 12 feet (3.7 meters) National Program for Playground Safety, S.A.F.E. Play Areas, Creating Safe Surfaces, Pg.
125 Fig. 6.5
d) Equipment must be stable, installed to specifications and inspected by a certified inspector upon completion of installation prior to acceptance of completed work. If errors in installation are found that do not meet regulations, the contractor must correct errors according to inspector direction.
Other Safety Requirements
1. Hazardous Materials
a) All materials must follow OSHA compliance or Japanese equivalent regulations. No materials listed as chemical hazards and toxic substances as per the United States Department of Labor may be present in the items installed in this playground. See osha.gov/chemical-hazards/standards
Asbestos Notice of Avoidance
a) Installers may not puncture the walls at 1006 during this installation as asbestos is present.
All walls must be avoided during installation.
b) Tripping/Future Hazards
a) All items installed must be adhered and fastened properly so that tripping, cuts, choking, or other injury hazards are not present. All fasteners, connectors, and covering devices should not loosen or be removable without the use of tools. CPSC Sect. 2.52. All items must be installed properly to ATSM standards for soft contained play areas. (atsm.org) Additionally, adhesives/fasteners must be of quality to support wear and tear of daily use and traffic as to not present future hazards. Flooring must not be porous as to hold in bacteria and/or lead to growth of mold.
Fire Sprinkler Deflector Clearance
a) Climber must maintain an 18 inch clearance from ceiling sprinkler deflectors. Please see below regulation:
DAFMAN 91-203 Para. 2.4.5. Stacking Materials. Refer to Air Force Joint Manual (AFJMAN) 23- 210, Joint Service Manual (JSM) For Storage and Materials Handling, for guidance on stacking materials. When materials are stacked to a height less than 15 feet, maintain an 18-inch clearance below ceiling sprinkler deflectors. If the stack is over 15 feet in height, increase the clearance to 36 inches (when only joists, rafters, beams and roof trusses exist, without a ceiling constructed below, a 36 inches clearance will also be required. (T-1) Position all stacks of materials to ensure an 18-inch clearance around light or heating fixtures, or follow the manufacturer‘s instructions, regardless of height.
Entrapment and Entanglement
a) Equipment must not endanger a child with entrapment or entanglement
b) U.S Consumer Product Safety Commission requires openings in surfaces be greater than 3.5 and less than 9 inches. The equipment installed in this facility must meet this requirement.
CPSC, Sect 3.3.1
Maintenance and Warranty
1. The NAFI expects durable, long lasting materials and equipment to be installed professionally and with care to the facility.
2. The NAFI expects a maintenance kit and resources to lifespan maintenance plans.
3. The NAFI seeks a minimum 5 year warranty on furniture parts and smaller items and a lifetime warranty on large climbers, galvanized, stainless steel, and high density polyethylene parts to ensure the longevity of this playground.