This document contains a bid schedule for a duress alarm system installation. The schedule lists Honeywell Vindicator alarm equipment including a Vindicator 1500 or V5 control panel, keypad, balanced magnetic switches, passive infrared sensors, and battery backup to be installed at access points and alarmed areas of Building 1030. It requires labeling, electrical support, removal of unnecessary existing equipment, coordination of programming with the 802nd Security Forces Squadron, provision of area drawings and equipment lists, inspection after installation, warranty support within 24 hours, and AES encryption of transmission lines. Installation must be complete by February 24, 2023.

View the file

Other files for this federal contract opportunity

Other files attached to Duress Alarm, newest first.
File Type Posted
Acth 3 Clause and Provisions.pdf PDF
Acth 2 SOW Lackland ADC Duress Alarm (21 Sep 23).docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table 1

Table 1. Motorcycle Specifications
ModelDescriptionDelivery DateQTYUnit CostAmount
Honeywell Vindicator1.Install Vindicator 1500 or Vindicator V5.
2.Install Vindicator Keypad for entry into (Building number and room number).
3.Install (x) Balanced Magnetic Switch(s) (BMS) and (x)Passive Infrared sensor(s) (PIR) at each access point.
4.Install battery backup lasting no less than 4 hours.
5.Label wiring before and after penetration of perimeter walls of alarmed areas.
6.Install all electrical support requirement for equipment that is not already available. Install dedicate electrical and communication lines from point of debark. Attachment #1 Date: 24 Feb 2023 Page 2 of 5
7.Remove all previous installed components that are identified as unnecessary.
8.Coordinate all programming of the Vindicator system and map of the area(s) with 802 SFS/ESS. All alarm programming at the headend will be conducted by 802 SFS/ESS in coordination with contactor at Building #1030
9.Provide an area drawing that shows all designated alarm points that will be programmed into the base alarm system; this will be reviewed by 802 SFS/Resource Protection and the 802 SFS/ESS during material submittals.
10.Provide a complete list of alarm devices to 802 SFS/Resource Protection and 802 SFS/ESS which will be reviewed during the material submittals. To include make, model, serial number and part number.
11.Coordinate with 802 SFS/ESS for Vindicator alarm point numbers for programming after installation is complete; this will also be provided to 802 SFS/ESS as a hard copy and electronic copy.
12.After installation but before alarm programming, 802 SFS/ESS will conduct an inspection of the installed parts.
13.Ensure each alarm device will have its own alarm point.
14.Provide a plan for a Vindicator certified technician to conduct warranty response within 24 hours from a call requesting warranty support.
15.Ensure all IDS data transmission lines shall be protected with a National Institute of Standards and Testing (NIST) certified Advanced Encryption Standard (AES) encryption.
16.Coordinate with the 802 SFS/ESS on the installation of mounted alarm boxes and fiber cables/Copper pairs prior to installation, or when within 80 percent of completion to ensure correct placement of equipment.1