STATEMENT OF WORK
Building 347 Sustainment Services
1. DESCRIPTION OF SERVICES
The contractor shall provide sustainment services of real property to ensure surface areas around the facilities are maintained to standards.
2. SCOPE OF WORK
Three areas, 1 primary requirement and two optional requirements, require sustainment services of real property to ensure the various areas of the facility are brought up to standards.
2.1 Building 347 Administrative Side, Pope Army Airfield (Primary Requirement). The contractor will remove all objects on the wall, strip all existing paint and textured material on walls, patch up all walls with a smooth consistency, prime wall surfaces, paint the walls, and reattach all previously removed objects. The required surface area is approximately 16480’ cubic ft. All paint will match the Fort Bragg DPW Gray Color Scheme for all interior walls (willow spring), doors & frames (volcanic ash), and ceilings (gypsum). The contractor will move all furniture and objects in each room, remove all existing carpet and trim, prepare all floor surfaces, and install new carpet tiling and trim, and move all furniture and objects back into original locations. The required surface area is approximately 2010’ square footage. The carpet will match the Fort Bragg DPW Gray Color Scheme of Tarkett, Aftermath II 03026, Flannel 23509 (24 x 24) carpet tiles. All construction debris and garbage will be the contractor’s responsibility to remove from the site and dispose of IAW applicable Federal, State, and Local laws and regulations.
2.2 Building 347 SCX Extension Side, Pope Army Airfield (Optional Requirement). The contractor will remove all objects on the wall, strip all existing paint, patch up all walls with a smooth consistency, prime wall surfaces, paint the walls, and reattach all previously removed objects.
The required surface area is approximately 30339’ cubic ft. All paint will match the Fort Bragg DPW Gray Color Scheme for all interior walls (willow spring), doors & frames (volcanic ash), and ceilings (gypsum). The contractor will move all furniture and objects in each room, remove all existing carpet and trim, prepare all floor surfaces, and install new carpet tiling and trim, and move all furniture and objects back into original locations. The required surface area is approximately 3640’ square footage. The carpet will match the Fort Bragg DPW Gray Color Scheme of Tarkett, Aftermath II 03026, Flannel 23509 (24 x 24) carpet tiles. All construction debris and garbage will be the contractor’s responsibility to remove from the site and dispose of IAW applicable Federal, State, and Local laws and regulations.
2.3 Building 347 Network Side, Pope Army Airfield (Optional Requirement). The contractor will remove all objects on the wall, strip all existing paint, patch up all walls with a smooth consistency, prime wall surfaces, paint the walls, and reattach all previously removed objects.
The required surface area is approximately 20455’ cubic ft. All paint will match the Fort Bragg DPW Gray Color Scheme for all interior walls (willow spring), doors & frames (volcanic ash), and ceilings (gypsum). The contractor will move all furniture and objects in each room, remove all existing carpet and trim, prepare all floor surfaces, and install new carpet tiling and trim, and move all furniture and objects back into original locations. The required surface area is approximately 3247’ square footage. The carpet will match the Fort Bragg DPW Gray Color Scheme of Tarkett, Aftermath II 03026, Flannel 23509 (24 x 24) carpet tiles. The contractor will remove all old bathroom stall doors, partitions, bolts, and fastenings from Male and Female restrooms, install new bathroom stall doors, partitions, bolts and fastenings matching the previous layout. The new partitions and doors will abide by DPW 09 06 00 instructions Floor Mounted Overhead Braced with Stainless Steel Shoes and High-Density Polyethylene HPDE and coordinate with tile color. All construction debris and garbage will be the contractor’s responsibility to remove from the site and dispose of IAW applicable Federal, State, and Local laws and regulations.
3. WORK HOURS
3.1 Work shall be performed during normal duty business hours: M-F 7:30am – 4:30pm EST.
3.2 Work shall be done in such as manner as to not interfere with daily communications operations.
Vehicle placement (parking) and movement shall be coordinated with the facility manager to ensure placement does not interfere with normal operations of the Squadron.
3.3 Work shall be completed within a timely manner not to exceed 14 days after projected end date
3.4 The contractor shall coordinate with the Unit Facility Manager, contact info to be provided after award, to coordinate arrangements for base access.
4. SECURITY
4.1 All workers shall be legal U.S. Citizens with valid picture IDs who are able to gain clearance on to the military installation.
4.2 No guns, drugs, or illegal paraphernalia will be authorized on the military installation.
4.3 All vehicles, equipment, and containers may be subject to search at any time while on or seeking access to the military installation.
5. INSPECTION AND ACCEPTANCE
Upon completion of work, the Unit Facility Manager will inspect the area prior to government accept