About this file

This is a Specifications document for flooring material procurement for Yosemite National Park.

The contractor must supply all items listed on the Quote and Price Schedule (Attachment 01) or provide comparable alternatives with documented make, part number, and description. Items are organized into five bundles (A through E): EPBG, MABG, PROJECTS, VABG, and WABG. Each bundle must be wrapped, palletized, and delivered together as a complete unit to the NPS Warehouse at 5083 Foresta Rd, El Portal, CA 95318, with each bundle distinctly labeled. All quotations must be inclusive of shipping and handling costs with FOB destination terms.

Delivery is preferred within 30 days after receipt of order, with delivery hours limited to 7:00 am to 4:00 pm, Monday through Thursday. Contractors must schedule deliveries at least 48 hours in advance and note actual delivery dates on the SF-1449 form. Deliveries are not accepted on Fridays, weekends, or Federal holidays without prior NPS approval. Freight must be unloaded by the contractor; while a docking bay is available, items may require ground-level offloading. Contractors must account for existing travel restrictions including vehicle size limitations (vehicles over 45 feet prohibited), one-way controlled traffic 20 miles east of Mariposa, and potential road closures on Highway 41. These existing conditions cannot be cause for additional compensation claims.

View the file

Other files for this federal contract opportunity

Other files attached to Flooring Materials for Yosemite NP, newest first.
File Type Posted
Sol_140P8526Q0087.pdf PDF
Combined_Synopsis_and_Solicitation.pdf PDF
Atch_01_Quote_and_Price_Schedule.xlsx XLSX spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Atch 02

Specifications

FLOORING MATERIAL

Yosemite National Park

The contractor shall supply all items listed on Atch 01 or a comparable alternative (i.e., brand name or equal). If offering an alternative, provide the item number of the alternate as indicated below along with make, part number, and description.

All items listed on the Quote and Price Schedule (Atch 01) have been grouped into five (5) bundles. Multiple deliveries may be made; however, each individual bundle must be wrapped, palletized, and delivered together as a complete unit. Each bundle must be labeled and delivered as follows:

Delivery to: NPS Warehouse, Attn: Building & Grounds, 5083 Foresta Rd, El Portal, CA 95318

• BUNDLE A – EPBG

• BUNDLE B – MABG

• BUNDLE C – PROJECTS

• BUNDLE D – VABG

• BUNDLE E – WABG

Quotes must be inclusive of all costs, including shipping and handling.

Delivery Delivery is preferred within 30 days after receipt of order (ARO) and will be FOB destination.

Offerors must specify actual delivery date on the SF-1449 when submitting their quotation package.

Delivery hours are 7:00 am to 4:00 pm, Monday - Thursday. Delivery must be scheduled at least 48 hours in advance to ensure proper personnel are on-site to accept delivery. Unless pre-approved by the NPS, deliveries will not be accepted on Fridays, weekends, or Federal holidays.

Freight to be unloaded by the contractor. This location has a docking bay; however, items may be required to be offloaded at ground level.

*Note- Visit www.nps.gov/yose to obtain the latest status and locations for road construction activities, estimated dates of construction, and estimated delays.

Travel restrictions: Vehicles over 45 feet are prohibited and 1-way controlled traffic for all other vehicles 20 miles East of Mariposa (Mariposa County) 24 hours per day, seven days per week due to rockslide repairs. The road leading to Wawona (Hwy 41) can close during inclement weather, see Caltrans website at http://www.dot.ca.gov. Please verify current road conditions prior to hauling. These delays and restrictions must be considered part of the existing conditions within the park and will not be cause for any additional compensation because of travel restrictions or related work.