Asphalt Adjustment 2026.xlsx
XLSX spreadsheet 15 KB Posted
- Solicitation number
- RFB 605 2700000077 1
- Issued by
- Kentucky
About this file
This is an asphalt price adjustment spreadsheet for master agreements effective March 1, 2026, administered by the Kentucky Department of Transportation in conjunction with the Bridge Maintenance & Repair program for FHWA ER Eligible Districts 1-12. The document provides a template for calculating monthly asphalt adjustments based on fluctuations in asphalt pricing throughout the contract year. The spreadsheet is designed to track delivery orders by month from January through December, with columns for recording tons of material used, asphalt content percentages, and adjustment calculations. No specific quantities, response dates, due dates, or contract term information is provided in this adjustment schedule template.
Pricing for asphalt adjustments is calculated using the formula: Asphalt Adjustment Quantity = (Q x 5.6)/100 x (PC - PL), where Q represents tons of material, PL is the KAPI (Kentucky Asphalt Pavement Index) for the month the contract is bid, and PC is the KAPI for the month of pickup or delivery. The threshold determination (indicated by a 1 for yes or 0 for no) and corresponding adjustment percentages are applied monthly to account for volatile asphalt pricing. The spreadsheet includes a link to the Kentucky Transportation Cabinet's Fuel and Asphalt Adjustments page for obtaining current KAPI pricing data. The template shows a total asphalt adjustment quantity of $0.00, indicating this is a blank form ready for population with actual project data and pricing information.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| District Map (1).pdf | ||
| How to Submit an Online Response - March 2023.pdf | ||
| Eastern Region Bid Tab - Federal Districts 9-12.xlsx | XLSX spreadsheet | |
| Final_RFB_605_2700000077_1_SO_FORM.PDF | ||
| Drawings and Notes -2026 (1).pdf | ||
| Western Region Bid Tab - Federal Districts 1-4.xlsx | XLSX spreadsheet | |
| Central Region Bid Tab - Federal Districts 5-8.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
In Place
| For Master Agreements effective March 1, 2026 | Delivery Order Number | |||||||
| Type Delivery Order Here | ||||||||
| Month Placed | Item | Tons (Q) | Asphalt Content | PL | ||||
| (Feb 2026) | PC (KAPI) | Threshold Met | ||||||
| (1=Yes, 0=No) | Adjustment | percent | Date | |||||
| 5.6 | January | |||||||
| 5.6 | February | |||||||
| 5.6 | March | |||||||
| 5.6 | April | |||||||
| 5.6 | May | |||||||
| 5.6 | June | |||||||
| 5.6 | July | |||||||
| 5.6 | August | |||||||
| 5.6 | September | |||||||
| 5.6 | October | |||||||
| 5.6 | November | |||||||
| 5.6 | December | |||||||
| Total Asphalt Adjustment Quantity | $0.00 |
To get the PC (KAPI), click HERE
Contract Formula for Calculating Asphalt Adjustment:
Asphalt Adjustment Quantity = (Q x 5.6)/100 x (PC - PL)
| Where: |
| Q = Tons of material or mixture used |
| PL = KAPI for the month that the contract is bid |
| PC = KAPI for the month of pick up or delivery |
https://transportation.ky.gov/Construction/Pages/Fuel-and-Asphalt-Adjustments.aspx