ASIS_SOW_Install_Hydraulic_Vehicle_Lift.pdf

PDF 153 KB Posted

Attached to
ASIS - HYDRAULIC LIFT INSTALLATION Federal contract opportunity
Solicitation number
140P4221Q0089
Issued by
Department of the Interior National Park Service Northeast Region

View the file

Other files for this federal contract opportunity

Other files attached to ASIS - HYDRAULIC LIFT INSTALLATION, newest first.
File Type Posted
Experience_Questionnaire.docx DOCX document
Sol_140P4221Q0089.pdf PDF
MD20210010.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

Assateague Island National Seashore

Install Hydraulic Vehicle Lift in the Maintenance Shop, Building A

PMIS 216394A

06/15/2021

1.0 INTRODUCTION

The vehicle lift, (Lift) is intended to be installed by a technically qualified Contactor in accordance with the manufacturer’s installation instructions and requirements and in accordance with ANSI/ALI ALIS-2001, Safety Requirements for Installation and Service of Automotive Lifts.

1.1 Principle Objective:

This statement of work, (SOW) outlines the requirements for the installation of one, (1) new Stertil Koni Hydraulic Vehicle Lift. Note: The Lift will be supplied by the National Park Service, (NPS) and two, (2) the removal and proper disposal of an existing Hydraulic Vehicle Lift located in the Maintenance Shop, Building A at the Assateague Island National Seashore, Maryland District. All work will be in accordance with industry acceptable standards and practices and all state and Federal rules and regulations, and laws. The Contractor will ensure work has minimal disruption to Maintenance Shop operations.

1.2 Project Overview:

The project includes cutting and removing an existing concrete floor, removing an existing floor drain. Installing a new level re-enforced concrete floor slab, testing, and documenting concrete compression strength, installing, and connecting a new floor drain, assembling, anchoring, connecting electrically to existing building power and programing the Lift. The Contractor shall furnish all supervision, labor, equipment, tools, materials, and any other items necessary to complete the work. All required work shall be accomplished by the Contractor even though minor items required may not been specifically mentioned in this document.

2.0 KEY ASSUMPTIONS

All work will be performed under a single contract. The time stated for completion shall include final clean-up of the work site.

3.0 CONTRACTOR RESPONSIBILITIES

3.1 Location:

All work will be performed at the Maintenance Shop, Building A at the Assateague Island National Seashore, Maryland District.

3.2 Tasks to Be Performed by Contractor, Base Bid:

The Contractor will in accordance with manufactures installation instructions and industry standards and practices:

3.2.1 Cut, remove, and properly dispose of the existing concrete floor 174”x 216” and 2’ x 4’ floor drain.

3.2.2 Install a new level 174”x 216” x 6’ minimum thickness concrete floor slab re-enforced with #4 rebar spaced 6’x 8” with a compressive strength of 4000 PSI. Pin/tie-in new floor slab to the existing floor slab with #4 x 18” rebar spaced 18’.

3.2.3 Test and document concrete compression strength in accordance with ASTM C-31, (Standard Practice for Making and Curing Concrete Test Specimens in the Field, and ASTM C-39 (Test Method for Compressive Strength of Cylinder Concrete Specimens.

3.2.4 Trench, install and connect a new 6’x6’ cast iron floor drain to the existing floor drain piping.

3.2.5 Uncrate, assemble, and anchor Lift with 5/8’x10” chemical anchors to achieve a minimum strength of 1200 PSI, level and torque a min. of 60 FT-LBS.

3.2.6 Install appropriately sized conduit, wire and supports in accordance with NEC to connect the Lift electrically to existing building power.

3.2.A Tasks to Be Performed by Contractor, Bid Option A:

3.2.7 Program and test the Lift.

3.2.B Tasks to Be Performed by Contractor, Bid Option B:

3.2.8 Remove and properly dispose of an existing Hydraulic Vehicle Lift located in the Maintenance Shop, Building A.

References in specifications to any brand name equipment or materials shall be regarded as establishing a standard of quality and shall not be construed as limiting competition. The Contractor may submit proposed equal equipment and/or materials for government consideration during the submittal process of the contract after award.

The point of contact is Eric Sherry, Chief of Maintenance. He can be reached at the following phone numbers:

(Office) 410-629-6062 (Cell) 443-365-4970

3.3 Tasks to Perform by Buyer:

N/A

3.4 Dates of Delivery:

Within 90 days of award.

3.5 Period of Performance:

Work shall be accomplished during the standard (8) hour day, (5) day week, Monday through Friday, between the hours of 7:30 A.M. and 4:30 P.M. local time, excluding federal legal holidays and non-workdays resulting from holidays occurring on weekends. If the Contractor desires to work other than the standard (8) hour day, then the Contractor must submit a written request at least three workdays prior to the proposed performance of work to the Contracting Officer (CO). This written request must state the proposed performance of work, day/days, time/amount of work, and reason why permission should be granted to perform work during non-standard hours.

LEGAL HOLIDAYS

New Year’s Day: 1 January

Martin Luther King Day: Third Monday in January

President’s Day: Third Monday in February

Memorial Day: Last Monday in May

Independence Day: 4 July

Labor Day: First Monday in September

Columbus Day: Second Monday in October

Veteran’s Day: 11 November

Thanksgiving Day: Fourth Thursday in November

Christmas Day: 25 December

4.0 CONTRACT COMPLETION CRITERIA

The contract is complete when the unit is tested, found to be operational, and the work has been approved by the COR or his designee.

5.0 ADDITIONAL TERMS AND CONDITIONS

All labor and materials supplied by the Contractor shall have a one-year warranty. All warranty and testing documentation will be provided to the Contracting Officer.

File details come from the government source that posted it. Updated .