ASHE 20-1016 DWGS REV01.pdf

PDF 10 MB Posted

Attached to
ASHE 20-1016 INSTALL WATER TREATMENT FOR HMU, AVIANO AB, ITALY
Solicitation number
FA568221R0003
Issued by

About this file

This document provides details on a federal contract solicitation for installation of a water treatment system at Aviano Air Base in Italy. The solicitation seeks proposals for project work involving categories OG01, OS22, and/or OG11, with a magnitude of construction between $250,000 and $500,000. Interested vendors must possess the relevant Statement of Accreditation certification and register with SAM. The work includes installing a water treatment system for the HMU facility at location F on the Aviano Air Base flightline. Proposals are due by the date specified in the solicitation. The performance period requires delivery of a complete project on a lump sum basis. The Department of the Air Force United States Air Forces in Europe - Air Forces Africa is the contracting agency.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

13909

14270

11607

10106

13040

11731

12043

12041

12042

12052

14234

14071

91603

91602

91604

12371

12372

921A

72701

13044

83111

14313

10163

10997

13846

71183

10461

13265

1135B

14231

11812

14684

78030

78350

78301

11720

10161

12273

10296

13845

11985

14033

13046

78270

12272

11401

13844

14314

1135E

15023

13050

14305

11894

14309

71192

11895

1135A

13812

14303

71905

14304

77190

13047

11361

10233

1135F

11892

10516

10514

14081

14311

10271

14307

71188

11982

10515

12002

10505

14312

10506

78702

14666

14302

10517

11226

13816

1362PB

1135C

13809

81019

10295

70905

91601

10108

11225

14310

13049

10232

13045

71196

13048

11891

14906

71189

1027A

11893

71193

89801

14641

11981

14901

10504

1135D

14315

71098

11986

71099

14686

71270

14301

10372

10462

12004

71388

918A

14611

14612

14084

10509

10510

14306

DEL PROGETTO

UBICAZIONE

LOCATION

PROJECT

ASHE 20-1016 INSTALL WATER TREATMENT

U.S. AIR FORCE

31ST CES/CENM

AVIANO AIR BASE

SYS FOR HMU FAC.933

AREA F, AVIANO AB, ITALY

FINAL (100% DESIGN) - REVISION 01

FEBRUARY 08 , 2021

TH

st

C E

S /C

E N

M st F

IG

H

TE

R

W

IN

G

100%

Engineering Tools Srl

Via del Makò n. 33

33084 Cordenons (PN)

TEL.: +39 0434 536333

FAX: +39 0434 542813

E-mail: info@engtools.eu

PEC: info@pec.engtools.eu

U .S

. A

IR

F O

R C

E

G-001

KEY PLAN

PIANTA CHIAVE

LOCATION MAP

MAPPA GENERALE

LOCAL AREA MAP

INQUADRAMENTO AREA

GENERAL / GENERALI

st

C E

S /C

E N

M st F

IG

H

TE

R

W

IN

G

100%

Engineering Tools Srl

Via del Makò n. 33

33084 Cordenons (PN)

TEL.: +39 0434 536333

FAX: +39 0434 542813

E-mail: info@engtools.eu

PEC: info@pec.engtools.eu

U .S

. A

IR

F O

R C

E

INDEX OF DRAWINGS / INDICE DELLE TAVOLE

G-002_rev01

CIVIL / CIVILI

SURVEY / RILIEVO

ELECTRICAL / ELETTRICHE

A

A st

C E

S /C

E N

M st F

IG

H

TE

R

W

IN

G

100%

Engineering Tools Srl

Via del Makò n. 33

33084 Cordenons (PN)

TEL.: +39 0434 536333

FAX: +39 0434 542813

E-mail: info@engtools.eu

PEC: info@pec.engtools.eu

U .S

. A

IR

F O

R C

E

EXISTING CONDITIONS - GENERAL PLAN - SURVEY

STATO DI FATTO - PLANIMETRIA GENERALE - RILIEVO

V-101

NEW WORK KEYNOTE

NOTA CHIAVE NUOVI LAVORI

st

C E

S /C

E N

M st F

IG

H

TE

R

W

IN

G

100%

Engineering Tools Srl

Via del Makò n. 33

33084 Cordenons (PN)

TEL.: +39 0434 536333

FAX: +39 0434 542813

E-mail: info@engtools.eu

PEC: info@pec.engtools.eu

U .S

. A

IR

F O

R C

E

EXISTING CONDITIONS - GENERAL PLAN - SURVEY

STATO DI FATTO - PLANIMETRIA GENERALE - RILIEVO

CD101_rev01

GENERAL NOTES/NOTE GENERALI

LEGEND / LEGENDA:

A

Q A.C.

st

C E

S /C

E N

M st F

IG

H

TE

R

W

IN

G

100%

Engineering Tools Srl

Via del Makò n. 33

33084 Cordenons (PN)

TEL.: +39 0434 536333

FAX: +39 0434 542813

E-mail: info@engtools.eu

PEC: info@pec.engtools.eu

U .S

. A

IR

F O

R C

ENEW CONDITIONS - GENERAL PLAN

STATO DI PROGETTO - PLANIMETRIA GENERALE

C-101

NEW WORK KEYNOTE

NOTA CHIAVE NUOVI LAVORI

FLIGHT OPERATION CONSTRAINTS VERIFICATION

VERIFICA DEI VINCOLI RICEVUTI DA FLIGHT OPERATION

Q A.C.

st

C E

S /C

E N

M st F

IG

H

TE

R

W

IN

G

100%

Engineering Tools Srl

Via del Makò n. 33

33084 Cordenons (PN)

TEL.: +39 0434 536333

FAX: +39 0434 542813

E-mail: info@engtools.eu

PEC: info@pec.engtools.eu

U .S

. A

IR

F O

R C

E

NEW CONDITIONS - GENERAL PLAN

STATO DI PROGETTO - PLANIMETRIA GENERALE

C-102

Q A.C.

Q A.C.

st

C E

S /C

E N

M st F

IG

H

TE

R

W

IN

G

100%

Engineering Tools Srl

Via del Makò n. 33

33084 Cordenons (PN)

TEL.: +39 0434 536333

FAX: +39 0434 542813

E-mail: info@engtools.eu

PEC: info@pec.engtools.eu

U .S

. A

IR

F O

R C

E

NEW CONDITIONS - ENLARGED PLAN

STATO DI PROGETTO - PIANTA INGRANDITA

KEY PLAN

PIANTA RIFERIMENTO

C-103

NEW WORK KEYNOTE

NOTA CHIAVE NUOVI LAVORI

DRAINING FIELD CALCULATION

CALCOLO CAMPO DRENANTE

PROJECT DATA / DATI DI PROGETTO

st

C E

S /C

E N

M st F

IG

H

TE

R

W

IN

G

100%

Engineering Tools Srl

Via del Makò n. 33

33084 Cordenons (PN)

TEL.: +39 0434 536333

FAX: +39 0434 542813

E-mail: info@engtools.eu

PEC: info@pec.engtools.eu

U .S

. A

IR

F O

R C

E

C-301 st

C E

S /C

E N

M st F

IG

H

TE

R

W

IN

G

100%

Engineering Tools Srl

Via del Makò n. 33

33084 Cordenons (PN)

TEL.: +39 0434 536333

FAX: +39 0434 542813

E-mail: info@engtools.eu

PEC: info@pec.engtools.eu

U .S

. A

IR

F O

R C

C-302

NOTES

NOTE

PHASE 0: EXISTING CONDITIONS

FASE 0: STATO DI FATTO

PHASE 1: CUTTING AND REMOVAL EXISTING PORTION OF SLAB

FASE 1: TAGLIO E RIMOZIONE PORZIONE ESISTENTE SOLETTA

PHASE 2: DIGGIN SECTION & SOIL COMPACTING

FASE 2: SEZIONE DI SCAVO E COMPATTAMENTO TERRENO

PHASE 3: LEAN CONCRETE AND BASEMENT CONSTRUCTION

FASE 3: MAGRONE E COSTRUZIONE BASAMENTO

PHASE 0 - 1: EXISTING CONDITION - PLAN

FASE 0 - 1: STATO DI FATTO - PIANTA

GENERAL NOTES/NOTE GENERALI

KEY PLAN

PIANTA RIFERIMENTO

st

C E

S /C

E N

M st F

IG

H

TE

R

W

IN

G

100%

Engineering Tools Srl

Via del Makò n. 33

33084 Cordenons (PN)

TEL.: +39 0434 536333

FAX: +39 0434 542813

E-mail: info@engtools.eu

PEC: info@pec.engtools.eu

U .S

. A

IR

F O

R C

C-501_rev01

PHASE 4: SLOT CHANNEL POSITIONING

FASE 4: POSIZIONAMENTO CANALINA A FERITOIA

PHASE 5: CONTAINMENT WALL CONSTRUCTION

FASE 5: REALIZZAZIONE MURETTI DI CONTENIMENTO

PHASE 6: LEAN CONCRETE FILLING

FASE 6: RIEMPIEMENTO CON MAGRONE

PHASE 7: RECONSTRUCTION NEW APRON SLAB

FASE 7: REALIZZAZIONE NUOVA SOLETTA APRON

NOTES

NOTE

PHASES 6-7: NEW CONDITION - JOINTS DETAILS

FASI 6-7: PROGETTO - DETTAGLI GIUNTI

st

C E

S /C

E N

M st F

IG

H

TE

R

W

IN

G

100%

Engineering Tools Srl

Via del Makò n. 33

33084 Cordenons (PN)

TEL.: +39 0434 536333

FAX: +39 0434 542813

E-mail: info@engtools.eu

PEC: info@pec.engtools.eu

U .S

. A

IR

F O

R C

C-502

90°

PRECAST MANHOLE

(800X800 OR SUPERIOR)

POZZETTO PREFABBRICATO

(800X800 O SUPERIORE)

SCALE: 1:25

DRAINAGE CHAMBERS - DETAIL

DETTAGLIO BACINI DRENANTI

BENCHING DETAIL

(FOR MANHOLE)

DETTAGLIO GETTO DI

SECONDA FASE (PER POZZETTI)

SCALE: 1:25

TYPICAL TRENCH SECTION

FOR PVC PIPE

SEZIONE TIPO DI SCAVO PER

TUBAZIONI IN PVC

SCALE: 1:25

PVC PIPE DETAIL

PARTICOLARE TUBAZIONE IN PVC

N.T.S.

NOTES

NOTE

NOTES

NOTE

NOTES

NOTE

NOTES

NOTE

NOTES

NOTE

st

C E

S /C

E N

M st F

IG

H

TE

R

W

IN

G

100%

Engineering Tools Srl

Via del Makò n. 33

33084 Cordenons (PN)

TEL.: +39 0434 536333

FAX: +39 0434 542813

E-mail: info@engtools.eu

PEC: info@pec.engtools.eu

U .S

. A

IR

F O

R C

C-503

NOTES

NOTE

NEW CONCRETE SLOT CHANNEL - PLAN

NUOVA CANALINA A FERITOIA - PLANIMETRIA

NEW CONCRETE SLOT CHANNEL

NUOVA CANALINA A FERITOIA

st

C E

S /C

E N

M st F

IG

H

TE

R

W

IN

G

100%

Engineering Tools Srl

Via del Makò n. 33

33084 Cordenons (PN)

TEL.: +39 0434 536333

FAX: +39 0434 542813

E-mail: info@engtools.eu

PEC: info@pec.engtools.eu

U .S

. A

IR

F O

R C

C-504

I II

P

GAC FILTER SYSTEM DETAIL

DETTAGLIO IN PIANTA SISTEMA

FILTRAZIONE A CARBONE ATTIVI

SCALE: 1:25

NOTES

NOTE

NOTES

NOTE

CLAMP SADDLE INSTALLATION DETAIL

DETTAGLIO INSTALLAZIONE PRESA A STAFFA

N.T.S.

st

C E

S /C

E N

M st F

IG

H

TE

R

W

IN

G

100%

Engineering Tools Srl

Via del Makò n. 33

33084 Cordenons (PN)

TEL.: +39 0434 536333

FAX: +39 0434 542813

E-mail: info@engtools.eu

PEC: info@pec.engtools.eu

U .S

. A

IR

F O

R C

C-505

EU

S

II

P

I II

P

EU

I

U

U

E

E

B

B

I II

P

P

S

S

I

II

P

SEDIMENTATION TANK

VASCA DI DISSABBIATURA

SCALE: 1:25

10 OIL SEPARATOR

VASCA DI DISOLEAZIONE

SCALE: 1:25

NOTES

NOTE

NOTES

NOTE

st

C E

S /C

E N

M st F

IG

H

TE

R

W

IN

G

100%

Engineering Tools Srl

Via del Makò n. 33

33084 Cordenons (PN)

TEL.: +39 0434 536333

FAX: +39 0434 542813

E-mail: info@engtools.eu

PEC: info@pec.engtools.eu

U .S

. A

IR

F O

R C

C-506

SCALE: 1:25

DIVERT VALVES INSTALLATION DETAIL

DETTAGLIO INSTALLAZIONE VALVOLE DEVIATRICI

NOTES

NOTE

SECTION "A-A"

SEZIONE "A-A"

A

A A st

C E

S /C

E N

M st F

IG

H

TE

R

W

IN

G

100%

Engineering Tools Srl

Via del Makò n. 33

33084 Cordenons (PN)

TEL.: +39 0434 536333

FAX: +39 0434 542813

E-mail: info@engtools.eu

PEC: info@pec.engtools.eu

U .S

. A

IR

F O

R C

C-507

QUARTZITE AND ACTIVE CARBON TANK DIAGRAM

SCHEMA INSTALLAZIONE COLONNA

QUARZITE E CARBONE ATTIVO

N.T.S.

NOTES

NOTE

3A

4A

2A

1A

3B 2B

1B 4B

START STOP

DON'T WASH

W A S H

WASHING PROCEDURE:

WHEN NO WASHING OPERATION IS GOING ON, THE DRAIN

VALVES ARE IN "NORMALLY CLOSED" STATUS.

BEFORE STARTING THE WASHING THE OPERATOR MUST PUSH

THE "START" BUTTON. THE DN150 VALVE OPENS AND THE LED

GREEN PANEL "WASH" SWITCHES ON. NOW THE WASHING

OPERATIONS CAN START.

AT THE END OF THE WASHING, THE OPERATOR MUST PUSH

THE "STOP" BUTTON AND THE LED PANEL SIGNAL "DON'T

WASH" SWITCHES ON, TO INDICATE THE DRAIN CLOSURE.

IN CASE OF RAIN, THE RAIN SENSOR OPENS THE DN400 VALVE.

THE SENSOR CLOSES THE VALVE 15 MIN AFTER THE RAIN

STOPS.

IN CASE OF RAIN, THE RAIN SENSOR WILL ALSO CHECK

WHETHER THE DN150 VALVE IS CLOSED OR NOT. IN CASE IT’S

STILL OPEN, IT FORCES VALVE CLOSURE.

PROCEDURE DI LAVAGGIO

LE VALVOLE DI SCARICO SARANNO "NORMALMENTE CHIUSE",

E LA PRESSIONE DEL PULSANTE "START" DA PARTE

DELL’OPERATORE FARÀ APRIRE LA VALVOLA DN150 E IL

PANNELLO A LED "WASH" CON SCRITTA VERDE SEGNALERÀ

ALL'OPERATORE LA POSSIBILITÀ DI POTER LAVARE. AL

TERMINE DEL LAVAGGIO LA PRESSIONE DEL PULSANTE "STOP"

FARÀ CHIUDERE LA VALVOLA E ACCENDERE IL PANNELLO A

LED "DON'T WASH" CON SCRITTA ROSSA AD INDICARE LA

CHIUSURA DELLO SCARICO. IN CASO DI PRECIPITAZIONE IN

CORSO, IL SENSORE PIOGGIA FARÀ APRIRE LA VALVOLA

DN400 E LA CHIUDERÀ CON UN RITARDO DI 15 MIN. ALLA

CESSAZIONE DELL’EVENTO. NEL CASO DI PIOGGIA IL SENSORE

OLTRE A FAR APRIRE LA VALVOLA DN400 CONTROLLERÀ CHE

LA VALVOLA DN150 SIA STATA CHIUSA, ALTRIMENTI

PROVVEDERÀ A FARLO FORZATAMENTE.

EMERGENCY PROCEDURE:

IN CASE OF EMERGENCY PUSH THE MUSHROOM BUTTON.

THE BUTTON PROVIDE TO CLOSE EACH MOTORIZED VALVE.

ALSO CLOSE MANUALLY THE VALVE INSTALLED IN THE

MAHNOLE CLOSE TO THE APRON.

PROCEDURE DI EMERGENZA:

IN CASO DI EMERGENZA, PREMERE IL PULSANTE DI ALLARME

CHE PROVVEDERA' A CHIUDERE TUTTE LE VALVOLE.

INOLTRE CHIUDERE MANUALMENTE LA VALVOLA INSTALLATA

NEL POZZETTO IN PROSSIMITA' DELL'APRON.

ALARM

A

SIDE VIEW

VISTA LATERALE

A

A st

C E

S /C

E N

M st F

IG

H

TE

R

W

IN

G

100%

Engineering Tools Srl

Via del Makò n. 33

33084 Cordenons (PN)

TEL.: +39 0434 536333

FAX: +39 0434 542813

E-mail: info@engtools.eu

PEC: info@pec.engtools.eu

U .S

. A

IR

F O

R C

C-508_rev01

AREA 1 - PHASE 3: LEAN CONCRETE AND BASEMENT CONSTRUCTION

AREA 1 - FASE 3: MAGRONE E COSTRUZIONE BASAMENTO

AREA 2 - PHASE 3: LEAN CONCRETE AND BASEMENT CONSTRUCTION

AREA 2 - FASE 3: MAGRONE E COSTRUZIONE BASAMENTO

NOTES

NOTE

GENERAL NOTES/NOTE GENERALI

NOTES

NOTE

GENERAL NOTES/NOTE GENERALI

KEY PLAN

PIANTA RIFERIMENTO

st

C E

S /C

E N

M st F

IG

H

TE

R

W

IN

G

100%

Engineering Tools Srl

Via del Makò n. 33

33084 Cordenons (PN)

TEL.: +39 0434 536333

FAX: +39 0434 542813

E-mail: info@engtools.eu

PEC: info@pec.engtools.eu

U .S

. A

IR

F O

R C

C-509

FeZn CABLE TRAY, IP4X st

C E

S /C

E N

M st F

IG

H

TE

R

W

IN

G

100%

Engineering Tools Srl

Via del Makò n. 33

33084 Cordenons (PN)

TEL.: +39 0434 536333

FAX: +39 0434 542813

E-mail: info@engtools.eu

PEC: info@pec.engtools.eu

U .S

. A

IR

F O

R C

E

NEW CONDITIONS - GENERAL PLAN

STATO DI PROGETTO - PLANIMETRIA GENERALE E-101

M D

P

JB JB

JB

JB

JB

JB

JB

st

C E

S /C

E N

M st F

IG

H

TE

R

W

IN

G

100%

Engineering Tools Srl

Via del Makò n. 33

33084 Cordenons (PN)

TEL.: +39 0434 536333

FAX: +39 0434 542813

E-mail: info@engtools.eu

PEC: info@pec.engtools.eu

U .S

. A

IR

F O

R C

E

E-102

NEW WORK KEYNOTE

NOTA CHIAVE NUOVI LAVORI

GAC FILTER SYSTEM DETAIL

DETTAGLIO DELL'IMPIANTO DI FILTRAZIONE

GENERAL NOTES

NOTE GENERALI

LEGEND AND NOTES

LEGENDA E NOTE

QF4

H1,H2,H3

MDP

MAIN DISTRIBUTION PANEL

QUADRO GENERALE

FU2QS.SPD

QF

FU1

QF7

SPD

Id

QS.M

QF1 QF2 QF3 QF5 QF6

QF.ROOM

Id

QF.EQP

Id

QF9QF8

K

E

I II

M G

B

JB

JB

JB

JB

JB

JB

ELECTRICAL BONDING

EQUIPOTENZIALIZZAZIONE

NOTE

NOTA

st

C E

S /C

E N

M st F

IG

H

TE

R

W

IN

G

100%

Engineering Tools Srl

Via del Makò n. 33

33084 Cordenons (PN)

TEL.: +39 0434 536333

FAX: +39 0434 542813

E-mail: info@engtools.eu

PEC: info@pec.engtools.eu

U .S

. A

IR

F O

R C

E-601_rev01

Fogli e viste
G-001
Fogli e viste
G-002
Fogli e viste
V-101
Fogli e viste
CD101
Fogli e viste
C-101
Fogli e viste
C-102
Fogli e viste
C-103
Fogli e viste
C-301_C-302
Fogli e viste
C-301_C-302
Fogli e viste
C-501
Fogli e viste
C-502
Fogli e viste
C-503
Fogli e viste
C-504
Fogli e viste
C-505
Fogli e viste
C-506
Fogli e viste
C-507
Fogli e viste
C-508
Fogli e viste
C-501
Fogli e viste
E-101
Fogli e viste
E-102
Fogli e viste
E-601