Asbestos and Lead Paint Abatement SOO.pdf

PDF 135 KB Posted

Attached to
Asbestos and Lead Paint Abatement
Solicitation number
F2E3CE4325AW01
Issued by

About this file

This Statement of Objectives (SOO) details requirements for asbestos and lead paint abatement at Building 584 at Holloman Air Force Base. The project involves an unoccupied 210' x 48' two-story barracks located between New Mexico Ave. and Connecticut Ave., with a 90-day construction period and standard working hours of 7:00 am to 5:00 pm.

The scope includes abatement of approximately 15,500 SF of ceiling drywall materials, 10,500 SF of floor tile and mastic under carpet in living/hallway areas, 1,200 SF of floor tile and mastic in kitchen areas, 35,000 SF of textured drywall throughout the building, and 4,100 SF of exterior soffit/ceiling drywall. Lead-based paint abatement includes 7.2 SF in a bathtub in room 4105 and 10.1 SF in the first floor janitor closet sink. The contractor must provide all materials, labor, and equipment, establish a staging area, and dispose of all materials at a certified landfill or recycling center according to state and federal laws. Asbestos and lead paint surveys have already been completed as of May 9, 2024.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HOLLOMAN AIR FORCE BASE

PROJECT KWRD 22-0053

Asbestos Abatement B584

STATEMENT OF OBJECTIVES

15 November 2024

1. PROJECT SPECIFIC INFORMATION:

1.1. Location: B584

1.2. User Contact: TBD

1.3. Design effort: None.

1.4. Performance Period of Design (days): 0

1.5. Performance Period of Construction (days): 90

1.6. Working Hours: Standard (7:00 am to 5:00 pm)

1.7. Restricted area (as defined in HAFB Instruction 31-102): No

2. SCOPE OF WORK:

This project will abate asbestos and lead paint* from B584. B584 is an unoccupied 210’ x 48’, 2 story barracks, accessible from 8th St., between New Mexico Ave. and Connecticut Ave.

Work shall be in accordance with this Statement of Objectives (SOO) and Unified Facilities Criteria (UFC).

2.1. The contractor shall provide all materials, labor and equipment to complete all work described in the SOO. The contractor is responsible for collecting and disposing of all demolished/discarded/unusable materials resulting from this project.

2.2. The contractor shall establish a staging area for all equipment and materials.

2.2.1. The contractor will coordinate with user for an appropriate staging area of materials and equipment.

2.3. All government provided dimensions are approximate. It is the contractor’s responsibility to determine exact dimensions for planning and estimating.

2.4. Contractor shall remove asbestos materials in B584.

2.4.1. Abate all asbestos referenced in attached asbestos survey dated 09 May 2024.

2.4.2. Abate approximately 15500 SF of ceiling drywall materials located throughout building

2.4.3. Abate approximately 10500 SF of floor tile and mastic under carpet located in living and hallway areas

2.4.4. Abate approximately 1200 SF floor tile and mastic located in kitchen areas

2.4.5. Abate approximately 35000 SF textured drywall located throughout building

2.4.6. Abate approximately 4100 SF exterior soffit/ceiling drywall located in exterior soffits/ceilings

2.5. Contractor shall remove Lead Based Paint materials in B584.

2.5.1. Abate all asbestos referenced in attached asbestos survey dated 09 May 2024.

2.5.2. Abate approximately 7.2 SF in bathtub in 4105 restroom

2.5.3. Abate approximately 10.1 SF in 1st floor janitor closet sink

2.6. All disassembled or demolished materials shall be removed from Holloman AFB and disposed of in a certified landfill or recycle center per state and federal laws.

*Surveys for asbestos and lead based paint have been accomplished.

END STATEMENT OF WORK