The document is a Request for Quotes (RFQ) #RFQ195240 issued by the City of Palo Alto's Community Services Department for an Art Center Gas Kiln Replacement and Installation project. The RFQ seeks a contractor to purchase and install a new Geil downdraft kiln model DLB-20 for the Palo Alto Art Center, with specific requirements including a 20 cubic foot capacity, brick-lined, natural draft, front-loading kiln that is ETL certified. The project involves delivery, removal of the old kiln, and installation, with the bid due date set for Friday, September 26, 2025, before 3:00 pm. Bidders are required to submit their quotes electronically through the City's OpenGov portal, with a question submission deadline of September 19, 2025, at 1:00 pm.

The project is partially funded by the Palo Alto Art Center Ceramics Programs under CIP AC-28003. Bidders must comply with various requirements, including prevailing wage regulations, Department of Industrial Relations (DIR) registration, and providing detailed information through a comprehensive Bidder's Questionnaire. The contract will be awarded to the lowest responsive and responsible bidder, with the City reserving the right to reject any or all quotes. Bidders must provide proof of insurance, submit performance and payment bonds, and demonstrate compliance with local, state, and federal regulations, including nondiscrimination policies and contractor licensing requirements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COMMUNITY SERVICES DEPARTMENT

REQUEST FOR QUOTES (BID )# RFQ195240

ART CENTER GAS KILN REPLACEMENT AND INSTALLATION

BID DUE DATE: Friday, September 26, 2025 BEFORE 3:00 pm

TABLE OF CONTENTS

Section 1 Request for Quotes Summary

Section 2 Instruction to Bidders

Section 3 Specifications/Scope of Work

Section 4 Bid Form

Section 5 Bidder's Questionnaire

Attachments:

A - 195240 Bid Form Art Center Gas Kiln Replacement

B - Minor_Public_Works_Agreement

C - Insurance Requirements

D - Payment Bond

E - Performance Bond

Request for Quotes (RFQ) #RFQ195240 2 Art Center Gas Kiln Replacement and Installation

1. REQUEST FOR QUOTES SUMMARY

1.1. Quote Submittal Information

Bids shall be submitted electronically through the City’s OpenGov portal at:

https://procurement.opengov.com/portal/palo-alto-ca

RFQ Date: September 3, 2025

Question Submission Deadline: September 19, 2025, 1:00pm

Quote Submission Deadline: September 26, 2025, 3:00pm

1.2. Addenda/Clarifications/Questions

Should discrepancies be found in this RFQ or should there be a need to clarify this RFQ, Questions/Clarifications must be received by no later than 1:00 pm on Friday, September 19, 2025.

Correspondence shall be communicated through the City’s OpenGov portal within the Q&A tab.

Responses from the City will be communicated through the City’s OpenGov portal to all recipients of this

RFQ via addendum. Inquiries received after the date and time stated may not be accepted. All addenda shall become part of this RFQ and acknowledged through the City’s OpenGov portal. The City shall not be responsible for nor be bound by any oral instructions, interpretations or explanations issued by the

City or its representatives.

“A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any contract for public work, as defined in this chapter, unless currently registered and qualified to perform public work pursuant to Section 1725.5. It is not a violation of this section for an unregistered contractor to submit a bid that is authorized by Section 7029.1 of the Business and Professions Code or by Section

10164 or 20103.5 of the Public Contract Code, provided the contractor is registered to perform public work pursuant to Section 1725.5 at the time the contract is awarded.”

Please note: If the City is unable to confirm that the bidder/contractor’s DIR registration is current, the

City may disqualify the bidder in accordance with applicable law including but not limited to Labor Code section 1725.5.

1.3. Suspension and Debarment Status

As applicable, the City will verify whether a contractor and its subcontractors, if any, are suspended or debarred from doing business with the federal government by searching the Excluded Parties List

System (www.sam.gov). This verification process applies to contracts funded by federal grants and which are for $25,000 or more (including as well any subcontract that is for $25,000 or more). Unless an exception applies, no such federal funds may go to a person or entity that is suspended or disbarred, thus any such person or entity found to be suspended or disbarred in the check of the www.sam.gov list system will be disqualified under the Request For Quotes.

https://procurement.opengov.com/portal/palo-alto-ca https://www.sam.gov/

Request for Quotes (RFQ) #RFQ195240 3

1.4. Verification of Contractor's License

The City will verify the status of the contractor’s license by checking the Contractor’ State License Board

(www.cslb.ca.gov). The contractor's license and business must match. This verification includes information on any outstanding Board disciplinary action pending against the contractor.

1.5. Pre-Bid Conference

A Pre-Bid Conference is not scheduled.

2. INSTRUCTION TO BIDDERS

The below Instructions to Bidders includes requirements for submitting a Bid for this request for quotes.

2.1. Submittal

Quotes shall be submitted through the City’s electronic procurement system. A Quote which is attempted to be delivered or which is received after the stated time shall be deemed non-responsive and rejected. The Bidder shall have the sole and exclusive responsibility for ensuring that a quote is received by the time stated herein. Any Quote that is incomplete, unclear, or that fails to fully comply with the applicable requirements set forth herein, including, but not limited to, use of the forms provided by the City, may be rejected as nonresponsive.

2.2. Responsibility of Bidder

A Quote shall be submitted at the sole cost and expense of the Bidder and, in submitting such quote to the City, the Bidder waives any claim or demand against the City which the Bidder may have for any direct or indirect cost or expense of preparing and submitting such Quote.

2.3. Bid Submittals

Bid Form and Bidder’s Documents: Bids must be submitted though the City’s OpenGov portal. Bidder must complete all required items in full and provide signed versions of any documents required in this

RFQ (collectively, the “Bidder’s Documents”). The Bidder will ensure that the information the Bidder inputs into the electronic procurement system matches the information on the Bidder’s Documents it uploads to the electronic procurement system. Any conflict or discrepancy will be resolved as provided in below in "Requirements and Order of Precedence", below, of this Section ("Bid Submittals").

Bidder’s Questionnaire: Each Bid must be accompanied by a completed Bidder’s Questionnaire as provided in this RFQ. Submission of a Bidder’s Questionnaire containing false or incomplete information may be grounds for rejection of the Bid as non-responsive and/or disqualification of the Bidder as not responsible.

Requirements and Order of Precedence: In the event of any conflict or discrepancy between any requirements provided in this RFQ (including but not limited to bid submittal requirements) and any requirements that may be stated in the City’s electronic procurement system, the requirements of this

RFQ will control. In the event of any conflict or discrepancy between information included on (or https://www.cslb.ca.gov/

Request for Quotes (RFQ) #RFQ195240 4 omitted from) the Bid Form or Bidder’s Documents uploaded to the City’s electronic procurement system and any information inputted into the City’s electronic procurement system, the information included on (or omitted from) the uploaded information or Bidder’s Documents will control. For clarity, the Bidder’s Documents uploaded into the electronic procurement system constitute a Bidder’s Bid, whereas the information a Bidder inputs into the electronic procurement system is for administrative convenience and will not control over the uploaded Bidder’s Documents in event of a conflict or discrepancy.

2.4. Bid Authorization

Any person logging into the electronic procurement system to submit a Bid or any other electronic document required by the City must be authorized by the company or entity being represented, either in a personal or representative capacity, to access and submit such bid documents. If the person does business under his or her own name, that person shall login under his or her own login as authorized by the City’s OpenGov portal. If the person does business under a fictitious business name, that person shall login under his or her own login as authorized by the City's OpenGov portal. If the person logins for and on behalf of a partnership, the person shall do so with his or her authority to sign/login under his or her own login as authorized by the OpenGov.

2.5. Withdrawal of Bid

Prior to the date and time set for the opening of Bids, a Bidder who has submitted a bid and accepted the terms and conditions in the City’s electronic procurement system, may withdraw its bid by selecting

“Unsubmit Bid” at any time before the deadline for the receipt of Bids as specified in the RFQ Summary.

No Bidder may withdraw its Bid for a period of ninety (90) days after the date set for the opening of, subject to applicable California Law and Palo Alto Municipal Code Section 2.30.460(c), whichever occurs first.

2.6. Request(s) for Clarification

Any Bidder may submit a Question or Inquiry to the Question & Answer section of this RFQ for the clarification of any aspect of the Specifications or any other related information, or part thereof, which is a part of the RFQ. Such request shall be submitted electronically via the City’s electronic procurement system Q&A function. Such requests shall be submitted before 1:00 pm on Friday, September 19, 2025.

All responses will be made available on the City's OpenGov portal at least three (3) Business Days prior to the opening of Quotes. The City reserves the right to issue an addendum or addenda per the

"Addenda" Section of the Instructions to Bidders of the RFQ.

2.7. Addenda

The City reserves the right to issue a written Addendum or Addenda to the electronic solicitation prior to the bid closing date and time. During the Bid process there may be changes to the Contract

Documents, which would require an issuance of an addendum or Addenda. City disclaims any and all liability for loss, or damage to any Bidder who does not receive any addendum issued by City in connection with this RFQ. Any Bidder by submitting a Bid waives any and all claims and demands Bidder may have against City on account of the failure of delivery of any such Addendum to Bidder. Any and all

Addenda issued by City shall be deemed included in this RFQ, and the provisions and instructions therein contained shall be incorporated into any Bid submitted by Bidder.

Request for Quotes (RFQ) #RFQ195240 5

2.8. Specifications

The specifications included have been prepared to describe the standard quality, and other characteristics needed to meet City requirements. The City has standardized its requirements for GEIL

DOWNDRAFT KILN MODEL DLB-20, 20 CU. FT. STACKING, BRICK LINED, NATURAL DRAFT, FRONT

LOADING. ETL CERTIFIED WITH SIDE DAMPER, DEMOUNTABLE FLUE, AUTOMATIC DAMPER CONTROL

SYSTEM WITH MICROPROCESSOR AND HOOD BAFFLE EXTENSION and will not accept alternate quotation of a designed material, product, thing, service, “or equal other that specified in the

"Specifications/Scope of Work" Section of this RFQ.

2.9. Prevailing Wages

This Project is subject to prevailing wages and related requirements as a “public works” under

California Labor Code Sections 1720 et seq. and related regulations. Contractor is required to pay general prevailing wages as defined in California Labor Code Section 1773.1 and Subchapter 3, Title 8 of the California Code of Regulations Section 16000 et seq., as amended from time to time. Pursuant to

Labor Code Section 1773, the City has obtained the general prevailing rate of per diem wages and the general rate for holiday and overtime work in this locality for each craft, classification, or type of worker needed to execute the contract for this Project from the State of California Department of Industrial

Relations (“DIR”). Copies of these rates may be obtained at the City’s Purchasing Department office. The general prevailing wage rates are also available at the DIR, Division of Labor Statistics and Research, website (see e.g. http://www.dir.ca.gov/DLSR/PWD/index.htm) as amended from time to time.

Contractor shall post a copy of the general prevailing wage rates at all Project job sites and shall pay the adopted prevailing wage rates as a minimum. Contractor shall comply with all applicable provisions of

Division 2, Part 7, Chapter 1 of the California Labor Code (Labor Code Section 1720 et seq.), including, but not limited to, Sections 1720, 1725.5, 1771, 1771.1, 1771.4, 1773.2, 1774, 1775, 1776, 1777.5, 1782, 1810, 1813 and 1815, and all applicable implementing regulations, including but not limited to

Subchapter 3, Title 8 of the California Code of Regulations Section 16000 et seq. (8 CCR Section 16000 et seq.), as amended from time to time.

2.10. DIR Registration and Other Requirements

General Notice to Contractor

City requires Contractor and its Subcontractors to comply with all applicable requirements of the

California Labor Code including but not limited to Labor Code Sections 1720 through 1861, and all applicable related regulations, including but not limited to Subchapter 3, Title 8 of the California Code of

Regulations Section 16000 et seq., as amended from time to time. Additional information regarding public works and prevailing wage requirements is available on the DIR website (see e.g.

http://www.dir.ca.gov) as amended from time to time.

Labor Code Section 1771.1(a)

City provides notice to Contractor of the requirements of California Labor Code section 1771.1(a), which reads:

“A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any contract http://www.dir.ca.gov/DLSR/PWD/index.htm) http://www.dir.ca.gov/

Request for Quotes (RFQ) #RFQ195240 6 for public work, as defined in this chapter, unless currently registered and qualified to perform public work pursuant to Section 1725.5. It is not a violation of this section for an unregistered contractor to submit a bid that is authorized by Section 7029.1 of the Business and Professions Code or Section 10164 or 20103.5 of the Public Contract Code, provided the contactor is registered to perform public work pursuant to Section 1725.5 at the time the contract is awarded.”

DIR Registration Required

City will not accept a bid proposal from or enter into this Construction Contract with Contractor without proof that Contractor and its Subcontractors are registered with the California Department of Industrial

Relations (“DIR”) to perform public work, subject to limited exceptions.

Posting of Job Site Notices; Compliance Monitoring

City gives notice to Contractor and its Subcontractors that Contractor is required to post all job site notices prescribed by law or regulation and Contractor is subject to compliance monitoring and enforcement by DIR.

2.11. Certified Payroll

Contractor shall furnish certified payroll records directly to the Labor Commissioner (DIR) in accordance with Subchapter 3, Title 8 of the California Code of Regulations Section 16461 (8 CCR Section 16461).

City requires Contractor and its Subcontractors to comply with the requirements of Labor Code section

1776, including but not limited to:

i. Keep accurate payroll records, showing the name, address, social security number, work classification, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by, respectively, Contractor and its Subcontractors, in connection with the Project.

ii. The payroll records shall be verified as true and correct and shall be certified and made available for inspection at all reasonable hours at the principal office of

Contractor and its Subcontractors, respectively.

iii. At the request of City, acting by its Project Manager, Contractor and its

Subcontractors shall make the certified payroll records available for inspection or furnished upon request to the City’s Project Manager within ten (10) days of receipt of City’s request.

iv. If the certified payroll records are not provided as required within the 10-day period, then Contractor and its Subcontractors shall be subject to a penalty of one hundred dollars ($100.00) per calendar day, or portion thereof, for each worker, and

City shall withhold the sum total of penalties from the progress payment(s) then due and payable to Contractor. This provision supplements the provisions of Section 15 hereof.

Request for Quotes (RFQ) #RFQ195240 7

v. Inform the City’s Project Manager of the location of Contractor’s and its

Subcontractors’ payroll records (street address, city and county) at the commencement of the Project, and also provide notice to the City’s Project

Manager within five (5) business days of any change of location of those payroll records.

2.12. Employment of Apprentices

Contractor shall comply with the statutory requirements regarding employment of apprentices including without limitation Labor Code Section 1777.5. The statutory provisions will be enforced for penalties for failure to pay prevailing wages and for failure to comply with wage and hour laws.

2.13. Opening of Bids

Electronic Opening

All Bidders and members of the public may view bid results in the electronic procurement system after bid closing. The City reserves the right to change the originally scheduled Bid date and time to a later date and time by issuing an electronic Addendum to that effect. Any and all Quotes received by the City on or before the deadline shall be accepted by the electronic procurement system on the date scheduled for the due date.

2.14. Contract Award

Subject to the conditions of this RFQ, the City will award the contract, if an award is made, to the lowest responsive and responsible Bidder. In determining whether the Bidder is responsible, the City will use the criteria set forth in Palo Alto Municipal Code Section 2.30.440, as set forth below:

1. To have demonstrated the attribute of trustworthiness, and to have the quality, fitness, capacity, experience, and skill to satisfactorily perform the work, or provide the goods and/or services called for in the request for quotes;

2. To have the ability to perform the contract within the time specified;

3. To have the equipment, facilities and resources of such capacity and location to enable the bidder to perform the contract;

4. To have the ability to provide, as required, future maintenance, repair, parts and service for the use of goods purchased;

5. To have a record of satisfactory or better performance under prior contracts with the city or others; and

6. To have complied with applicable laws, regulations, policies (including city policies), guidelines and orders governing prior or existing contracts performed by the bidder.

Request for Quotes (RFQ) #RFQ195240 8

2.15. Determination of Lowest Bid

The lowest bid shall be the lowest total of the bid prices quoted on the Bid Schedule. This total is being used for the purpose of determining the lowest bid for the purchase, delivery, and installation of the new kiln.

2.16. Waiver of Minor Irregularities

The City may exercise its discretion to waive minor irregularities, defects or informalities in the

Bids/Quotes, so long as the waiver would not affect the amount of the Bid or give the Bidder an advantage over others.

2.17. Bid Discrepancies

In the case of a discrepancy between a written amount and the corresponding figures, the written amount shall govern. In the case of a discrepancy between an item price and the corresponding unit price multiplied by the corresponding estimated quantity, the unit price multiplied by the estimated quantity shall govern. In the case of discrepancy between the actual arithmetic total of all items and the total stated by the Bidder, the actual arithmetic total shall govern.

2.18. Award of Contract and Rejection of Bids

Decision to Award

A contract may be awarded to the lowest responsible bidder. The City reserves the right to award more than one Contract with respect to the RFQ.

Decision to Reject

The City reserves the unfettered right to reject all Quotations for any reason or for no reason, to re-advertise an RFQ, or to cancel an RFQ. The City reserves the right to reject as non-responsive any

Quotation which is incomplete, modified, unsigned, or illegible or which is not otherwise submitted in accordance with the requirements of this RFQ.

2.19. Certification of Nondiscrimination

By submitting a quotation, the Bidder certifies that: in the performance of the Contract, if awarded, it shall not discriminate in the employment of any person due to the race, skin color, gender, gender identity, age, religion, disability, national origin, ancestry, sexual orientation, pregnancy, genetic information or condition, housing status, marital status, familial status, weight or height of such person;

and further certifies that it is in compliance with all Federal, State and local laws, regulations, rules, directives and executive orders regarding nondiscrimination in employment.

2.20. Exceptions

To the specifications, scope of work, General Services Agreement or requirements issued must be itemized and justified in writing and included with proposals or quotations submitted.

Request for Quotes (RFQ) #RFQ195240 9

2.21. Performance, Payment Surety Bonds

Within ten (10) business days of issuance of the Notice of Award, the selected Bidder shall furnish City a

Performance Surety Bond, and Payment Surety Bond. Both bonds shall be in the amount of 100% of the

Contract Sum, and in accordance with requirements contained in the General Conditions of this RFQ.

2.22. Liquidated Damages

Pursuant to Public Contract Code Section 7203, if Contractor fails to achieve Final Completion of the entire Work within the Contract Time, including any approved extensions thereto, City may assess liquidated damages on a daily basis for each day of Unexcused Delay in achieving Final Completion, based on the amount of five hundred dollars ($500) per day, or as otherwise specified in the Special

Provisions. Liquidated damages may also be separately assessed for failure to meet milestones specified elsewhere in the Contract Documents, regardless of impact on the time for achieving Final Completion.

The assessment of liquidated damages is not a penalty but considered to be a reasonable estimate of the amount of damages City will suffer by delay in completion of the Work. The City is entitled to setoff the amount of liquidated damages assessed against any payments otherwise due to Contractor, including, but not limited to, setoff against release of retention. If the total amount of liquidated damages assessed exceeds the amount of unreleased retention, City is entitled to recover the balance from Contractor or its sureties. Occupancy or use of the Project in whole or in part prior to Final

Completion, shall not operate as a waiver of City’s right to assess liquidated damages.

2.23. Insurance Requirements

The Bidder awarded the Contract must, for the term of the Contract obtain and maintain insurance with the coverage specified the attachment regarding Insurance Requirements , provided by companies with

AM Best’s key rating of A-:VII, or higher, which are licensed or authorized to transact insurance business in the state of California.

3. SPECIFICATIONS/SCOPE OF WORK

3.1. Art Center Gas Kiln Replacement

SCOPE:

To purchase a new gas kiln to replace existing aging and dying kiln. This purchase is partially funded by the Palo Alto Art Center Ceramics Programs per CIP AC-28003.

Equipment:

A. Geil downdraft kiln model DLB_20

• 20 Cubic feet

• Stacking

• brick lined

• natural draft

• front loading

Request for Quotes (RFQ) #RFQ195240 10

• ETL certified

B. With:

• side damper

• demountable flue

• automatic damper control system with microprocessor

• hood baffle with extension

C. Delivery

D. Removal of old kiln

E. Installation

4. BID FORM

Complete the following line items as part of your electronic submittal. All quotations must be submitted for each line item identified on this form.

QUANTITIES

Quantities as specified are approximate and no guarantee is implied that the exact amount will be purchased.

DELIVERY:

Delivery terms shall be F.O.B. Palo Alto, Freight Prepaid in accordance with the supplied "Terms and

Conditions of Purchase".

Line Item Description Quantity Unit of

Measure Unit Cost Total

1 All items 1 through 8 listed in the bid form.

1 LOT

TOTAL

5. BIDDER'S QUESTIONNAIRE

5.1. Company Type*

Please indicate that which most closely reflects the type for your company.

☐ California Corporation

☐ Corporation Organized under the laws of a State other than California (Provide the name of the State, location of head offices and locations of all offices in California)

☐ Limited Liability Company (Provide list of names of general partners and state which partner or partners are managing partner(s) in "Additional Information" section of Bidder's Questionnaire)

☐ Sole Proprietorship

Request for Quotes (RFQ) #RFQ195240 11

☐ Partnership

☐ Limited Liability Partnership (Provide list of names of general partners and state which partner or partners are managing partner(s) in "Additional Information" section of Bidder's Questionnaire)

☐ Other (Attach applicable information in "Additional Information" section of Bidder's Questionnaire)

*Response required

5.2. Head Office Location*

Please specify where your head office is located.

*Response required

5.3. California Offices*

Please specify, if there are any, where your California offices are located.

*Response required

5.4. Years of Experience Under Current Business Name*

How many years have you (or your company) done business under the name being used to submit?

*Response required

5.5. Years of Similar Experience*

How many years of experience similar to work or services covered in this RFQ?

*Response required

5.6. References*

Please provide relevant references of similar projects satisfactorily completed in the last three (3) years.

For each reference, please provide the following:

• Company Name

• Company Address

• Contact Individual Name

• Contact Phone Number

• Contact Email Address

• Date of Completion of Project or Service

• Contract Amount

*Response required

5.7. Previous Work for City of Palo Alto*

Have you (or your company) previously worked for the City of Palo Alto?

Request for Quotes (RFQ) #RFQ195240 12

☐ Yes

☐ No

*Response required

When equals "Yes"

5.7.1. Previous Work for City of Palo Alto (continued)*

You have indicated that you (or your company) have previously worked for the City of Palo Alto.

Please provide the Position Title you held, the Department in which you worked, Start and End Dates and indicate if you were Full Time or Part Time or worked as a Consultant or indicate some other type of business relationship that applied.

*Response required

5.8. Plants, Facilities, and Equipment*

Please provide a list of the plant(s), and/or facilities, and equipment owned by the Bidder which are available for use in connection with the proposed work as may be required herein.

For each item item on the list, please provide the following:

• Quantity

• Name, Type, Model, Capacity of Item, Facility or Equipment

• Condition

• Location

*Response required

5.9. Management Staff*

Please provide a list of the Bidder's management staff who will manage the proposed work or service.

For each staff member, please be sure to provide the following:

• Full Name

• Field of Expertise

• Capabilities

• Relevant Experience

*Response required

5.10. DIR Registration*

Enter your California Department of Industrial Relations (DIR) Contractor Registration Number.

Please Note:If the City is unable to confirm that the bidder/contractor’s DIR registration is current, the

City must disqualify the bidder, as required by Labor Code section 1725.5.”

*Response required

Request for Quotes (RFQ) #RFQ195240 13

5.11. System for Award Management (SAM) Verification*

Unless an exception applies, no federal funds may go to a person or entity that is suspended or disbarred. Verification of this is provided through www.sam.gov. As part of your submittal please upload verification provided by SAM.gov.

*Response required

5.12. Quote Documents Upload*

Please upload your documents here. This includes warranty information and any other documentation you are uploading as a part of your quote.

*Response required

5.13. Separate Pricing Sheet**

Confirm that your pricing information is not attached in your Bid and is attached separately here.

• 195240_Bid_Form_Art_Center_...

*Response required

5.14. Additional Information

This file upload is for any sections or questions or responses of yours that indicated to provide additional information. Please provide all information by uploading a file here with all required information or your bid may be deemed incomplete and as such non-responsive.

5.15. Bidder Acknowledgement*

In response to this Request for Quotation (RFQ), the undersigned, as Bidder, declares that the only persons or parties interested in this Bid as principals are those named herein; that this Bid is made without collusion with any other person, firm or corporation; that the Bidder has carefully examined the specifications herein referred to; and the Bidder proposes and agrees, if this Bid is accepted, that the

Bidder will contract with the City of Palo Alto (City), to provide all necessary materials, and furnish the specified requirements in this RFQ, in the manner herein prescribed and at the prices stated in the Bid.

☐ Please confirm

*Response required

5.16. Confirmation of Information*

The undersigned certifies under penalty of perjury under the laws of the State of California that all of the answers and responses to all questions and requested information within the Bidder's Questionnaire are true and correct.

*The individual confirming represents and warrants that he or she has the legal capacity and authority to bind the bidder/party submitting the Bid.

☐ Please confirm

*Response required https://government-project.s3.us-west-2.amazonaws.com/192863/87249805-09db-4843-ab12-68cf8da49d41_195240_Bid_Form_Art_Center_Gas_Kiln_Replacement.docx?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=ASIA47RIURE4N7RQZP2X%2F20250903%2Fus-west-2%2Fs3%2Faws4_request&X-Amz-Date=20250903T154817Z&X-Amz-Expires=72000&X-Amz-Security-Token=IQoJb3JpZ2luX2VjEOD%2F%2F%2F%2F%2F%2F%2F%2F%2F%2FwEaCXVzLXdlc3QtMiJIMEYCIQDSJoPetTHc%2B1LFju36o3BNORgbeQGawDKs%2FubT00JL5wIhANDr7ctmkqTO1D6wiZDwt0RQ02DvoilEvxamHwP0I%2FWAKoMFCEkQAhoMODkyMzY0Njg3NjcyIgxPGGA6hHlOAQ%2BoEwkq4ATQvvCFXFYJQLsoPYvnjS2VSZJyL%2BE2RqRoY%2BQqGiCcjpEYaQt15m0tT96B%2FJo2vl1ZhHVn3yVzDiKRMODAKnbmJgJJ4mG4%2Bb58CDzl11cSyN3Uol8jf8L2ogE0Wy4PCPcAZwODHc7y73UdSY1dNncj7YEMw4tK%2Fhuzg%2FWLj0P1qr3O%2FkizoQKuf5ANFvuCky6%2BczoJqaVE9yoR0kmrvdvH0A98hoazsJllkz77FC0fNjHjWi3LM6Dpk19uNVawpw5MSWdQyUD0RDDUW3bXLjNQNiap2GP6UsPD9NvHR3Oy0tJgDwxCTempfJZHOsbz8%2B2odR0Xs2EnzpNPslm2vfT7j%2FRFffoDJltEhUV8d5VuvgqIuyT0IRC%2FKQKOOJSQhMriMhl97T0cpUkL5XK4vjCcR4gssv8q%2FEJk3xHWb4mRlz2Pn0qf5Wrzn0IaFQBqSYJeQTrux7X5t0n2vz0282eNJfqWq%2B77XqQ0CXzaAfSFqGplb%2B2a6WjBF28pVkUcvYY9Kh0Qs65ZWtmS0OVoGI22c0DqTCAdDFK5Ez6qTJ62NPkmsnr73rByFClsGKDclJVCQ0X%2Ba9gnekZQL9LjRxx9VrZtJWn0qpTxU8obPJLXl%2Fhjue9lPMHPdwzxszVziv9X4J7OjTLLwQ4GFm7qUxv4%2B9Be2BsliTLNkNOR80GKN%2Fgd2%2FK9WCyMDqLe2TpPDT87mdTN4cZo0rhEQ3ObR5ASvVufcoYrTmRom8W57uZFJYL0BGAq5ARtqRbPLbExpytDBePYsa%2Fxq%2BNbMwhy0VivPPcr7Qye5tHY%2FrAwV2VHvzC3uuHFBjqaAXuScZkhsWVN3qPLqVrTFpLauk0%2FWJt4RuoKtuJRlCVTubNJJ8JlAdvzjZHcyAv9QhSgX9JykTzOC2G5pMsPXymZl%2BjdaveVP1faE55%2BqZeEYQmzoTg2VG3EWeFJhVrKnb7aTSX%2BjKebvcrHrRn1ddR54W%2F2HfwDcOfR9tdiFQ%2BCDtte2DbBmg2pPnMhhY%2BB6cA%2FvtMrsiU61%2Fw%3D&X-Amz-Signature=27d5f23a411b86bc38730c1a1c017486d6cdb9051d6f194d65750400e82e34cb&X-Amz-SignedHeaders=host&response-content-disposition=attachment%3B%20filename%3D%22195240_Bid_Form_Art_Center_Gas_Kiln_Replacement.docx%22&x-id=GetObject

Request for Quotes (RFQ) #RFQ195240 14

Text133

File details come from the government source that posted it. Updated .