About this file

This document outlines the requirements for subrecipients of funding from the American Rescue Plan Act (ARPA) through the Virginia Department of Health (VDH). It covers general obligations, audit and financial management requirements, equipment management, contracting, monitoring and reporting, and project wrap-up procedures that subrecipients must follow. Key reporting requirements include quarterly updates on project timelines, locations, speeds and pricing for broadband projects, and environmental permit information for water and sewer projects. Subrecipients must also prepare and submit ARPA financial, performance, and compliance reports within 30 days of each quarter.

The related state and local contract opportunity is for a Well Installation project (2022-SWR-31W) in Giles County, Virginia. This contract seeks to procure well installation services, but no further details are provided about the specific scope of work, quantities, response deadlines, or contract term.

View the file

Other files

File Type Posted
SPECIAL TERMS AND CONDITIONS.docx DOCX document
2022-SWR-31W_SOW_Well Installation.docx DOCX document
General Terms and Conditions .docx DOCX document
2022-SWR-31W_SOW_Well Installation.docx DOCX document
REDACTED 2022-SWR-31W UPDATED Permit.pdf PDF
Construction Terms and Conditions-.docx DOCX document
General Terms and Conditions .docx DOCX document
Construction Terms and Conditions-.docx DOCX document
SPECIAL TERMS AND CONDITIONS.docx DOCX document
ARPA FUNDING-.docx DOCX document
REDACTED 2022-SWR-31W UPDATED Permit.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ARPA FUNDING

· General Obligations

· Adopt and abide by a conflicts of interest policy, prohibiting subrecipients from competing for awards or grants in which they develop or draft specifications, requirements, or statements of work [See 2 CFR 2 CFR 200.319(b)].

· Audit/Financial Management

· The subrecipient makes audit reports available for public inspection [See 2 CFR 200.507].

· Make subrecipient’s personnel available to speak with federal auditors [See 2 CFR 200.508(d)].

· Document any material deviations from budget or project scope or objective, and request prior approval from VDH [See 2 CFR 200.308(b)]

· Equipment Management

· Procure insurance policies for equipment purchased with federal funds equal to the value of such equipment for the duration of the project [See 2 CFR 200.310]

· Maintaining equipment records that include equipment description, a serial number or other identification number, Federal funding source (if applicable), the acquisition date, acquisition cost, location, and equipment condition [See 2 CFR 200.313(d)]

· At least every two years, take a physical inventory of equipment and reconcile the results with equipment records [See 2 CFR 200.313(d)]

· Contracting

· Incentivize cost reductions and opportunities to reduce operating cost going forward [e.g., see 2 CFR 200.318(g)]

· Describe the process by which VDH may withhold payments, including determining unallowable costs, from a subrecipient and the subrecipient’s options to appeal such a decision [See 2 CFR 200.305(b)(6) and 2 CFR 200.410]

· Monitoring/Reporting

· Relate financial data and accomplishments to performance goals and objectives when preparing periodic reports [See 2 CFR 200.329(b)]

· Conduct onsite technical inspections and gain certified percentage of completion data to monitor for construction project completion [See 2 CFR 200.329(d)]

· Inform VDH if the supported activity is significantly impacted by unforeseen positive or negative events [See 2 CFR 200.329(e)]

· Quarterly reporting for all subrecipient ARPA funded Water, Sewer, and Broadband projects include: (1) Projected/actual construction start date; (2) Projected/actual initiation of operations date; (3) Location (for broadband, geospatial location data); (4) Labor documentation requirements for projects over $10 million [See SLFRF Compliance and Reporting Guidance, pg. 21]

· Quarterly reporting for all subrecipient ARPA funded Broadband projects include:(1) Speeds/pricing tiers to be offered; (2) Technology to be deployed; (3) Miles of fiber; (4) Cost per mile; (5) Cost per passing; (6) Number of households projected to have increased access to broadband (7) Number of institutions and businesses projected to have increased access to broadband [See SLFRF Compliance and Reporting Guidance, pg. 22]

· Quarterly reporting for all subrecipient ARPA funded Water and/or Sewer projects include: (1) National Pollutant Discharge Elimination System (NPDES) Permit Number for projects aligned with the Clean Water State Revolving Fund; (2) Public Water System (PWS) ID number for projects aligned with the Drinking Water State Revolving Fund [See SLFRF Compliance and Reporting Guidance, pg. 22]

· Ensure subrecipients prepare, complete, and submit ARPA SLFRF financial, performance, and compliance reporting within 30 days of each quarter [See SLFRF Compliance and Reporting Guidance, pg. 9]

· Project Wrap-up

· Remit the value of any unused supplies in excess of $5,000 to VDH [See 2 CFR 200.314(a)]