AppendixA_IFB26-0519_Chiller-Boyce.pdf

PDF 6 MB Posted

Attached to
Invitation for Bids #26-0519 Chiller: Boyce Elementary School
Solicitation number
IFB-118894
Issued by
Clarke County, Virginia

About this file

Summary of Appendix A - IFB26-0519 Chiller Replacement Technical Specifications

This document is a set of technical design drawings and specifications prepared by the Commonwealth of Virginia Professional Engineer for Clarke County Public Schools' chiller replacement project at Boyce Elementary School located at 119 W. Main St., Boyce, VA 22620. The project scope includes the complete removal of the existing chiller unit, chiller supports, and associated accessories while retaining the existing chilled water pump, concrete pad, chain link fence, disconnect switch, and Building Automation System (BAS) wiring for reuse. The new work requires the installation of a replacement chiller with vibration isolators on the existing concrete slab, new power wiring and water-tight conduit from the existing disconnect to the new chiller, connection of existing BAS wiring to the new chiller with extended wiring and conduit as necessary, and installation of new 3-inch chilled water supply and return piping with heat trace and insulation. The project is governed by the 2021 Virginia Existing Building Code (VEBC) and includes mechanical and electrical work with detailed plans for basement mechanical room demolition and new work, piping diagrams, and electrical modifications to existing panelboards and circuits.

The electrical work encompasses removal of the existing 250-amp three-pole breaker supporting the old chiller and installation of a new 300-amp three-pole breaker (Eaton/Westinghouse CAT.KT3300T) in Panel A, installation of three #350KCMIL conductors with #4 ground in 3.0-inch conduit from the new breaker to the chiller's integral breaker disconnect, extension of existing control power sources and heat trace power sources to the new chiller unit, and provision of a 20-amp single-pole breaker for the new evaporator heater. All contractors are required to visit the site prior to bid submission to verify existing conditions and determine the full extent of demolition and relocation work required, with no change orders approved for additional work due to contractor failure to conduct pre-bid site visits. All new wiring must utilize simpul or equal impregnated color-coded insulation without color tape, and all panel schedules must be typed with updated nameplates reflecting the scope of work.

View the file

Other files

File Type Posted
IFB_26-0519_Chiller-Boyce.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DESIGNED DRAWN

APPROVEDCHECKED

COMM. NO. DATE

SHEET

B O

Y C

E E

LE

M

E N

T A

R Y

S C

H O

O L

C H

IL

LE

R R

E P

LA

C

E M

E N

T B

O Y

C E

, V

IR

G

IN

IA

REVISION DATE

26101.10 04-21-26C O M M O

N W

EA

LTH OF

V

IR

G I N I A

P R O

F E

SS IONAL E

N G

IN

E R E

04/21/26

C O M M O

N W

EA

LTH OF

V

IR

G I N I A

P R O

F E

SS IONAL E

N G

IN

E R E

04/21/26

T001

T

IT

LE

S

H E

E T

JLK/MAR WBS

RCH LPA

BOYCE

ELEMENTARY

SCHOOL

INDEX OF DRAWINGS

T001 TITLE SHEET

M001 MECHANICAL LEGEND, SCHEDULES, CONTROLS & PIPING DIAGRAMS

M101 MECHANICAL PARTIAL BASEMENT PLANS & PIPING DIAGRAMS

M102 MECHANICAL DETAILS AND DIAGRAMS

E001 ELECTRICAL LEGEND, NOTES AND ABBREVIATIONS

E101 ELECTRICAL PARTIAL BASEMENT PLANS DEMO AND NEW WORK

BOYCE ELEMENTARY SCHOOL

CHILLER REPLACEMENT

119 W. MAIN ST.

BOYCE, VA 22620

VICINITY MAPVICINITY MAP

BOYCE VA.

CODE GOVERNING NEW WORK: 2021 VIRGINIA EXISTING BUILDING CODE (VEBC)

CODE GOVERNING ORIGINAL WORK:

VIRGINIA FIRE SAFETY REGULATIONS (VSFR)

CODE MODIFICATIONS FOR EXISTING WORK: NONE KNOWN

BOILER ROOM PUMP ROOM

C W

S

C W

R

CH-1

AS

CWP

3" CWR

3" CWS

3" CWS

DEMOLITION PLAN NOTES: X

1. REMOVE CHILLER, CHILLER SUPPORTS, AND ACCESSORIES COMPLETE. REMOVE

POWER WIRING BACK TO DISCONNECT, RETAIN DISCONNECT FOR REUSE. RETAIN

BAS WIRING FOR REUSE. CONCRETE PAD AND CHAIN LINK FENCE TO REMAIN.

2. REMOVE PIPING, PIPE INSULATION, SUPPORTS, AND ACCESSORIES COMPLETE TO

POINTS INDICATED.

3. CHILLED WATER PUMP TO REMAIN FOR REUSE.

DISC

BOILER ROOM PUMP ROOM

CWP

DISC

CH-1

3" CWR

3" CWS

3" CWS

3" CWR

AS

ET

3"CWS

NEW WORK PLAN NOTES:

1. FURNISH AND INSTALL NEW CHILLER WITH VIBRATION ISOLATORS ON EXISTING

CONCRETE SLAB. PROVIDE NEW POWER WIRING AND WATER TIGHT CONDUIT

FROM EXISTING DISCONNECT TO NEW CHILLER. CONNECT EXISTING BAS WIRING

TO NEW CHILLER, EXTEND WIRING AND CONDUIT AS NECESSARY. ROUTE NEW 3"

CWS/CWR PIPING FROM NEW CHILLER THROUGH EXISTING WALL OPENINGS.

SUPPORT PIPING FROM GRADE. APPLY HEAT TRACE AND INSULATION TO NEW

PIPING.

2. FURNISH AND INSTALL NEW 3" CWS/CWR PIPING AND INSULATION. ROUTE PIPING

AS HIGH AS POSSIBLE AND CONNECT TO EXISTING AT POINTS INDICATED.

3. CHILLED WATER PUMP TO REMAIN FOR REUSE.

4. FLOOR MOUNTED EXPANSION TANK.

X

DESIGNED DRAWN

APPROVEDCHECKED

COMM. NO. DATE

SHEET

B O

Y C

E E

L E

M E

N T

A R

Y S

C H

O O

L

C H

IL

L

E R

R E

P L A

C E

M E

N T

B O

Y C

E

V

IR

G

IN

IA

REVISION DATE

26101.10 04-21-26

C O M M O

N W

EA

LTH OF

V

IR

G I N I A

P R O

F E

SS IONAL E

N G

IN

E R E

04/21/26

KEY PLAN

BASEMENT MECHANICAL

ROOM - PLAN - DEMOLITION

SCALE: 1/4" = 1'-0"

M101

M E

C H

A N

IC

A

L

P A

R T

IA

L

B A

S E

M E

N T

P L

A N

S D

E M

O A

N D

N E

W W

O R

K

RCH RCH / WBS

RCH LPA

BASEMENT MECHANICAL

ROOM - PLAN - NEW WORK

SCALE: 1/4" = 1'-0"

C W

S

HVAC CHILLED WATER FLOW PIPING SCHEMATIC (PROVIDE ALL VALVES, SWITCHES,

GAUGES AND PIPING SPECIALITIES SHOWN ON THIS SCHEMATIC)

1"

1"

CWR

1"

C W

R

CW

1"

CWR

1 1/2"1 1/2"1 1/2"

C W

S

C W

R

CWS CWS

NO SCALE

DIFFERENTIAL PRESSURE

SENSOR (INSTALLED AT THE 2/3

POINT IN THE PIPING SYSTEM

2" DRAIN TO

FLOOR DRAIN

TO BUILDING

COOLING SYSTEMS

GLOBE VALVE

BYPASS LINE

PRESSURE REDUCING VALVE (FILL)

EXTEND TO DOMESTIC COLD

WATER MAIN (SEE PLUMBING

DRAWINGS FOR CONTINUATION)

R

EXTERIOR WALL

FLEXIBLE PIPE

CONNECTOR (TYPICAL)

1/4" BALL VALVE (TYPICAL)

CHP-2

SUCTION DIFFUSER

PRESSURE

GAGE (TYPICAL)

TRIPLE DUTY

VALVE (TYPICAL)

CHILLER

(CH-1)

AIR SEPARATOR (AS)

EXPANSION TANK (ET)

CWR

CWS

C W

R

MOUNT CHILLER ON

CONCRETE PAD AND

RUBBER ISOLATORS

FLEX CONNECTOR (TYP)

3/4" HOSE END

DRAIN VALVE (TYP)

HEAT TRACE ALL ABOVE-

GRADE EXTERIOR

PIPING, 5 WATTS/LINEAR

FOOT AT 120V/1PH,

CHROMALOX, CPR, SELF-

REGULATING HEAT TRACE

OR EQUAL.

TO FLOOR

DRAIN

RELIEF VALVE

FLOW SWITCH

1/4" BALL

VALVE (TYP)

PRESSURE GAUGE (TYP.)

THERMOMETER (TYP.)

SERVICE VALVE (TYP.)

BAS TEMPERATURE

SENSOR (TYP.)

GLOBE VALVE

BYPASS CHEMICAL FEEDER

PIPE INSULATION

(WHERE REQUIRED)

WALL

GALVANIZED STEEL

PIPE SLEEVE

WALL

PIPE

1/4" SPACE BETWEEN

SLEEVE & INSULATION

NOTE:

WHERE PIPES PENETRATE FIRE-RATED WALLS, FILL

SPACE BETWEEN PIPE AND SLEEVE WITH A

FIRE-RESISTANT MATERIAL WITH SUFFICIENT RATING TO

MAINTAIN THE FIRE RATING OF THE WALL. WHERE PIPE

PENETRATE EXTERIOR WALLS, FILL SPACE BETWEEN

PIPE AND SLEEVE WITH FIBERGLASS INSULATION.

WALL PIPE SLEEVE DETAIL

NO SCALE

PIPE SUPPORT DETAIL

NO SCALE

PIPE

VAPOR BARRIER

(WHERE REQUIRED)

12" LONG, HALF-SECTION OF

HYDROUS CALCIUM SILICATE

AT EACH HANGER SUPPORT

HEAVY DUTY

CLEVIS HANGER

HANGER ROD, SUPPORT

FROM BUILDING STRUCTURE

INSULATION

16 GAGE ZINC COATED

SHEET STEEL SADDLE

AT LEAST 12" LONG

NOTE:

SADDLE AND HALF-SECTION OF HYDROUS CALCIUM SILICATE

SHALL BE INSTALLED AT THE SAME TIME THAT THE PIPE AND

PIPE HANGERS ARE INSTALLED.

SEE SPECIFICATIONS FOR LOCATIONS WHERE HYDROUS

CALCIUM SILICATE SHALL BE REQUIRED.

COLD WATER MAKE-UP DETAIL

NO SCALE

3/4" PIPE TO

EXPANSION TANK

3/4" PIPE FROM

AIR SEPARATOR

3/ 4"

3/4" COLD

WATER MAKE-UP

3/4" CW BYPASS

FILL VALVE

FEEDER BODY

NOTE:

SIZE FILTER FEEDER AS RECOMMENDED BY UNIT MANUFACTURER.

BYPASS CHEMICAL FEEDER

NO SCALE

LID

GLOBE VALVE

3/4" FROM PUMP

DISCHARGE

3/4"

REMOVABLE BASKET

AND FILTER

HOSE END

DRAIN VALVE

3/4" TO PUMP

INTAKE

DESIGNED DRAWN

APPROVEDCHECKED

COMM. NO. DATE

SHEET

B O

Y C

E E

LE

M

E N

T A

R Y

S C

H O

O L

C H

IL

LE

R R

E P

LA

C

E M

E N

T B

O Y

C E

, V

IR

G

IN

IA

REVISION DATE

26101.10 04-21-26

C O M M O

N W

EA

LTH OF

V

IR

G I N I A

P R O

F E

SS IONAL E

N G

IN

E R E

04/21/26

M102

M E

C H

A N

IC

A

L D

E T

A

IL

S A

N D

D

IA

G R

A M

S

RCH RCH / WBS

RCH LPA

1 PLAN NOTE DESIGNATION.

NOTES (ELECTRICAL LEGEND):

1. THESE ARE STANDARD ELECTRICAL SYMBOLS AND MAY NOT ALL APPEAR ON THE PROJECT DRAWINGS. HOWEVER, WHEREVER AN ELECTRICAL SYMBOL APPEARS ON THE PROJECT DRAWINGS, THE ITEM SHALL BE FURNISHED AND INSTALLED.

2. MOUNTING HEIGHTS NOTE IN THIS SCHEDULE ARE FROM FINISHED FLOOR TO TOP OF OUTLET OR EQUIPMENT, UNO. WHERE

THE MOUNTING HEIGHT INDICATED ON THE DRAWINGS IS DIFFERENT FROM THE LEGEND, THE DRAWING TAKES PRECEDENT.

SEE DRAWINGS FOR MOUNTING HEIGHTS NOT INDICATED IN THE LEGEND. MOUNTING HEIGHT NOTED ON THE DRAWINGS ARE

FROM FINISHED FLOOR TO TOP OF DEVICE.

3. SEE ELECTRICAL ABBREVIATIONS FOR ALPHABETIC SUBSCRIPT WITH SYMBOL, UNO.

4. REFER TO DETAILS ON DRAWINGS FOR ADDITIONAL INFORMATION.

1 REVISION DESIGNATION.

ASTERISK DENOTES BOTTOM OF OUTLET BOX MOUNTED 8 IN. ABOVE TOP OF COUNTER.

DISTANCE INCLUDES HEIGHT OF BACKSPLASH.

MTG. HGT. SYMBOL DESCRIPTION

NEW CONNECTED TO EXISTING AT THIS POINT.

EXISTING REMOVED FROM THIS POINT.

208/120 VOLT SURFACE OR FLUSH MOUNTED PANELBOARD.6'-0" TO TOP

480/277 VOLT SURFACE OR FLUSH MOUNTED PANELBOARD.6'-0" TO TOP

CIRCUIT DESIGNATION. DESIGNATION SHOWN INDICATES PANEL NLA1A AND CIRCUIT

NUMBER 3.

NLA1A-3

ELECTRICAL LEGEND - GENERAL

NOTE (ELECTRICAL ABBREVIATIONS):

ELECTRICAL ABBREVIATIONS

1. ALL ABBREVIATIONS LISTED MAY NOT APPLY TO THIS PROJECT. REFER TO OTHER ABBREVIATION

LISTS ELSEWHERE IN THESE DOCUMENTS FOR ABBREVIATIONS NOT LISTED HERE.

AIC

GND

C

EF

A OR AMP GROUND

CONDUIT

EXHAUST FAN

AMPERES INTERRUPTING CAPACITY

AMPERE

MAIN LUGS ONLY

WATT OR WIRE

PHASE

MLO

PH

WEXIST TO REMAINER

VOLTV

ATS AUTOMATIC TRANSFER SWITCH

MAIN CIRCUIT BREAKERMCB

KILOVOLT-AMPEREKVA

GENERAL NOTES:

1. ALL VFD'S WILL BE FURNISHED BY THE MECHANICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR SHALL MOUNT THE

VFD'S (UNLESS THEY ARE INTEGRAL TO THE EQUIPMENT SERVED). CONNECT THE LINE SIDE POWER WIRING AND THE

LOAD SIDE POWER WIRING FROM THE VFD'S TO THE EQUIPMENT. ALL CONTROL AND INTERLOCK WIRING FOR THE VFD'S

WILL BE BY THE CONTROL SYSTEM CONTRACTOR.

2. LOAD SIDE CONDUCTOR AND CONDUIT SIZES FROM DISCONNECT SWITCHES, STARTERS AND VFD'S TO EQUIPMENT SHALL

BE THE SAME AS LINE SIDE CONDUCTORS AND CONDUIT.

3. CAREFULLY COORDINATE ALL ELECTRICAL EQUIPMENT LOCATIONS WITH DUCTWORK, PIPING AND MECHANICAL

EQUIPMENT. MAINTAIN ALL CLEARANCES AND SPACES REQUIRED BY THE NEC.

4. WHERE MULTIPLE CIRCUITS ARE COMBINED IN A SINGLE CONDUIT, DERATE CONDUCTORS PER THE NEC.

5. WHERE RE-USE OF EXISTING CONDUIT, WIRING AND/OR OUTLET BOXES IS INDICATED, ALSO PROVIDE NEW MATERIALS IF

NECESSARY. IF NEW EXPOSED MATERIALS ARE NEEDED, USE SURFACE RACEWAY (SINGLE-CHANNEL EXCEPT WHERE

SPECIFICALLY INDICATED OTHERWISE), EXCEPT EXPOSED CONDUIT AND BOXES MAY BE USED IN UNFINISHED AREAS

(MECHANICAL/ELECTRICAL/IT ROOMS, STORAGE AND HOUSEKEEPING CLOSETS, ETC.).

6. PROVIDE ALL 120-VOLT POWER NEEDED BY THE BAS. COORDINATE WITH THE CONTROLS SPECIFICATIONS AND

CONTRACTOR.

7. MODIFY EXISTING PANEL SCHEDULES TO ACCURATELY REFLECT ALL CHANGES MADE AS PART OF THIS CONTRACT. ALL

NEW BREAKERS IN EXISTING PANELS SHALL MATCH EXISTING AIC. PROVIDE NEW "TYPED" AS-BUILT PANEL SCHEDULES, HANDWRITTEN PANEL SCHEDULES WILL NOT BE ACCEPTED.

8. THE CONTRACTOR SHALL VISIT THE SITE PRIOR TO SUBMITTING BID IN ORDER TO VERIFY ALL EXISTING CONDITIONS, TO

DETERMINE THE FULL EXTENT OF DEMOLITION WORK REQUIRED, AND TO DETERMINE THE FULL EXTENT OF RELOCATION

AND MODIFICATION WORK REQUIRED FOR ELECTRICAL WORK (DUE TO OTHER DISCIPLINES INTERFERING OR ANY OTHER

REASON). EXISTING SPACE IS TIGHT IN MANY AREAS (PARTICULARLY ABOVE CEILINGS), AND THE CONTRACTOR SHALL BE

FULLY RESPONSIBLE TO COORDINATE ALL ELECTRICAL WORK WITH BOTH NEW AND EXISTING PIPING, DUCTWORK, CONDUIT, ETC. NO CHANGE ORDERS WILL BE APPROVED FOR ADDITIONAL WORK DUE TO THE CONTRACTOR NEGLECTING

TO VISIT THE SITE AND GATHER ALL NECESSARY INFORMATION.

9. THE CONTRACTOR SHALL PROVIDE COVERPLATES ON ALL EXISTING JUNCTION BOXES ABOVE THE ACCESSIBLE CEILING

SPACES AND ANY WALL MOUNTED BOXES IN THE AREA OF RENOVATIONS WHERE EXISTING COVERPLATES ARE MISSING.

THE CONTRACTOR SHALL ALSO PROVIDE ADDITIONAL SUPPORTS FOR EXISTING CONDUIT AND JUNCTION BOXES IN THE

AREA OF RENOVATIONS THAT CURRENTLY DO NOT MEET CODE REQUIREMENTS.

10. WHERE EXISTING CIRCUITS ARE SPECIFIED TO BE REUSED FOR THE AREA OF RENOVATIONS AND THE CONTRACTOR

DISCOVERS IN THE FIELD THAT THE CIRCUITS DO NOT MEET CODE, OR THEY HAVE SHARED NEUTRALS, OR THEY ARE

MISSING A GROUND CONDUCTOR THE CONTRACTOR SHALL PROVIDE NEW CONDUIT AND WIRING FROM THE PANEL TO

THE EXISTING AND NEW ELECTRICAL EQUIPMENT. ALL NEW CIRCUITS SHALL MEET SPECIFICATIONS FOR VOLTAGE DROP

FOR SINGLE-PHASE WIRING.

GENERAL DEMOLITION NOTES:

1. SCOPE : THE SCOPE OF ELECTRICAL DEMOLITION IS DEFINED IN THE FOLLOWING NOTES AND IN LIMITED FASHION ON THE

DRAWINGS; THE DRAWINGS ARE ONLY INTENDED TO BE A PARTIAL REPRESENTATION OF THE ACTUAL DEMOLITION WORK

REQUIRED. THESE NOTES ONLY APPLY TO THE AREAS OF RENOVATION. IN GENERAL, THE DEMOLITION SCOPE IS THE

REMOVAL OF THE ELECTRICAL CONNECTIONS TO THE EXISTING CHILLER AND THE EXISTING CHILLED WATER PUMPS, EXCEPT AS NOTED OTHERWISE IN THESE NOTES AND ON THE DRAWINGS.

2. MECHANICAL EQUIPMENT : DISCONNECT EXISTING MECHANICAL EQUIPMENT THAT IS BEING REMOVED, AND REMOVE ALL

ASSOCIATED STARTERS, DISCONNECTS, ETC. CONDUIT AND CONDUCTORS TO REMOVED MECHANICAL EQUIPMENT SHALL BE

REUSED ONLY WHERE SPECIFICALLY INDICATED. SEE MECHANICAL DRAWINGS FOR MORE INFORMATION. UNLESS

SPECIFICALLY INDICATED OTHERWISE, EXISTING WIRING TO EXISTING-TO-REMAIN EQUIPMENT SHALL REMAIN.

3. ELECTRICAL SERVICE : THE EXISTING ELECTRICAL SERVICE SHALL BE RE-USED, BUT SOME DOWNTIME WILL LIKELY STILL BE

REQUIRED. ALL ELECTRICAL SERVICE DOWNTIME REQUIRED SHALL BE COORDINATED WITH OWNER AND SHALL BE AT THE

OWNER'S CONVENIENCE. DOWNTIME SHALL BE KEPT TO THE MINIMUM. ALL EXTENDED DOWNTIME REQUIRED SHALL BE

COORDINATED WITH OWNER AND SHALL BE OUTSIDE OF NORMAL SCHOOL HOURS.

4. PANELBOARDS : ALL EXISTING PANELBOARDS ARE TO REMAIN. EXISTING PANELBOARDS ARE TO BE MODIFIED AS INDICATED

ON FLOOR PLANS AND PANEL SCHEDULES. WHERE EXISTING PANELBOARDS ARE TO REMAIN UPDATE THE CIRCUIT

DIRECTORIES TO REFLECT ALL AS-BUILT/EXISTING CIRCUIT CHANGES, ALL REVISED CIRCUIT DIRECTORIES SHALL BE "TYPED"

NOT HANDWRITTEN. CIRCUIT CHANGES INCLUDE, BUT IS NOT LIMITED TO, MOVING EXITING LOADS IN EXISTING PANELS, REMOVING EXISTING LOADS FROM AN EXISTING PANELS, ADDING NEW LOADS TO EXISTING PANELS, CHANGING BREAKERS IN

EXISTING PANELS, ETC. EXISTING CIRCUITS NO LONGER BEING USED AFTER DEMOLITION WORK SHALL BE MADE "SPARES"

AND SHALL BE PLACED IN THE "OFF" POSITION. PROVIDE BLANK PLATES FOR ALL EXISTING CIRCUIT BREAKERS BEING

REMOVED.

5. CONDUIT : ALL ACCESSIBLE UNUSED CONDUIT SHALL BE REMOVED; ALL INACCESSIBLE UNUSED CONDUIT SHALL BE

ABANDONED. ALL CONDUIT TO NEW DEVICES AND EQUIPMENT SHALL BE NEW, UNLESS NOTED OTHERWISE TO BE REUSED.

6. WIRING : ALL WIRING TO DEMOLISHED DEVICES AND EQUIPMENT SHALL BE REMOVED, UNLESS NOTED OTHERWISE. ALL

EXISTING WIRING TO EXISTING-TO-REMAIN DEVICES AND EQUIPMENT SHALL REMAIN, UNLESS NOTED OTHERWISE. ALL

ACCESSIBLE UNUSED WIRING SHALL BE REMOVED; ALL INACCESSIBLE UNUSED WIRING SHALL BE ABANDONED. ALL WIRING

TO NEW DEVICES AND EQUIPMENT SHALL BE NEW, UNLESS NOTED OTHERWISE.

7. MAINTAIN CIRCUIT CONTINUITY AS NECESSARY IN ALL DEMOLITION WORK.

8. THE CONTRACTOR SHALL INFORM THE OWNER'S REPRESENTATIVE OF ELECTRICAL EQUIPMENT REMOVED FROM THE

BUILDING. IF THE OWNER DESIRES TO RETAIN EQUIPMENT, HE WILL REMOVE IT FROM THE SITE. ALL EQUIPMENT NOT

RETAINED BY THE OWNER SHALL BECOME PROPERTY OF THE CONTRACTOR AND SHALL BE REMOVED FROM THE SITE.

DISPOSAL OF ALL EQUIPMENT CONTAINING HAZARDOUS MATERIALS SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR, AND THE COST OF DISPOSAL SHALL BE INCLUDED.

9. INFORMATION ON DEMOLITION DRAWINGS DOES NOT INDICATE ALL EXISTING EQUIPMENT AND DEVICES. REFER TO

ARCHITECTURAL AND MECHANICAL DEMOLITION DRAWINGS FOR ADDITIONAL INFORMATION.

10. THE CONTRACTOR SHALL VISIT THE SITE PRIOR TO SUBMITTING BID AND SHALL VERIFY ALL DEMOLITION REQUIRED.

ADDITIONAL COMPENSATION WILL NOT BE ALLOWED FOR DEMOLITION DUE TO CONTRACTOR NOT VISITING SITE AND

DETERMINING FULL SCOPE OF DEMOLITION REQUIRED.

11. SEE THE DEMOLITION FLOOR PLANS FOR ADDITIONAL DEMOLITION REQUIREMENTS. ON THE DEMOLITION FLOOR PLANS AND

RISERS, ALL DASHED ITEMS SHALL BE REMOVED AND ALL SOLID ITEMS SHALL REMAIN, UNLESS NOTED OTHERWISE. SOME

DEMOLITION ITEMS ARE AFFECTED BY ADD ALTERNATES, AS INDICATED IN THE FLOOR PLANS. NEW WORK FLOOR PLANS

MAY CONTAIN ADDITIONAL DEMOLITION INFORMATION IN SOME LOCATIONS.

BAS BUILDING AUTOMATION SYSTEM

DESIGNED DRAWN

APPROVEDCHECKED

COMM. NO. DATE

SHEET

B O

Y C

E E

LE

M

E N

T A

R Y

S C

H O

O L

C H

IL

LE

R R

E P

LA

C

E M

E N

T B

O Y

C E

, V

IR

G

IN

IA

REVISION DATE

26101.10 04-21-26

04/21/26

C O M M O

N W

EA

LTH OF

V

IR

G I N I A

P R O

F E

SS IONAL E

N G

IN

E R E

E001

E

LE

C T

R

IC

A L

LE

G

E N

D , N

O T

E S

A N

D A

B B

R E

V

IA

T

IO

N S

MAR MAR

WAM LPA

PUMP ROOM

CH-1

CWP-1

M M M

M M M

EM

ER

PANEL "A"

EM

A-8

ER

A-1

BOILER ROOM

ER

7 9

BOILER ROOM PUMP ROOM

CWP-1

AS

ET

ER

PANEL "A"

ER

MM

MM

A-8

8 6 6

DESIGNED DRAWN

APPROVEDCHECKED

COMM. NO. DATE

SHEET

B O

Y C

E E

LE

M

E N

T A

R Y

S C

H O

O L

C H

IL

LE

R R

E P

LA

C

E M

E N

T B

O Y

C E

, V

IR

G

IN

IA

REVISION DATE

26101.10 04-21-26

04/21/26

KEY PLAN

C O M M O

N W

EA

LTH OF

V

IR

G I N I A

P R O

F E

SS IONAL E

N G

IN

E R E

BASEMENT ELECTRICAL

ROOM - PLAN - DEMOLITION

SCALE: 1/4" = 1'-0"

E101

E

LE

C T

R

IC

A L

P A

R T

IA

L

B A

S E

M E

N T

P

LA

N S

D E

M O

A N

D N

E W

W O

R K

MAR MAR

RCH LPA

BASEMENT ELECTRICAL L

ROOM - PLAN - NEW WORK

SCALE: 1/4" = 1'-0"

GENERAL NOTES:

A. CONTRACTOR IS RESPONSIBLE FOR REVIEWING THE ENTIRE CONTRACT DOCUMENTS TO HAVE A

COMPLETE UNDERSTANDING OF THE PROJECT SCOPE OF WORK AND SHALL COORDINATE WITH ALL

DISCIPLINES AND THE OWNERS REPRESENTATIVE PRIOR TO ANY WORK.

B. ELECTRICAL DEMOLITION IS DEFINED IN THE FOLLOWING NOTES AND IN LIMITED TO FIELD OBSERVATION

AND ACCESSIBILITY TO THE EXISTING CONDITIONS. THE DRAWINGS ARE ONLY INTENDED TO BE A

PARTIAL REPRESENTATION OF THE ACTUAL DEMOLITION WORK REQUIRED. THESE NOTES ONLY APPLY

TO THE AREAS OF RENOVATION. IN GENERAL, THE DEMOLITION SCOPE IS THE REMOVAL OF EXISTING

LIGHTING AND ASSOCIATED CONTROLS IN THE AREAS OF RENOVATION, EXCEPT AS NOTED OTHERWISE IN

THESE NOTES AND ON THE CONTRACT DOCUMENTS.

C. CONTRACTOR SHALL COORDINATE ALL REQUIRED SHUTDOWNS WITH PROJECT MANAGER/GC AND

OWNER'S REPRESENTATIVE.

D. ALL WIRING FOR ALL SIZES WILL BE SIMPUL OR EQUAL TO IMPREGNATED COLOR CODED INSULATION, FOR EACH VOLTAGE AND PHASES - NO COLOR TAPE WILL BE ACCEPTED - THIS IS TYPICAL FOR THE

ENTIRE SCOPE OF WORK, THIS INCLUDES THE NEW CHILLER AND ASSOCIATED PUMPS.AGAIN COLOR

TAPE WILL NOT BE ACCEPTABLE.

NEW PLAN NOTES:

1. EXISTING ELECTRICAL BRANCH PANEL "A" SHALL REMAIN AS INSTALLED AND WILL SUPPORT THE PROJECT

SCOPE OF WORK. CONTRACTOR IS RESPONSIBLE FOR PROVIDING NEW NAMEPLATES ON THE PANEL -

BLACK FACE WHITE CORE - MINIMUM LETTER SIZE .25". CONTRACTOR IS RESPONSIBLE FOR PROVIDING A

NEW (TYPED) PANEL SCHEDULE REFLECTING THE SCOPE OF WORK, NO HAND WRITTEN ENTRIES WILL BE

ACCEPTED. CONTRACTOR IS NOT RESPONSIBLE FOR CONFIRMING THE EXISTING CONNECTED LOADS, BUT

IS RESPONSIBLE FOR TRANSFERRING THE NOTED EXISTING DESCRIPTION FROM THE EXISTING PANEL

SCHEDULE TO THE NEW PANEL SCHEDULE.

2. THE EXISTING CHILLED WATER PUMP (CWP-1) AND ASSOCIATED COMBINATION STARTER SHALL REMAIN AS

INSTALLED, NO WORK REQUIRED.

3. THE CONTRACTOR SHALL REMOVE THE EXISTING WESTINGHOUSE (CAT.KT3250T) 250A 3 POLE BREAKER IN

PANEL A, THAT WAS SUPPORTING THE EXISTING CHILLER UNIT. THE CONTRACTOR SHALL PROVIDE A NEW

EATON/WESTINGHOUSE (CAT.KT3300T) PLEASE CONFIRM CAT NUMBER, RATED FOR 300A 3 POLE WITH

LONG-TIME AND INSTANTANEOUS SETTINGS), 208V. 65 AKIC RATING. THE CONTRACTOR SHALL MOUNT IN

THE SAME LOCATION OF THE REMOVED 250A 3 POLE. PROVIDE ALL REQUIRED MOUNTING HARDWARE.

4. THE NEW CHILLER SHALL BE PROVIDED WITH A INTEGRAL 300A 3 POLE BREAKER FOR A LOCAL

DISCONNECTION.

5. THE CONTRACTOR SHALL PROVIDE (3) #350KCMIL W/#4 GROUND IN 3.0" CONDUIT FROM THE NEW

ASSIGNED 300A, 3 POLE BREAKER IN THE PANEL A AND TO THE NEW CHILLER'S ONE POINT POWER

SOURCE CONNECTION POINT ON THE PROVIDED INTEGRAL BREAKER, COORDINATE WITH MECHANICAL

CONTRACTOR. THE CONTRACTOR SHALL PROVIDE A MINIMUM OF 6'-0" OF SEAL-TIGHT FLEXIBLE CONDUIT

FROM THE CHILLER'S POWER CONNECTION POINT. THE CONTRACTOR SHALL REFER TO GENERAL NOTE

"D".THE CONTRACTOR SHALL PROVIDE A TECHNOLOGY DROP AT THE CHILLER CONTROL CABINET, COORDINATE WITH OWNER'S "IT" FOR AVAILABILITY.

6. THE CONTRACTOR SHALL INTERCEPT AND EXTEND THE EXISTING RETAIN POWER SOURCES (PANEL A -5)

NOTED IN THE DEMOLITION NOTES 7 TO THE NEW CHILLER'S CONTROLS PANEL. THE CONTRACTOR SHALL

MATCH THE EXISTING CONDUCTORS, CU, 75 DEGREE, ETC. THE CONTRACTOR SHALL PROVIDE A MINIMUM

OF 6'-0" OF SEAL-TIGHT FLEXIBLE CONDUIT FROM THE CONTROL PANEL'S POWER CONNECTION POINT.

7. THE CONTRACTOR SHALL INTERCEPT AND EXTEND THE EXISTING RETAIN POWER SOURCES (PANEL A

-14/16/18) NOTED IN THE DEMOLITION NOTES 8 TO THE NEW CHILLER'S HEAT TRACE SYSTEM. THE

CONTRACTOR SHALL COORDINATE WITH MECHANICAL CONTRACTOR FOR POWER CONNECTION POINTS

ON THE PROVIDED HEAT TRACE SYSTEM. THE CONTRACTOR SHALL MATCH THE EXISTING CONDUCTORS, CU, 75 DEGREE, ETC. THE CONTRACTOR SHALL PROVIDE A MINIMUM OF 6'-0" OF SEAL-TIGHT FLEXIBLE

CONDUIT FROM THE CONTROL PANEL'S POWER CONNECTION POINT.

8. THE CONTRACTOR SHALL PROVIDE A 20A SINGLE POLE BREAKER IN POSITION #41 IN EXISTING BRANCH

PANEL-A TO SUPPORT THE NEW EVAPORATOR HEATER ON THE NEW CHILLER UNIT.

9. THE CONTRACTOR SHALL PROVIDE (2)#12 W/#12 GROUND IN .75" CONDUIT FROM THE ASSIGNED 20A

SINGLE BREAKER #41 TO THE CHILLER UNIT'S EVAPORATED HEATER'S POWER CONNECTION POINT. THE

CONTRACTOR SHALL PROVIDE A MINIMUM OF 6'-0" OF SEAL-TIGHT FLEXIBLE CONDUITS FROM THE

EVAPORATOR HEATER'S CONNECTION POINT.

10. THE CONTRACTOR SHALL MAKE ALL EXTERIOR WALL PENETRATIONS WEATHER/WATER TIGHT.

DEMOLITION PLAN NOTES:

1. EXISTING ELECTRICAL BRANCH PANEL "A" SHALL REMAIN AS INSTALLED AND WILL SUPPORT THE PROJECT

SCOPE OF WORK. CONTRACTOR IS RESPONSIBLE FOR PROVIDING NEW NAMEPLATES ON THE PANEL -

BLACK FACE WHITE CORE - MINIMUM LETTER SIZE .25". CONTRACTOR IS RESPONSIBLE FOR PROVIDING A

NEW (TYPED) PANEL SCHEDULE REFLECTING THE SCOPE OF WORK, NO HAND WRITTEN ENTRIES WILL BE

ACCEPTED. CONTRACTOR IS NOT RESPONSIBLE FOR CONFIRMING THE EXISTING CONNECTED LOADS, BUT

IS RESPONSIBLE FOR TRANSFERRING THE NOTED EXISTING DESCRIPTION FROM THE EXISTING PANEL

SCHEDULE TO THE NEW PANEL SCHEDULE.

2. THE EXISTING CHILLED WATER PUMP (CWP-1) AND ASSOCIATED COMBINATION STARTER SHALL REMAIN AS

INSTALLED, NO WORK REQUIRED.

3. THE CONTRACTOR SHALL SAFE-OFF THE EXISTING 250A, 3 POLE BREAKER SUPPORTING THE EXISTING TO

BE REMOVED CHILLER UNIT, LOCATED IN BRANCH PANEL "A" WESTINGHOUSE POW-R-LINE C PRL4, RATED

FOR 800A, 208/120V, 3 PHASE, 4 WIRE, 42AIC - MLO.

4. THE CONTRACTOR SHALL DISCONNECT AND REMOVE THE EXISTING CHILLER'S 300 KCMIL FEEDER

CONDUCTORS AND ASSOCIATED CONDUIT FROM THE ASSIGNED 250A BREAKER IN THE PANEL "A" TO THE

EXTERIOR MOUNTED NON-FUSED DISCONNECT SWITCH FROM THE LINE-SIDE.

5. THE CONTRACTOR SHALL DISCONNECT AND REMOVE THE EXISTING CHILLER'S 300KCMIL FEEDER

CONDUCTORS FROM THE LOAD-SIDE OF THE LOCAL DISCONNECT SWITCH AND FROM THE CHILLER'S

POWER CONNECTION POINT.

6. THE CONTRACTOR DISCONNECT AND REMOVE THE EXTERIOR MOUNTED NON-FUSED DISCONNECT SWITCH.

7. THE CONTRACTOR SHALL LABEL, DISCONNECT AND COIL BACK POWER SOURCE FROM THE CHILLER'S

CONTROL PANEL BACK TO THE EXTERIOR WALL MOUNTED DOUBLE GANG FS BOX. REMOVE THE CONDUIT

BACK TO THIS JUNCTION AS WELL. THE ASSIGNED CIRCUIT IS PANEL A, CIRCUIT #5, 20A SINGLE POLE. THIS

POWER SOURCE SHALL BE RETAIN AND EXTENDED TO THE NEW CHILLER'S CONTROL PANEL.

8. THE CONTRACTOR SHALL LABEL, DISCONNECT AND COIL BACK POWER SOURCE FROM THE CHILLER'S HEAT

TRACE BACK TO THE EXTERIOR WALL MOUNTED DOUBLE GANG FS BOX. REMOVE THE CONDUIT BACK TO

THIS JUNCTION AS WELL. THE ASSIGNED CIRCUIT IS PANEL A, CIRCUIT #14/16/16, 30A 3 POLE. THIS POWER

SOURCE SHALL BE RETAIN AND EXTENDED TO THE NEW CHILLER'S CONTROL PANEL.

9. THE CONTRACTOR SHALL RETAIN POWER SOURCE WIRING AND ASSOCIATED CONDUIT FROM THE

ASSIGNED PANEL A TO THE EXTERIOR WALL MOUNTED DOUBLE GANG FS BOX.

T001
M001
M101
M102
E001
E101

File details come from the government source that posted it. Updated .