This document is a Client Draft Summary Report for Lead-Containing Paint (LCP) Surveys conducted by the U.S. Army Corps of Engineers at Surry Mountain Lake in Surry, NH on November 7, 2016. The survey involved examining seven structures and one bridge, with a total of 88 X-ray fluorescence (XRF) readings taken to detect lead-containing paint. The inventory details various components such as metal structures, door frames, railings, and fence brackets, documenting their substrate, condition, color, and lead concentration levels.

The report provides a comprehensive photo log of the surveyed components, including wainscoting, door jams, desks, storage cabinets, work benches, and privacy fence brackets. Each component is identified with a sample number, building number, and precise location. The XRF readings range from 0.4 to >9.9 mg/cm2, with most components found to be in intact condition and made of metal or wood substrates. The survey was conducted as part of Contract No. W912WJ-16-D-0004 TO#0003 by Mabbett & Associates, Inc. on behalf of the U.S. Army Corps of Engineers for the Upper Connecticut River Basin project.

View the file

Other files

File Type Posted
Amendment W912WJ25QA063-0002.pdf PDF
Amendment W912WJ25QA063-0001.pdf PDF
Appendix C- Informational Photos.pdf PDF
Appendix A - MAPS.pdf PDF
Solicitation - W912WJ25QA063.pdf PDF
Appendix B-Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CLIENT DRAFT SUMMARY REPORT

LEAD-CONTAINING PAINT SURVEYS

U.S. Army Corps of Engineers (USACE) Upper Connecticut River Basin | Various Locations

© 2017, Mabbett & Associates, Inc. 1 February 2017 Contract No. W912WJ-16-D-0004 TO#0003 APPENDIX A - SURRY MOUTAIN LAKE LCP INVENTORY Project No. R7063003.000.001 US Army Upper CT River Basin Lead Survey Report - FINAL DRAFT

Surry Mountain Lake On November 7, 2016, a limited LCP survey was performed at the Surry Mountain Lake location (Project office at 108 Surry Dam Road, Surry, NH 03431). During this survey seven (7) structures and one (1) bridge were surveyed and a total of 88 XRF readings were taken, including calibration checks. Building components testing positive for LCP are provided in the inventory below, along with their quantity, condition, substrate, color, and highest measured lead concentration. A photo log of each LCP component is also provided in this Appendix.

LCP Inventory Surry Mountain Lake

Project Office - 108 Surry Dam Road, Surry, NH 03431

Sample # Building BLD

# Component Substrate Condition Color

XRF

Reading (mg/cm2)

2nd XRF Reading

(mg/cm2) Quantity Unit

SM1-

01 Gatehouse 1 Bridge - Steel Metal Intact Silver 5.8 1 EA

SM1-

05 Gatehouse 1 Air Vent

Grate Metal Deteriorated Green >9.9 15 EA

SM1-

07 Gatehouse 1 Gate

Operators Metal Intact Green >9.9 1 EA

SM1-

08 Gatehouse 1 Door Frame

(In/Out) Metal Intact Green >9.9 34 LF

SM1-

09 Gatehouse 1 Floor Grating Metal Intact Green 8.0 1 EA

SM1-

10 Gatehouse 1 Floor Tracks Metal Deteriorated Green 3.3 1 EA

SM1-

11 Gatehouse 1 Stairwell

Railing Metal Intact Green 8.9 1 EA

SM1-

12 Gatehouse 1 Lower Level

Door Metal Intact Green 1.0 19 LF

SM1-

13 Gatehouse 1 Lower Level

Door Frame Metal Intact Green 6.0 19.5 LF

SM1-

16 Gatehouse 1 Lower Level

Hand Rails Metal Deteriorated Gray 1.5 1 EA

SM1-

18 Gatehouse 1 Doorway

Threshold Concrete Intact Yellow 3.7 5.5 LF

SM1-

19 Gatehouse 1 Shelf Wood Intact Green 1.8 3 LF

SM1-

20 Gatehouse 1 Cabinet Metal Intact Green 1.0 16 LF

SM1-

24 Gatehouse 1 Table Legs Metal Intact Green 1.6 16 LF

SM2-

Project Office 2 Wainscoting Wood Intact Beige 0.4 1 EA

SM2-

Project Office 2 Door Jam Metal Intact Beige 6.3 19.5 LF

SM2-

Project Office 2 Admin Room

Desk Metal Intact Gray 1.0 1 EA

SM2-

Project Office 2 Storage

Cabinet Metal Intact Gray 0.4 16 LF

SM3-

Annex Garage 3 Work Bench Wood Intact Gray 2.2 28 LF

SM5- Change 5 Privacy Metal Intact Brown 0.4 0.82 LF e6odujms Highlight

Contract No. W912WJ-16-D-0004 TO#0003 APPENDIX A - SURRY MOUTAIN LAKE LCP INVENTORY Project No. R7063003.000.001 US Army Upper CT River Basin Lead Survey Report - FINAL DRAFT

LCP Inventory Surry Mountain Lake

Project Office - 108 Surry Dam Road, Surry, NH 03431

Sample # Building BLD

# Component Substrate Condition Color

XRF

Reading (mg/cm2)

2nd XRF Reading

(mg/cm2) Quantity Unit

07 House Fence Bracket

SM6-

Lower Restroom 6

Privacy Fence

Bracket Metal Intact Brown 1.0 0.82 LF

SM7-

Shelter Restroom 7

Privacy Fence

Bracket Metal Intact Brown 1.8 0.82 LF

Contract No. W912WJ-16-D-0004 TO#0003 APPENDIX A – SURRY MOUNTAIN LAKE PHOTO LOG Project No. R7063003.000.001 US Army Upper CT River Basin Lead Survey Report - FINAL DRAFT

Surry Mountain Lake – Photo Log of LCP Components

Wainscoting (SM2-03) Door Jam (SM2-06)

Desk (SM2-20) Storage Cabinet (SM2-23)

Work Bench (SM3-04) Privacy Fence Bracket (SM5-07)

Contract No. W912WJ-16-D-0004 TO#0003 APPENDIX A – SURRY MOUNTAIN LAKE PHOTO LOG Project No. R7063003.000.001 US Army Upper CT River Basin Lead Survey Report - FINAL DRAFT

Surry Mountain Lake – Photo Log of LCP Components

Privacy Fence & Bracket (SM6-05) Privacy Fence Bracket (SM7-02)