About this file

This is a Workforce Participation Report Forms appendix from the Massachusetts Department of Fish and Game, Division of Fisheries and Wildlife, required for the Access Improvements at Birch Hill ACOE project in Winchendon, Massachusetts. The document establishes two mandatory reporting mechanisms for contractors: a Quarterly Projected Workforce report and a Contractor's Weekly Manpower Report. Contractors must submit the Quarterly Projected Workforce report for each calendar quarter (January-March, April-June, July-September, October-December) detailing the trades to be utilized, estimated total hours to complete work, and total contract dollar value. The Weekly Manpower Report must be submitted on a weekly basis (by week ending date) and requires documentation of job categories, weekly total hours, minority employee hours, and cumulative minority manhours to date, with a final report submission upon project completion.

The forms require contractors to identify the number of minority employees and minority manhours both weekly and cumulatively to track compliance with established minority hiring goals for the contract. Reports must be submitted to the Division of Inland Fisheries and Wildlife at 1 Rabbit Hill Road, Westborough, MA 01581, attention Lori Cookman. The document notes that a revised Quarterly Projected Workforce table must be submitted if any changes to projections occur during the contract term. Non-filed subcontractors are required to complete separate manpower reports, ensuring comprehensive workforce tracking across all project participants.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX C – WORKFORCE PARTICIPATION REPORT

FORMS

Name of Contractor

Massachusetts Department of Fish and Game, Division of Fisheries and Wildlife

QUARTERLY PROJECTED WORK FORCE

Address:

Telephone: Fax

Trades to be Utilized

Estimated Total Hours to Complete Work

Total Contract Dollar Value: Name of Project

Quarter: Jan 1 - Mar 31 Apr 1 - Jun 30 Jul 1 - Sep 30 Oct1-Dec31,200

Week Ending Projected Total Hours Projected Total of All of all Personnel Minority Hours

Trades Used this Week

Note : A revised table must be submitted if any changes on projections occur.

Prepared by:

Title:

Date;

01110-2

General Contractor:

Massachusetts Department of Fish and Game, Division of Inland Fisheries and Wildlife

CONTRACTOR'S WEEKLY MANPOWER REPORT

Project No. Contract Amount $

Minority Goal

Name of Contractor Filing Report:

Week Ending: Report No.:

Check Here if this is a Final Report Date Work Began:

Trade(s):

Check Here if you are a non-filed Subcontractor

Date Work Completed

Job Category # Weekly Total #Min Weekly Total Weekly% Total Manhours Total Minority %of Minority

Employees Manhours Minority Mnhours

Minority Manhours to Date Manhours to Manhours to Date Date

Mail Reports to:

0111b-3

Division of Inland Fisheries and Wildlife 1 Rabbit Hill Road Westborough, MA 01581 Attn: Lori Cookman

Prepared by:

Title:·

Date: 200

APPENDIX C_Workforce Participation Report Forms.pdf
Quarterly Projected Work Force report
Weekly Manpower Report