This file is the West Basin Municipal Water District (WBMWD) Standard Specifications and Standard Drawings for Recycled Water Facilities, a comprehensive design and construction manual applicable to the ECLWRF Fence Replacement Project through reference standards. The document establishes mandatory design criteria, material specifications, construction methods, and inspection requirements for all recycled water system facilities owned and operated by West Basin. The specifications require that all improvements be designed and constructed in accordance with these criteria, with plans submitted to the District Engineer for approval before construction. All recycled water facilities must be guaranteed against defects in workmanship and material for one year after District acceptance, and record drawings must be submitted within 30 days of construction completion. The document references the 2018 edition of the Standard Specifications for Public Works Construction as supplementary guidance and incorporates requirements from multiple regulatory agencies including the California Department of Toxic Substance Control, State Water Board's Division of Drinking Water, Los Angeles County Department of Public Health, and local jurisdictional authorities.
The specifications establish comprehensive technical requirements covering pipe materials (ductile iron, PVC, and steel), valve installations, trench excavation and backfill procedures, thrust blocks, geotechnical investigations, corrosion protection, pressure testing, and pipeline identification using purple-colored marking or tape. Design pressures are set at a maximum of 200 psi for off-site systems with minimum supply pressure of 55 psi at meters, and minimum pipe sizes are established at 8 inches for transmission mains and 6 inches for distribution mains with maximum design velocity of 7 feet per second. The document mandates minimum pipe cover of 42 inches below pavement grade and specifies separation requirements from potable water, sewer, and other utilities in compliance with Title 22 Section 64572 of the California Code of Regulations. All construction activities require coordination with the District Inspector, preconstruction conferences, jurisdictional permits, and compliance with CAL/OSHA requirements, with the Contractor bearing responsibility for utility location, damage prevention, and all required testing and inspections prior to final acceptance.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WEST BASIN MUNICIPAL WATER DISTRICT
STANDARD SPECIFICATIONS
AND STANDARD DRAWINGS FOR
RECYCLED WATER FACILITIES
TABLE OF CONTENTS
PAGE
INTRODUCTION i
DEFINITIONS ii
ABBREVIATIONS vii
PART I DESIGN CRITERIA FOR RECYCLED WATER FACILITIES I-1
Section A General Design Criteria I-1
A-1 IMPROVEMENT PLANS I-1
A-1.1 Drawings I-1 A-1.2 Signatures I-2 A-1.3 Submittals I-3
A-2 SEPARATION BETWEEN WATERLINES AND SEWER LINES I-4
A-2.1 Horizontal Separation I-4 A-2.2 Vertical Separation I-5 A-2.3 Separation from New and Existing Utilities I-5
Section B Design Criteria for Recycled Water Facilities I-6
B-1 GENERAL RECYCLED WATER SYSTEM CRITERIA I-6
B-1.1 Standard Requirements I-6 B-1.2 Calculations Required I-6 B-1.3 Design System Demands I-6 B-1.4 Design Off-site and On-site System Pressures I-6 B-1.5 Improvement Plans I-6
B-2 RECYCLED WATER MAINS I-9
B-2.1 Sizes of Mains I-9 B-2.2 Types and Class of Pipe I-10 B-2.3 Minimum Depth to Top of Recycled Water Main I-10 B-2.4 Standard Location I-10
B-3 VALVES I-10
B-3.1 Types of Valves I-10 B-3.2 Location of Valves I-10 B-3.3 Blow-offs and Combination Air Valves I-11
B-4 SERVICES I-11
TABLE OF CONTENTS
B-5 PUMP STATIONS AND PRESSURE REDUCING STATIONS I-12
B-6 RECYCLED WATER IDENTIFICATION I-12
B-7 DUCTILE IRON PIPE I-12
B-8 POLYVINYL CHLORIDE PRESSURE PIPE (AWWA C900) I-13
B-9 STEEL PIPE I-14
B-10 TRENCH EXCAVATION AND BACKFILL I-14
B-10.1 Pipe Bedding Zone Material I-14 B-10.2 Trench Widths I-15 B-10.3 Shoring/Sloping of Trench I-15 B-10.4 Backfill and Surface Restoration I-15 B-10.5 Special Conditions I-15 B-10.6 Groundwater and Surface Water Control I-16
B-11 THRUST BLOCKS AND THRUST RESTRAINT I-16
B-12 EASEMENTS AND RIGHTS-OF-WAY I-17
B-13 CORROSION PROTECTION I-17
B-14 GEOTECHNICAL INVESTIGATIONS I-17
B-14.1 Field Investigation I-17 B-14.2 Laboratory Testing I-18 B-14.3 Engineering Analyses I-18 B-14.4 Geotechnical Report I-20
B-15 CONTAMINATED SOILS SURVEYS I-20
B-16 ROADWAY AND MAJOR UTILITY UNDERCROSSINGS I-20
B-16.1 Type of Crossing I-20 B-16.2 Size of Casing I-20 B-16.3 Support of Pipe Within Casing I-21 B-16.4 Length and Wall Thickness of Casing I-21 B-16.5 Cathodic Protection I-21
B-17 POTHOLING EXISTING UTILITIES I-21
B-18 HYDRAULIC ANALYSIS I-22
B-19 PERMITTING I-22
B-19.1 District-Obtained Approvals I-22 B-19.2 Contractor Obtained Permits I-23
B-20 ORDER OF PRECEDENCE I-23
i
INTRODUCTION
In April 1989, the West Basin Municipal Water District (“West Basin” or “District” or “WBMWD”), in conjunction with the Metropolitan Water District of Southern California, began to study the feasibility and implementation of a recycled water system. It is the District' intent to provide recycled water service and to standardize wherever possible the design and construction of these facilities.
Therefore, this manual has been prepared to formulate the general procedures and requirements to serve these purposes. These design criteria and standards are to be used in conjunction with the "Standard Specifications for Public Works Construction," (2018 edition) to identify and provide the formal guidelines and requirements for obtaining recycled water service from the District and for the design and construction of the District's recycled water facilities.
West Basin is a public agency that wholesales imported drinking water to 17 cities and nearly one million people in the coastal Los Angeles area. West Basin also owns and operates several treatment facilities and a recycled water distribution system that provides tertiary recycled water to sites for irrigation, industrial and other non-potable applications. These design criteria and standards are to be used for any new or repairs/modifications to existing recycled water distribution system, services or appurtenance construction.
West Basin distributes recycled water on a wholesale basis. The local water and recycled water purveyor is responsible for the metering and sale of the potable and recycled water to the customers. West Basin owns the recycled water piping up to the connection to the meter. The local water purveyor is responsible for the meter up to the customer side of the service. The local water purveyor also has jurisdiction over the protection of their drinking water systems by confirming the water main separation from any new recycled water main is in compliant with Title 22 Section 64572 of the California Code of Regulations.
The State Water Board Division of Drinking Water (DDW) is the primary State agency responsible for protection of public health and the regulation of drinking water. They are the primary agency for the approval of all new recycled water pipelines, services and appurtenances located within public right-of-way.
As the Recycled Water Producer and the Recycled Water Use Permit holder, West Basin is responsible for ensuring the safe use of recycled water at all Recycled Water Use Sites (“Use Sites” or “Customer Sites”) utilizing recycled water in compliance with the use permit conditions.
Los Angeles County Department of Public Health (LACDPH) is the primary local agency responsible for on-site public health issues and cross connection control.
LACDPH has established guideline for pipeline construction and installation of on-site recycled water facilities. These guidelines are intended to protect public health by ensuring the safety of the local domestic potable water supplies.
ii
All off-site recycled water systems shall be constructed in compliance with the applicable drinking water standards, specifically the water main separation requirements stated in Title 22 Section 64572 of the California Code of Regulations with the primary agency for review and approval being DDW.
All on-site recycled water systems shall be constructed in compliance with applicable potable water system construction standards as well as those specified in “THE PURPLE BOOK”, California Health Laws related to recycled water, (California Health and Safety Code, Water Code, Titles 22 and 17 of the California Code of Regulations) and the Los Angeles County Code (LACC), Title 28 – Plumbing, Appendix J. The primary agency responsible for the approval of the on-site facilities is LACDPH.
The jurisdictional agency (i.e.: cities, County, Caltrans, or railroad) shall have authority over all trench backfill, pavement replacement, traffic control and street special construction limitations and requirements for all pipeline construction within their jurisdiction. West Basin has authority on the materials within the pipe zone, pipe material, pipe identification and appurtenances.
DEFINITIONS
Whenever the following terms, or pronouns used in their place, occur in these Design Criteria and Standards, or in any documents that these Design Criteria and Standards govern, the intent and meaning shall be interpreted as follows:
Acceptance, Final Acceptance - The formal action by the Board accepting the work as being complete.
Agency - The West Basin Municipal Water District.
Applicant - An owner, his developer, builder, engineer, or other authorized representative who applies as the owner's official agent to the District for recycled water service.
ASTM - The American Society for Testing and Materials. All references to the specifications of the ASTM are understood to refer to the current specifications as revised or amended at the date of construction.
Attorney - The District's General Counsel.
AWWA - The American Water Works Association. All references to the specifications of the AWWA are understood to refer to the current specifications as revised or amended at the date of construction.
Board - The Board of Directors of the West Basin Municipal Water District.
iii
Calendar Day - Any day including legal holidays, Saturdays and Sundays.
Contaminated Soil - Soil which contains hazardous materials as defined in Title 22, Division 4.5 of the California Code of Regulations, or materials deemed unacceptable to use as 'clean fill' material by the California Department of Toxic Substance Control or California Regional Water Quality Control Board, Los Angeles Region.
Contractor - The person, firm, or corporation entering into contract with the owner or developer for the performance of work required under said contract and the District's ordinances, rules, regulations, and specifications.
Contract Time - Number of calendar days stated in the Contract for the completion of the Work.
Contract Completion Date - The date on which the District accepts the work as being complete.
Contract Documents - The complete contract includes all of the documents set forth herein, to wit:
Bid Documents (including Advertisement for Bid, Instructions to Bidders, Bid Form, and Bid Bond) Contract Documents (including Agreement, Performance Bond, Payment Bond) General and Special Provisions Technical Specifications Standard Drawings Construction Drawings Addenda Issued Prior to Bid Opening Signed Agreement Certificates of Insurance Workers' Compensation Insurance Notice of Award Notice to Proceed Executed Change Orders, if any
County - The County of Los Angeles, State of California.
Design Consultant - The engineer or architect designated by the Owner to have design control over the Work or a specified portion of the Work, acting either directly or through duly authorized representatives. Such representatives shall act within the scope of the particular duties delegated to them.
Direct - Action of the District by which the Contractor is ordered to perform or refrain from performing work under the Contract.
iv
District - The West Basin Municipal Water District (“District” or “West Basin” or “WBMWD”), its authorized employees and agents.
Domestic Water (Potable Water) - That water which is pure and wholesome, does not endanger the lives or health of human beings, and conforms to the latest edition of the United States Public Health Service Drinking Water Standards, the California Safe Drinking Water Act, or other applicable standards.
Engineer - The Engineer of the West Basin Municipal Water District or their authorized agent.
Field Directive - Written documentation of the actions of the District in directing the Contractor. Also referred to as a Directive.
Field Order - A written instruction given to the Contractor authorizing work that is a change to the scope of work carried out on a time and material basis.
Float - Float or "total float" shall be defined as provided in the Associated General Contractors of America "CPM in Construction, A Manual for General Contractors".
Furnish - To deliver to the job site or other specified location any item, equipment, or material.
General Manager - An individual designated by the West Basin Municipal Water District as the chief executive officer and agent for the District.
Holidays - Legal holidays designated by the District or specifically identified in the Contract.
Inspector - A duly authorized representative of the District with the authority to require work to be accomplished in accordance with the contract plans and specifications.
Install - Placing, erecting, or constructing any item, equipment, or material.
Liquidated Damages - The amount prescribed in the Contract Documents, to be paid to the District or to be deducted from any payments due or to become due the Contractor for each day's delay in completing the whole or any specified portion of the Work beyond the time allowed in the specifications.
Los Angeles County Department of Public Health – Environmental Health Division (LACDPH) - The local primacy health agency responsible for on-site public health issues and cross connection control. Regulatory responsibility is to confirm that all on-site recycled water facilities are constructed in compliance with applicable water system standards and plumbing codes.
v
Off-site Facilities - Designates or relates to recycled water facilities up to and including the water meters. All off-site recycled water facilities will be owned, operated, and maintained by the District upon Acceptance by the District of the dedicated facilities.
On-site Facilities - Designates or relates to recycled water facilities downstream of the water meters. All on-site recycled water facilities will be owned, operated, and maintained by the On-Site Property Owner, unless otherwise specified.
Owner or District - The West Basin Municipal Water District. The Owner is referred to throughout the contract documents as if singular in number and masculine in gender. The term "Owner" means the Owner or his authorized representative.
Owner's Representative - The person designated in writing by the Owner to act as its agent on specified matters relating to this Contract.
Plans - The plans, working drawings, detail drawings, profiles, typical cross sections, general cross sections, and supplemental drawings or reproductions thereof, approved by the Engineer, which show locations, character, dimensions or details of the work.
Provide - Furnish and install, complete in place.
Punch List - List of incomplete items of work and of items of work which are not in conformance with the Contract.
Recycled Water - A combination of treated wastewater and intercepted surface and subsurface stream flow, supplemented by other waters, including domestic (potable) water. The pipeline distribution system is similar to domestic water construction and operation.
Record Drawings - Drawings which show the facilities including all revisions to the original plans.
Service - The furnishing of recycled water to an Owner through a metered connection to the on-site facilities.
Sewer - A pipe or conduit used to convey liquid waste.
Standard Specifications - The "Standard Specifications for Public Works Construction" (Green Book), 2018 edition, which are the District's reference specifications to be used in conjunction with these "Design Criteria and Standard Specifications and Standard Drawings."
State - The State of California.
vi
State Water Board’s Division of Drinking Water (DDW) - The primary State agency responsible for protection of public health and the regulation of drinking water. One of its specific regulatory responsibilities is to confirm that the separation of potable water, recycled water and sanitary sewers are constructed in compliance with Title 22, Section 64572 of the California Code of Regulations.
Sub-subcontractor - A sub-subcontractor is a person or entity who has a direct or indirect contract with a subcontractor to perform any of the Work at the Site. The term sub-subcontractor means a sub-subcontractor or an authorized representative thereof.
Substantial Completion - Substantial Completion is the stage in the progress of the Work when the Work is sufficiently complete in accordance with the Contract Documents so the Owner can occupy or utilize the Work for its intended use.
Supplemental Standard Specifications - Includes modifications to Standard Specifications.
Supplier - Any person, firm, corporation, or organization who supplies materials or equipment for the Work, including that fabricated to a special design, and may also be a Subcontractor or a Sub-subcontractor.
Terms - The terms "acceptable," "accepted," "adequate," "approved," "directed," "necessary," "or equal," "proper," "required" and "specified" mean acceptable, accepted, adequate, approved, directed, necessary, or equal, proper, required or specified by or in the opinion of the District.
Time of Completion - Time allowed for completion of contract computed in calendar days.
Will - Actions entered into by the Contractor or the District as a covenant with the other party to do or to perform the action.
Work - The improvements proposed to be constructed or done pursuant to a legal agreement and consistent with these Design Criteria and Standards, including the furnishing of all labor and materials.
Working Day - Any day, other than a holiday, Saturday or Sunday, on which the Contractor may proceed with regular work on the current controlling operation as determined by the District toward the completion of the Contract. A working day is equivalent to 1.45 calendar days.
vii
ABBREVIATIONS
List of General Abbreviations
A Area AASHTO American Association of State Highway and Transportation Officials AB Anchor Bolt/Aggregate Base ABAN Abandoned ABC Asphalt Base Course ABT About AC Acre/Asphaltic Concrete ACI American Concrete Institute ACP Asbestos-Cement Pipe ADDL Additional AHD Ahead AI The Asphalt Institute AISC American Institute of Steel Construction AISI American Iron and Steel Institute AL Aluminum ALIGN Alignment ALTN Alternate ANCH Anchor ANG Angle ANSI American National Standards Institute APPROX Approximate APWA American Public Works Association ARCH Architecture/Architectural AREA American Railway Engineering Association ARV Air-Release Valve ARVV Air-Release/Vacuum Valve Abbreviation Term ASCE American Society of Civil Engineers ASME American Society of Mechanical Engineers ASPH Asphalt ASSY Assembly ASTM American Society of Testing and Materials AVE Avenue AVG Average AWG American Wire Gauge AWS American Welding Society AWWA American Water Works Association
BC Beginning of Curve BCR Begin Curb Return BEG Begin BETW Between viii
BF Blind Flange BK Back BL Base Line BLDG Building BLK Block BM Bench Mark/Beam BO Blowoff BOCA Building Officials Code Administration International, Inc.
BOT Bottom BRG Bearing BUR CBL Buried Cable BV Butterfly Valve BVC Begin Vertical Curve BW Block Wall
C Conduit CAB Crushed Aggregate Base CALTRANS California Department of Transportation CAP Capacity CATV Cable Television CB Catch Basin C-C Center-to-Center CCB Concrete Block CCP Concrete Cylinder Pipe CD Cross Drain CEM Cement CF Cubic Feet/Curb Face CFH Cubic Feet Per Hour Abbreviation Term CFM Cubic Feet Per Minute CFS Cubic Feet Per Second C & G Curb and Gutter CHG Change CHKD PL Checkered Plate CI Cast Iron CIP Cast in Place/Cast-Iron Pipe CISP Cast Iron Soil Pipe CISPI Cast-Iron Soil Pipe Institute CJ Construction Joint CL Centerline/Class/Clearance CLR Clear CMC Cement-Mortar Coated or Coating CML Cement-Mortar Lined or Lining CMLCSP Cement-Mortar Lined and Coated Steel Pipe CMP Corrugated Metal Pipe CMPA Corrugated Metal Pipe Arch CMU Concrete Masonry Unit ix
CO Cleanout/Conduit Only COL Column COMPL Complete CONC Concrete CONN Connection CONST Construct or Construction CONT Continuous CONTR Contractor COORD Coordinate/Coordinated COP Copper COR Corner CPLG Coupling CRES Corrosion Resistant Steel CRSI Concrete Reinforcing Steel Institute CS Carbon Steel/Commercial Standard CSP Corrugated Steel Pipe CT Center Top CTG Coating CTR Center CTV Cable Television CULV Culvert CU YD, CY Cubic Yard CYL Cylinder
D Degree of Curvature DB Direct Buried DBL Double DDW State Water Board’s Division of Drinking Water DEPT Department DET Detail/Detour DI Drop Inlet/Ductile Iron Abbreviation Term DIA Diameter DIM Dimension DIMJ Ductile-Iron Mechanical Joint DIP Ductile-Iron Pipe DIPRA Ductile-Iron Pipe Research Association DISCH Discharge DIST Distance DMH Drop Manhole DN Down DR Drain/Door DWG Drawing DWY Driveway
E East EA Each x
EC End of Curve ECC Eccentric ECR End of Curb Return ED External Distance EE Each End EF Each Face EFF Efficiency EFL Effluent EGL Energy Grade Line EL Elevation E/L Easement Line ELEC Electric ELEV Elevation ELP Elliptical ENC Encasement ENCL Enclosure EOP Edge of Pavement EOS Equivalent Opening Size EP Edge of Pavement EPA Environmental Protection Agency (Federal) EQ Equation EQL Equal ESMT Easement EST Estimate or Estimated ETC And so Forth EVC End Vertical Curve EW Each Way EXC Excavate or Excavation EXP Expansion EXST Existing EXT Exterior/Extension Abbreviation Term
F Fahrenheit/Floor FAB Fabricate FCO Floor Cleanout FCV Flow Control Valve FD Floor Drain FE Flanged End FF Finished Floor/Flat Face FG Finished Grade FHY Fire Hydrant F&I Furnish and Install FIG Figure FIN Final FIT Fitting FL Floor/Flow Line xi
FLG Flange FM Force Main/Factory Mutual FNSH Finish FPC Flexible Pipe Coupling FPM Feet Per Minute FPS Feet Per Second FPT Female Pipe Thread FS Finished Surface/Federal Specifications FT Feet or Foot FTG Footing FUT Future FWY Freeway
G Gas GA Gauge GAL Gallon GALV Galvanized GB Grade Break GDR Guard Rail GE Grooved End GENL General GM Gas Main GND Ground GPD Gallons Per Day GPM Gallons Per Minute GR Grade GRTG Grating GSKT Gasket GUT Gutter GV Gate Valve Abbreviation Term
HARN Harness HB Hose Bibb HD Heavy Duty HDPE High Density Polyethylene HGL Hydraulic Grade Line HGT Height HORIZ Horizontal HP High Pressure HPT High Point HR Hour/Handrail HS High Strength HV Hose Valve HVY Heavy HW Headwall HWL High Water Level xii
HWY Highway HYDR Hydraulic
I Intersection Angle Officials ID Inside Diameter IE Invert Elevation IN Inches INCL Include INL Inlet INS Insulating INSTL Install or Installation INTR Interior/Intersection INV Invert IP Iron Pipe IPS Iron Pipe Size IPT Iron Pipe Thread IRR Irrigation JCT Junction IN Join
JT Joint
KIPS Thousands of Pounds Abbreviation Term
L Length of Curve/Long/Left LACDPH Los Angeles County Department of Public Health LATL Lateral LB Pound LF Linear Foot LG Long LOC Location/Locate LP Light Pole LPT Low Point LR Long Radius LS Lift Station LT Left/Light LWL Low Water Level
MATL Material MAX Maximum MB Machine Bolt MECH Mechanical MFR Manufacturer MG Million Gallons/Milligram MGD Million Gallons Per Day MH Manhole xiii
MI Malleable Iron/Mile MIL Military Specifications MIN Minimum MISC Miscellaneous MJ Mechanical Joint MOD Modification MON Monument MPT Male Pipe Thread MSL Mean Sea Level MSS Manufacturer's Standardization Society
N North NA Not Applicable NBFU National Board of Fire Underwriters N & C Nail and Cap NC Normally Closed NE Northeast NIC Not in Contract NIP Nipple NO Number/Normally Open NOM Nominal Abbreviation Term NPT National Pipe Taper NRS Nonrising Stern NTS Not to Scale NW Northwest NWL Normal Water Level
OA Overall OC On Center OD Outside Diameter OE Or Equal OF Outside Face OPNG Opening OPP Opposite ORIG Original OSHA Occupational Safety and Health Administration OVFL Overflow
P Pole PC Point of Curvature PCA Portland Cement Association PCC Point of Compound Curvature/Portland Cement Concrete PE Plain End/Polyethylene/Professional Engineer PI Point of Intersection PKWY Parkway PL Plate/Property Line xiv
PLF Pounds Per Lineal Foot POB Point of Beginning POC Point of Connection POJ Push-On Joint PP Power Pole/Polypropylene PRC Point of Reverse Curve PRESS Pressure PRL Parallel PROV Provisions PRPSD Proposed PRVC Point of Reverse Vertical Curve PSI Pounds Per Square Inch PSIG Pounds Per Square Inch Gauge PSF Pounds Per Square Foot PT Point of Tangency PVC Polyvinyl Chloride Abbreviation Term PVMT Pavement
Q Flow Rate QTY Quantity
R Right/Radius RC Reinforced Concrete RCP Reinforced Concrete Pipe RCPA Reinforced Concrete Pipe Arch RD Road ROC Reduce RDCR Reducer REF Reference REINF Reinforce or Reinforced RELOC Relocated REQ Required/Requirement REQD Required RF Raised Face RND Round RJ Restrained Joint RPM Revolutions Per Minute RR Railroad RST Reinforcing Steel RT Right RW Recycled Water R/W Right-of-Way
S South/Slope in Feet Per Foot/Sewer SAN Sanitary SCHED Schedule xv
SO Storm Drain SDG Siding SDWK Sidewalk SE Southeast SECT Section SF Square Feet SGL Single SH Sheet/Sheeting SIM Similar SLP Slope SLV Sleeve SOL Solenoid SOV Solenoid-Operated Valve Abbreviation Term SP Steel Pipe SPCG Spacing SPEC Specification SPLC Splice SPRT Support SQ Square SQ FT Square Feet SR Short Radius SS Sanitary Sewer SSPC Steel Structures Painting Council SST Stainless Steel ST Street STA Station STD Standard STK Stake STL Steel STR Straight STRL Structural STRUCT Structure SURF Surface SW Southwest SYMM Symmetrical SYS System
T Tangent Length of Curve/Telephone TAN Tangent TB Top of Bank T & B Top and Bottom TBG Tubing TBM Temporary Bench Mark TC Top of Curb TDH Total Dynamic Head TEL Telephone xvi
TEMP Temperature/Temporary THB Thrust Block THD Thread or Threaded THH Thrust Harness THK Thick T/O Top of TOC Top of Concrete TOS Top of Slab TOT Total TP Telephone Pole TV Television TYP Typical Abbreviation Term
UBC Uniform Building Code UD Underdrain UG Underground UL Underwriters' Laboratories, Inc.
UNO Unless Noted Otherwise UTC Underground Telephone Cable
V Vent/Valve/Volt VC Vertical Curve VCP Vitrified Clay Pipe VEL Velocity VERT Vertical VOL Volume VPC Vertical Point of Curve VPI Vertical Point of Intersection VPT Vertical Point of Tangency
W West/Wide/Water W/ With WL Waterline WLD Welded WM Water Meter W/O Without WSE Water Surface Elevation WT Weight WTR Water WWF Welded Wire Fabric WWM Woven Wire Mesh
YD Yard YR Year YS Yield Strength
I-1
PART I
DESIGN CRITERIA
FOR
RECYCLED WATER FACILITIES
SECTION A GENERAL DESIGN CRITERIA
A-1 IMPROVEMENT PLANS
Improvement plans shall be prepared and submitted to the Engineer for approval and signature for all recycled water facilities to be constructed by the District or by the Applicant and dedicated to the District for operation and maintenance. All improvements shall be designed and constructed in accordance with these Design Criteria and Standards. For tract developments, the off-site recycled water facilities may be shown on the improvement plans, which are to be approved by the City or County. However, all of the below requirements shall also be included on the improvement plans for the tract development including the District’s Standard Recycled Water System Notes.
The general requirements for the preparation of the improvement plans are outlined below.
A-1.1 Drawings
a. Drawings shall be on standard (22" x 34") or maximum size of 24" x 36" sheets with sheet number, title, revisions, and signature blocks and shall be per the District’s latest CAD standards.
b. Improvement plans shall conform to the Standard Procedure for
Processing Maps and Improvement Plans of the city or county having jurisdiction using the latest version of Auto CAD required by the jurisdictional agency.
c. Title sheets shall have an index or key map clearly indicating the sheet numbers issued.
d. The following shall be clearly shown on the drawings, preferably on the Title Sheet:
(1) Project bench mark(s) and basis of bearings; and
(2) Detailed quantity estimates and standard notes, categorized by domestic water, sewer and recycled water facilities.
e. The District’s Standard Recycled Water General Notes shall be included
(Standard Drawing RW39).
I-2
f. Improvement plans for tracts or other developments shall have a separate small scale map showing the overall layout of recycled water facilities if improvement plans contain three or more separate sheets of drawings.
g. The following scales shall be used on all drawings, unless otherwise approved or specified by the Engineer:
(1) Plan and Profile sheets:
Horizontal: 1" = 40 feet Vertical: 1" = 4 feet (1" = 8 feet or as appropriate for steep grades)
(2) Details: As appropriate to clearly indicate the required details (minimum: trench/pavement replacement, appurtenance, services, and RW pipe identification)
h. Profiles shall be shown on the top of the sheets.
i. All facilities to be operated and maintained by the District shall be located within public rights-of-way or recorded easements, which shall be clearly shown on the improvement plans.
j. The drawings shall show on plan and profile the position of all other known or proposed underground facilities.
k. Record drawings shall be prepared upon completing the construction of the improvements. The record drawings shall be submitted to the District within 30 days of completion of construction of recycled water facilities.
l. Professional Land Surveyor, hired by the improvement plans design engineer or the Applicant, shall verify in writing that the recycled water facilities were constructed within the easements as listed in the easement documents and shown on the improvement plans.
A-1.2 Signatures
a. Unless otherwise specified or approved by the Engineer, each sheet of plans submitted for the Engineer's approval shall be signed by the civil engineer responsible for that design, except that a sheet of complex grading, structural, mechanical, or electrical plans shall be signed by the professional engineer responsible for that design. All electronic submittals shall include the official signature and signed seal of the design engineer.
b. Civil and other professional engineers signing plans to be submitted for the Engineer's approval shall be registered with the State of California.
The Engineers signing the plans shall also affix their seal to the drawings near their signature.
I-3
c. Plan revisions subsequent to the Engineer's approval shall be legibly identified and resigned per the requirements of Subsection A-1.2 "a" and "b" above, prior to resubmittal for the Engineer's approval.
A-1.3 Submittals
a. Recycled water calculations complete in accordance with the requirements of Section B, shall accompany plans submitted for checking, unless this requirement is specifically waived by the Engineer.
b. Plans submitted for approval shall be accompanied by a letter of transmittal addressed to the Engineer. All submittals shall include one (1) set, at a minimum, of improvement plans (bond paper) plus one (1) set of the plans in electronic (PDF file) format on CD, flash drive or other acceptable media. Plans not approved shall have a watermark or stamp stating “NOT FOR CONSTRUCTION” or “DRAFT” to make it clear that there are not an approved set. Prior to submittal, confirm with the Engineer the number of hard copies required for each submittal.
c. Plans shall be checked for consistency, accuracy, drafting, and conformance with the District's Standards and these Design Criteria prior to submission for the Engineer's approval. If plans have obviously not been checked by the submitting design engineer, they will be returned unapproved by the Engineer.
d. Check prints shall accompany revised plans, which are resubmitted for approval. Resubmitted plans shall be accompanied by a letter of transmittal addressed to the Engineer and shall be resigned prior to resubmittal to the District.
e. Geotechnical and corrosion investigation reports, unless specifically waived by the Engineer. Reports shall be signed and stamped.
f. Any and all proposed off-site recycled water facilities must be reviewed and approved by the District through the District’s plan approval process before the facilities will be allowed to be constructed. Approval by the Engineer does not neglect the professional design engineer liability for the design. In addition, the plans will need to be approved by the jurisdictional and regulatory agency that the work is being performed within.
g. Once the plans have been approved by the District, the approved plans shall be submitted to the District. The submittal shall include one (1) set, at a minimum, of improvement plans (bond paper) plus one (1) set of the plans in electronic (PDF file) format on CD, flash drive or other acceptable media. The PDF file will be of a quality of high resolution. Prior to submittal, confirm with the Engineer the number of hard copies required of the approved plans.
I-4
h. All recycled water facilities shall be guaranteed against defects in workmanship (improper contractor’s installation) and material defects for a period of one (1) year after the date of acceptance of the facilities by the District.
It is further agreed that the facilities shall be restored to full compliance with the requirements of the District and these Design Criteria and Standards if during said one (1) year period the facilities or any portion thereof are found not to be in conformance with any provisions of the Improvement Plans or these Design Criteria and Standards. This guarantee is in addition to any and all other warranties or guarantees, express or implied within the Project Specifications or Plans prepared for these recycled water facilities.
A-2 SEPARATION BETWEEN WATERLINES AND SEWER LINES
A-2.1 Horizontal Separation
Per Title 22 Section 64572 of the California Code of Regulations, Division of Drinking Water (DDW) require that all new recycled water mains and services (conveying Title 22 recycled water) be installed at least four (4) feet horizontally from and one (1) foot vertically below any parallel pipeline conveying potable water. The vertical separation noted above is required only when the horizontal distance between the potable water main and the recycled water main or service is less than ten (10) feet. The minimum separation distances noted above shall be measured from the nearest outside edge of each pipe barrel.
If crossing a pipeline containing potable water, the new recycled water main or service shall be constructed no less than 45-degrees to and at least one (1) foot vertically below that pipeline. No connection joints shall be made in the recycled water main within eight (8) horizontal feet of the other crossing pipeline.
The DDW separation requirements are shown on the District’s Standard Drawing No.
RW18.
The above separation requirements shall be met, whenever feasible for all new construction. If the District agrees that it is not feasible to meet these requirements, the District will be required to propose an alternative to these requirements to the water purveyor as well as to DDW.
The waiver and alternative proposed shall: demonstrate to the State Board that the proposed alternative would provide at least the same level of protection to public health;
and obtain written approval from DDW prior to implementation of the alternative. The Design Engineer shall be responsible to provide a draft of the waiver request. DDW has prepared an application checklist that may be used in proposing an alternative to the Waterworks Standards. This checklist is available from the District, the water purveyor and DDW. The District will review, revise, and finally submit the waiver request to the water purveyor for forwarding to DDW.
I-5
In addition, the District requires the following additional horizontal separation requirements from untreated sewage, primary or secondary treated sewage, disinfected secondary recycled water, and hazardous fluids (such as fuels, industrial wastes and wastewater sludge):
• New recycled water mains shall be installed at least four (4) feet horizontally from, and one (1) foot vertically above, any parallel pipeline conveying the above sewage or fluids.
• If crossing a pipeline containing the above sewage or fluids, a new recycled water main shall be constructed no less than 45-degrees to and at least one (1) foot above that pipeline. No connection joints shall be made in the recycled water main within eight (8) feet of the other crossing pipeline.
A-2.2 Vertical Separation
Normally, domestic water, recycled water, and sewer mains shall be located vertically from the street surface in order of the higher quality, i.e., domestic water shall be above recycled water/storm drains and recycled water/storm drains shall be above sewer.
Whenever a crossing must occur where the new recycled water main or service passes within one (1) foot vertically of a domestic water main or a sewer main, special construction will be required. Encasement may be required if the vertical separation requirements cannot be met. One of the following types of encasement may be required: reinforced concrete encasement, a minimum thickness of six (6) inches; or piping within a continuous welded steel casing which shall have a thickness of not less than 1/4-inch.
If the recycled water main is above a water main, the special construction shall extend a minimum of eight (8) feet of horizontal clearance on both sides, or if not feasible, center the piece of new recycled water pipe over the crossing to maximize this horizontal clearance.
If the sewer is located above the recycled water main or within a vertical distance of one (1) foot clearance distance, the special construction shall extend a minimum of four (4) feet of horizontal clearance on both sides of the crossing. These construction requirements shall not apply to house laterals that cross perpendicular less than one (1) foot below the recycled water main.
A-2.3 Separation from New and Existing Utilities
Construction of new recycled water mains or new utilities or structures shall maintain a minimum of five (5) foot parallel separation and a minimum of one (1) foot vertical separation from all District recycled water mains unless written authorization is obtained from the District. Construction of all new recycled water mains and services shall maintain a minimum of five (5) foot parallel separation and one (1) foot minimum vertical separation from all existing utilities and structures unless written authorization is obtained from the District.
I-6
SECTION B DESIGN CRITERIA FOR RECYCLED WATER FACILITIES
B-1 GENERAL RECYCLED WATER SYSTEM CRITERIA
B-1.1 Standard Requirements
The design and construction of all off-site recycled water system facilities to be operated and maintained by the District shall be in accordance with these Design Criteria and Standards, the District's "Regulations for Recycled Water Facilities," and the applicable potable water system construction standards related to recycled water, California Code of Regulations Title 17 and Title 22, and the requirements of the State Water Quality Control Board.
No fire hydrants or service connections other than recycled water services shall be connected to the recycled water system without prior District written approval.
B-1.2 Calculations Required
Substantiating engineering calculations for demands, pressures, and structural designs shall accompany plan submittals to the Engineer.
B-1.3 Design System Demands
In general, the design of the recycled water system facilities shall be based on the recycled water demands, pressures, and system elements as outlined in these Design Criteria and Standards. The off-site recycled water system facilities shall be designed to deliver peak flows to the new recycled water customer to be irrigated by the on-site recycled irrigation systems, which they will supply. All demand estimations shall be submitted to the Engineer for approval.
Unless otherwise approved by the Engineer, the recycled water demand shall be estimated by using 3.0 acre-feet per year per acre for turf irrigation and 1.0 acre-feet per year per acre landscape irrigation with a peak hour demand factor of 7 due to restricted hours of irrigation with recycled water and seasonal peaking.
B-1.4 Design Off-site and On-Site System Pressures
The off-site recycled water system facilities shall be designed to operate at a maximum working pressure of 200 psi, unless otherwise specified by the District. The on-site irrigation system shall be designed assuming a minimum supply pressure of 55 psi at the meter.
B-1.5 Improvement Plans
Improvement plans for off-site recycled water system facilities shall be prepared in accordance with the requirements of Subsection A-1 and shall include the following:
I-7
a. Profiles of recycled water mains 4 inches in diameter and larger. Profile of recycled water service laterals may be required by the District when the service crosses multiple existing utilities. A clear description of the pipeline material shall be provided on the profile portion of the drawings.
b. Detailed quantity estimates indicating linear footage of pipe by size, class, and type; number of valves by size, class, and type; number of recycled water services by size; number of blow-offs and combination air valve assemblies;
linear footage of concrete encasements (if applicable); and any other appurtenances that should be identified for quantity purposes.
c. For the project bench marks and basis of bearings: the horizontal datum shall be NAD 1983, State Plane California V FIPS (Zone 5), and the vertical datum shall be NAVD 1988. The following horizontal control information shall be provided for each project: horizontal control coordinates reference points, dedicated recycled water pipeline calculated coordinates, and the description of the project vertical bench mark. For all projects at District facilities, the plans shall reference the horizontal and vertical bench mark points installed within the District’s facilities.
District will provide the survey report for vertical and horizontal monument network within their facilities.
d. Improvement plans shall conform to the Standard Procedure for Processing Maps and Improvement Plans of the city or county having jurisdiction using the latest version of Auto CAD required by the jurisdictional agency.
e. For mechanical piping within buildings and at treatment plants, the plans shall be created using REVIT or equivalent 3D software approved by the District.
f. Standard Recycled Water System Notes to be included, but not limited to, on all Improvement Plans or recycled water construction plans:
(1) The recycled water system, as shown on these plans, shall be constructed by the Owner/Developer/Applicant in accordance with the latest West Basin Municipal Water District Standards for recycled water construction.
The Owner’s/Developer’s/Applicant’s contractor shall have a copy of these standards, as well as a copy of the project plans and specifications, on the job at all times.
(2) The Owner/Developer/Applicant shall furnish the District with recorded easements for all portions of the recycled water system outside the public right-of-way. In addition, post construction, the Owner/Developer/Applicant shall have a Professional Land Surveyor verify in writing that the facilities to be accepted by the District were constructed within the easements as listed in the recorded easements.
(3) The District shall be furnished with four hard copies (full size) of the approved construction plans prior to the start of construction.
(4) The District Inspector shall be notified at least 3 working days prior to the start of construction and any subsequent required inspection.
I-8
(5) A preconstruction conference with representatives from all affected agencies and the Contractor shall be held on the job-site at least 48 hours prior to the start of construction.
(6) The Contractor shall obtain all necessary jurisdictional agency’s permits (i.e.: City, County, Caltrans or Railroad/Metro) prior to the start of construction.
(7) Construction of recycled water mains and appurtenances shall only be performed by qualified contractors with a valid California Contractor “A” or “C34” license.
(8) Recycled water mains shall be staked for line and grade or shall be installed subsequent to the installation of the curbs but prior to paving of the streets.
(9) The minimum cover over recycled water mains shall be 42 inches below pavement finished grade or at no time shall there be less than 36 inches of cover from the top of pipe to subgrade or street undercut (existing ground during construction) unless approved in advance by the District.
For circumstances where the District has approved in advance a cover less than 42-inches, the recycled water main shall be concrete encased if the cover is less than 36-inches.
(10) Contractor to verify depth and location of all utilities prior to trenching as required in the District’s Design Criteria, Part 1, Section B-17.
(11) Maximum deflection of pipe joints allowable on curved alignments shall be in accordance with the pipe manufacturer’s recommendations. The Design Engineer may specify even stricter requirements. PVC pipe sections shall not be bent to achieve a curve. Pipe deflections for short radius curves and angle points shall be accomplished by means of standard fittings.
The location of all fittings shall be detailed on the plans.
(12) No valve shall be located within a gutter or other concrete drainage device.
(13) No recycled water service or meter shall be located within a driveway. All recycled water services shall be installed per the District’s Standard Drawings. Curbs shall be inscribed with a 2-inch high “RW” indicating locations of all recycled water services.
(14) All flanged connections shall be coated with three coats of eight mils each of low VOC epoxy coating after installation, including nuts, bolts, and flanges and then shall be wrapped with 10-mil polyethylene sheet.
(15) No facility is to be backfilled until inspected by the District and, if necessary, by the jurisdictional agency.
I-9
(16) Thrust blocks shall be installed in accordance with the District Standard Drawing RW19 at all pipe deflections (greater than 5 degrees), all angle points (both horizontal and vertical), and at all fittings. Valve anchor blocks shall be installed at all valves.
(17) Shut down of existing recycled waterlines to facilitate connection to existing facilities shall be coordinated with the District Inspector. The District cannot guarantee a complete shutdown of existing mains and the contractor shall be responsible for any required dewatering of the excavation.
No connections shall be made to the District's existing recycled water system until the new facilities have been successfully pressure tested. All connections to the District's recycled water system shall be made in the presence of the District Inspector.
(18) The recycled water system shall be pressure tested in accordance with the District's Standards. Recycled water mains are not required to pass disinfection or bacteriological tests unless required by the District.
(19) All recycled water piping, including service lines, attached appurtenances, and connections shall be installed with recycled water identification tape and/or tags in accordance with the District's "Design Criteria, Standard Specifications, and Standard Drawings" and in accordance with LACDPH Guidelines.
(20) All valve boxes or manhole frame and covers shall be adjusted to finished pavement grade by the contractor. This is to be done prior to placing seal coat paved roadway.
(21) Final acceptance of the construction will not occur until original record drawings and digital file of the record drawings are delivered to and accepted by the District’s Inspector. All field changes shall be showed on the record drawings.
(22) All recycled water facilities included in this work shall be installed in accordance with the District's "Regulations for Recycled Water Facilities."
B-2 RECYCLED WATER MAINS
B-2.1 Sizes of Mains
The normal minimum size transmission main shall be 8 inches in diameter. The normal minimum size distribution main shall be 6 inches in diameter.
The maximum allowable design velocity shall be 7 feet per second.
All water mains 4 inches in diameter and larger shall have a profile shown on the improvement plans.
I-10
B-2.2 Types and Class of Pipe
All recycled water mains, 12-inches in diameter and smaller, shall be AWWA C-900 PVC pipe, DR-14 or AWWA C-151 Ductile Iron Pipe, Class 350. All other pipe materials require special review and approval by the Engineer.
Ductile iron pipe and fittings shall be encased in a loose polyethylene encasement in accordance with AWWA C105 standard. All PVC pipe shall be installed with tracer wire and detectable warning tape in accordance with these Design Criteria and Standards.
For pipe sizes 14-inches in diameter and larger, the pipe material will need special review and approval by the Engineer and may be AWWA C-900 PVC, ductile iron pipe or cement mortar lined and coated steel pipe.
Cathodic protection and/or test stations shall be provided on ductile iron and steel pipe, 14-inches in diameter and larger.
B-2.3 Minimum Depth to Top of Recycled Water Main
The top of recycled water mains shall be a minimum of 42 inches below street pavement or finished grade, or at no time shall there be less than 36 inches of cover from the top of pipe to subgrade or street undercut (existing ground during construction) unless approved in advance by the District. For circumstances where the District has approved in advance a cover less than 42-inches, the recycled water main shall be concrete encased if the cover is less than 36-inches.
B-2.4 Standard Location
Recycled water mains shall normally be located on the opposite side of the street from the potable water mains and shall conform to the separation requirements of Subsection A-2.
B-3 VALVES
B-3.1 Type of Valves
Resilient wedge gate valves shall be used on all recycled water mains 12-inches in diameter and smaller. Butterfly valves shall be used on all recycled water mains greater than 12-inches in diameter. All other valves require special review and approval by the Engineer. All butterfly valves shall be bi-directionally tested with the operator installed in accordance with these Design Criteria and Standards.
B-3.2 Location of Valves
There shall be at least two control valves at the three-way intersection of any recycled water mains; at least three control valves at the four-way intersection of any recycled water mains; and four control valves at any four-way intersection of major distribution mains.
I-11
The control valves at all intersections, as described herein, shall be flanged to the main line tee or cross, unless otherwise approved by the Engineer. Unless specifically approved by the Engineer, the maximum allowable spacing for intermediate valves on transmission mains is 2,000 feet. All intermediate main line valves should be located on the prolongation of a property line wherever possible.
Where recycled water mains are located within an easement outside of paved streets, a valve shall be located at each end of the easement within the street section.
In no event shall any valve be installed within a gutter or other concrete drainage device.
Valve stem operating nuts having over 48 inches of cover shall be provided with an approved extension.
The final determination of the locations of all valves shall be subject to the approval of the Engineer.
B-3.3 Blow-offs and Combination Air Valves
Blow-offs shall be installed at the end of all mains where either the flow velocity or the slope of the main could cause sediment to settle at the end of the main. A blow off valve shall be installed as near a catch basin as possible to flush the line.
This is the start of the file's text. The full file is on GovTribe.