This solicitation is for a multiple award trail maintenance contract on the Nez Perce-Clearwater National Forests. The contractor will perform annual trail opening and maintenance including logging out, drainage maintenance, and rock removal on non-wilderness and wilderness trails. The work will be separated into 13 items covering specific trail segments identified in the attachments. The period of performance is from date of award through September 2025, with option years. The Department of Agriculture Forest Service will administer the contract. Pricing is on a firm fixed price basis by the mile for each trail segment item. The solicitation allows for multiple awards with only one contractor performing work for each defined geographic area. Responses are due by April 14, 2023.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUMIS CHECKED

CODE 18a. PAYMENT WILL BE MADE BY

CODE

FACILITYCODE

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER

OFFEROR

COEUR DALENE ID 83815

3232 WEST NURSERY ROAD

SUPERVISORS OFFICE

IDAHO PANHANDLE NATIONAL FORESTS

0278 CODE 16. ADMINISTERED BYCODE

X

X

X

115310

SIZE STANDARD:

100.00 % FOR:SET ASIDE:UNRESTRICTED OR0281

RFPIFB

10. THIS ACQUISITION ISCODE

RFQ

14. METHOD OF SOLICITATION

13b. RATING

NAICS:

SMALL BUSINESS

05/15/2023 1700 PT

04/14/2023

208-765-7318DANIEL SZAMBELAN

(No collect calls)

INFORMATION CALL:

FOR SOLICITATION 8. OFFER DUE DATE/LOCAL TIMEb. TELEPHONE NUMBERa. NAME

4. ORDER NUMBER3. AWARD/ 6. SOLICITATION

1284LL23Q0037

5. SOLICITATION NUMBER

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS 1. REQUISITION NUMBER PAGE OF

1 54 1084813OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

TELEPHONE NO.

17a. CONTRACTOR/

KOOSKIA ID 83539

502 LOWRY STREET

LOCHSA RANGER DIST KOOSKIA OFFICE

USDA FOREST SERVICE

15. DELIVER TO

COEUR DALENE ID 83815

3232 WEST NURSERY ROAD

SUPERVISORS OFFICE

9. ISSUED BY

7.

2. CONTRACT NO.

EFFECTIVE DATE

$11.5

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW

ISSUE DATE

DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

11.

SEE SCHEDULE

12. DISCOUNT TERMS

THIS CONTRACT IS A

RATED ORDER UNDER

DPAS (15 CFR 700)

13a.

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

HUBZONE SMALL

BUSINESS

8(A)

IDAHO PANHANDLE NATIONAL FORESTS

WOMEN-OWNED SMALL BUSINESS

(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

24.

AMOUNT

23.

UNIT PRICE

22.

UNIT

21.

QUANTITY

20.

SCHEDULE OF SUPPLIES/SERVICES

19.

ITEM NO.

Trail Maintenance Contract Nez Perce-Clearwater National Forests-Forest Wide This is estimated to be a multiple award contract. Please return the 1449, price cost schedule, past performance and reps and certs to daniel.szambelan@usda.gov Delivery: 05/01/2024 Period of Performance: 06/01/2023 to 04/30/2028

0001 All items, Forest-wide, per Schedule B Continued ...

(Use Reverse and/or Attach Additional Sheets as Necessary)

HEREIN, IS ACCEPTED AS TO ITEMS:

XX

DATED

DANIEL A. SZAMBELAN

. YOUR OFFER ON SOLICITATION (BLOCK 5),

INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE SET FORTH

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER

ARE

ARE

31c. DATE SIGNED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA

31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (Type or print)

ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL

SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA

26. TOTAL AWARD AMOUNT (For Govt. Use Only)

OFFER

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA - FAR (48 CFR) 53.212

ARE NOT ATTACHED.

ARE NOT ATTACHED.

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

30b. NAME AND TITLE OF SIGNER (Type or print)

30a. SIGNATURE OF OFFEROR/CONTRACTOR

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

25. ACCOUNTING AND APPROPRIATION DATA

29. AWARD OF CONTRACT:

REF.

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32c. DATE 32b. SIGNATURE OF AUTHORIZED GOVERNMENT REPRESENTATIVE

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

40. PAID BY39. S/R VOUCHER NUMBER38. S/R ACCOUNT NUMBER

37. CHECK NUMBER

FINALPARTIAL

36. PAYMENT

FINALPARTIAL

35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER33. SHIP NUMBER

COMPLETE

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

42d. TOTAL CONTAINERS42c. DATE REC'D (YY/MM/DD)

42b. RECEIVED AT (Location)

42a. RECEIVED BY (Print)

41c. DATE41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

STANDARD FORM 1449 (REV. 2/2012) BACK

24.

AMOUNT

23.

UNIT PRICE

22.

UNIT

21.

QUANTITY

20.

SCHEDULE OF SUPPLIES/SERVICES

19.

ITEM NO.

32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT REPRESENTATIVE

54 2 of

Continuation of 1449Price Cost Schedule Part B - Schedule of Items

Base Period of Performance: Date of Award to 04/30/2024

Item No. Description Unit QTY Unit Price* Total

1 NZ Trails #191, #531, #691 Mile 27.8 NW 2 NZ Trails #167, #634 Mile 33.5 NW 3 NZ Trail #567 Mile 22.5 NW 4 NZ Trails #419-A, #414, #429, #478 Mile 23.6 NW 5 NZ Trails #144, #169 Mile 32.3 NW

NZ Trails #735, #747, #740, #740-A, #740-B, #740-C Mile 16.4 NW

7 CZ Trails #405, #693 Mile 1.0 NW 7 cont’d Mile 18.2 W

CZ Trails #49, #49-A, #60, #917, #24, #89 Mile 3.6 NW

8 cont’d 40.3 W 9 CZ Trail #206 Mile 10.0 NW

9 cont’d 38.3 W 10 CZ Trail #133 Mile 5.0 NW

10 cont’d 5.8 W 11 SZ Sourdough Trails Mile 41.6 NW

11 cont’d 0.55 W 12 SZ American River Trails Mile 19.5 NW 13 SZ Rapid River Trails Mile 17.0 NW

Base Total:

Option Year One 05/01/2024 to 04/30/2025

Item No. Description Unit QTY Unit Price* Total

1 NZ Trails #191, #531, #691 Mile 27.8 NW 2 NZ Trails #167, #634 Mile 33.5 NW 3 NZ Trail #567 Mile 22.5 NW 4 NZ Trails #419-A, #414, #429, #478 Mile 23.6 NW 5 NZ Trails #144, #169 Mile 32.3 NW

NZ Trails #735, #747, #740, #740-A, #740-B, #740-C Mile 16.4 NW

7 CZ Trails #405, #693 Mile 1.0 NW 7 cont’d Mile 18.2 W

CZ Trails #49, #49-A, #60, #917, #24, #89 Mile 3.6 NW

8 cont’d 40.3 W 9 CZ Trail #206 Mile 10.0 NW

9 cont’d 38.3 W 10 CZ Trail #133 Mile 5.0 NW

10 cont’d 5.8 W 11 SZ Sourdough Trails Mile 41.6 NW

11 cont’d 0.55 W 12 SZ American River Trails Mile 19.5 NW 13 SZ Rapid River Trails Mile 17.0 NW

Option Year 1 Total:

Option Year Two 05/01/2025 to 04/30/2026

Item No. Description Unit QTY Unit Price* Total

1 NZ Trails #191, #531, #691 Mile 27.8 NW 2 NZ Trails #167, #634 Mile 33.5 NW 3 NZ Trail #567 Mile 22.5 NW 4 NZ Trails #419-A, #414, #429, #478 Mile 23.6 NW 5 NZ Trails #144, #169 Mile 32.3 NW

NZ Trails #735, #747, #740, #740-A, #740-B, #740-C Mile 16.4 NW

7 CZ Trails #405, #693 Mile 1.0 NW 7 cont’d Mile 18.2 W

CZ Trails #49, #49-A, #60, #917, #24, #89 Mile 3.6 NW

8 cont’d 40.3 W 9 CZ Trail #206 Mile 10.0 NW

9 cont’d 38.3 W 10 CZ Trail #133 Mile 5.0 NW

10 cont’d 5.8 W 11 SZ Sourdough Trails Mile 41.6 NW

11 cont’d 0.55 W 12 SZ American River Trails Mile 19.5 NW 13 SZ Rapid River Trails Mile 17.0 NW

Option Year 2 Total:

Option Year Three 05/01/2026 to 04/30/2027

Item No. Description Unit QTY Unit Price* Total

1 NZ Trails #191, #531, #691 Mile 27.8 NW 2 NZ Trails #167, #634 Mile 33.5 NW 3 NZ Trail #567 Mile 22.5 NW 4 NZ Trails #419-A, #414, #429, #478 Mile 23.6 NW

5 NZ Trails #144, #169 Mile 32.3 NW

NZ Trails #735, #747, #740, #740-A, #740-B, #740-C Mile 16.4 NW

7 CZ Trails #405, #693 Mile 1.0 NW 7 cont’d Mile 18.2 W

CZ Trails #49, #49-A, #60, #917, #24, #89 Mile 3.6 NW

8 cont’d 40.3 W 9 CZ Trail #206 Mile 10.0 NW

9 cont’d 38.3 W 10 CZ Trail #133 Mile 5.0 NW

10 cont’d 5.8 W 11 SZ Sourdough Trails Mile 41.6 NW

11 cont’d 0.55 W 12 SZ American River Trails Mile 19.5 NW 13 SZ Rapid River Trails Mile 17.0 NW

Option Year 3 Total:

Option Year Four 05/01/2027 to 04/30/2028

Item No. Description Unit QTY Unit Price* Total

1 NZ Trails #191, #531, #691 Mile 27.8 NW 2 NZ Trails #167, #634 Mile 33.5 NW 3 NZ Trail #567 Mile 22.5 NW 4 NZ Trails #419-A, #414, #429, #478 Mile 23.6 NW 5 NZ Trails #144, #169 Mile 32.3 NW

NZ Trails #735, #747, #740, #740-A, #740-B, #740-C Mile 16.4 NW

7 CZ Trails #405, #693 Mile 1.0 NW 7 cont’d Mile 18.2 W

CZ Trails #49, #49-A, #60, #917, #24, #89 Mile 3.6 NW

8 cont’d 40.3 W 9 CZ Trail #206 Mile 10.0 NW

9 cont’d 38.3 W 10 CZ Trail #133 Mile 5.0 NW

10 cont’d 5.8 W 11 SZ Sourdough Trails Mile 41.6 NW

11 cont’d 0.55 W 12 SZ American River Trails Mile 19.5 NW 13 SZ Rapid River Trails Mile 17.0 NW

Option Year 3 Total:

Base Total:

OY One:

OY Two:

OY Three:

OY Four:

Total Contract Value:

*(NW) Non-Wilderness, (W) Wilderness

For each item, please provide a price per mile.

Regular per mile work includes the following requirements: 982 – Logging Out, 984 – Loose Rock Removal, 991 – Drainage Maintenance

Solicitation No: 1284LL23Q0037 Project Name: Trail Maintenance Nez Perce-Clearwater N.F.

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C-1 SCOPE OF CONTRACT

The Nez Perce-Clearwater National Forest requires annual trail opening and maintenance on Forest Service trails. The work includes logging out, drainage maintenance and rock removal on non-wilderness and wilderness trails as described in the technical specifications. Slide maintenance and tread repair are required in connection with uprooted trees. Contractors shall be held responsible for all downed trees;

there will be NO tree counting. However, trees felled by unusual, extreme wind events are outside the scope of this contract. Slide maintenance/tread repair (outside of that referred to above) and brushing are not standard trail opening/maintenance requirements but may be authorized by separate orders as needed and negotiated under the rates provided in Items 17-19. The Contractor(s) shall furnish all labor, supervision, equipment and materials to perform all operations necessary to accomplish the work in accordance with the contract terms, conditions, specifications, drawings and contract attachments/exhibits.

This solicitation will result in the award of multiple firm fixed priced contracts. Each resultant award will require performance of trail maintenance work for the Forest in a specific geographic area as defined by the Item descriptions and maps provided as attachments to the contract. Only one contractor will be awarded work for each geographic area.

This project is one of the implementation projects of the Collaborative Forest Landscape Restoration Project (CFLRP). The goal of the CFLRP project is to utilize collaborative, science based ecosystem restoration techniques to improve watershed function while encouraging ecological, economic and social sustainability with an emphasis on providing local employment opportunities.

This project is also within the Central Idaho Complex Priority Trail Maintenance area.

C-2 PROJECT LOCATION North Zone Items 1 through 6

NORTH FORK DISTRICT ITEM # 1 For 2023

Work items include: 982(01) Logout 984(01) Loose Rock Removal 991(01) Drainage Maintenance

Note: Last Maintenance Period is intended to identify the last time FS records reflect any work performed on the trail; it does not necessarily mean that all maintenance work items were performed on all miles or to full maintenance standards. Contractors are responsible for assessing trail conditions.

• Power Tools are allowed

• Motorcycles are allowed on all trails

Total: 27.8 miles

Tr. #191 Junction Mountain (13.1 miles) Starting Point: T39N R10E, Sec. 17, jct. Tr. #106 Ending Point: T38N R10E, Sec. 15, jct. Tr. #531

Last maintenance period was 2022, log out.

Tr. #531 Windy Bill (14.2 miles) Starting Point: T37N R10E, Sec. 7, Jct. Tr. 167 Ending Point: T39N R11E, Sec. 31, Jct. Tr. 524 Last maintenance period was 2022, log out, brushing.

Tr. #691 Junction Lookout (.5 miles) Starting Point: T39N R9E, Sec. 25, jct. Tr. #191 Ending Point: T39N R9E, Sec. 25, at lookout tower

NORTH FORK DISTRICT ITEM # 2 For 2023

Work items include: 982(01) Logout

984(01) Loose Rock Removal 991(01) Drainage Maintenance

Note: Last Maintenance Period is intended to identify the last time FS records reflect any work performed on the trail; it does not necessarily mean that all maintenance work items were performed on all miles or to full maintenance standards. Contractors are responsible for assessing trail conditions.

• Power Tools are allowed

• Motorcycles are allowed on some trails

Total: 33.5 miles

Tr. #167 Windy Ridge (24.8 miles) Starting Point: T38N R9E, Sec. 6, jct. Rd. 250

Ending Point: T37N R10E, Sec. 35, jct. Rd. 500 Last maintenance period was 2022.

Motorcycles are allowed after Aug.1, from Rd. 250 to Jct. with Tr. 531

Tr. #634 Windy Creek (8.7 miles)

Starting Point: T36N R9E, Sec. 3, jct. Tr. 20 Ending Point: T37N R10E, Sec. 21, jct. Tr. 167 Last maintenance period was 2020, by contract. Partially cleared by users in 2021.

Motorcycles are not allowed

NORTH FORK DISTRICT ITEM # 3 for 2023

Work items include: 982(01) Log out performed on all miles or to full maintenance standards. Contractors are responsible for assessing trail conditions.

Total: 22.5 miles

Tr. #567 Kelly Creek (22.5 miles) Starting Point: T39N R12E, Sec. 16, jct. Rd. 581

Ending Point: T40N R13E, Sec. 27, jct. Tr. 738 Last maintenance period was 2022.

Motorcycles are not allowed

NORTH FORK DISTRICT ITEM # 4 for 2023

Work items include: 982(01) Log out performed on all miles or to full maintenance standards. Contractors are responsible for assessing trail conditions.

Total: 23.6 miles

Tr. #419-A Fish Lake Stock Bypass (1.1 miles) Starting Point: T40N R12E, Sec. 18, jct. Tr. 419 Ending Point: T40N R12E, Sec. 11, jct. Tr. 419 Last maintenance period was 2021.

Motorcycles are not allowed

Tr. #414 Goose Creek (5.8 miles)

Starting Point: T41N R12E, Sec.30, jct. Rd. 5450 Ending Point: T41N R12E, Sec. 10, jct. Tr. 738, at Goose Lake Last maintenance period was 2021, by contract.

Motorcycles are not allowed

Tr. #429 Osier Ridge (5.2 miles) Starting Point: T40N R11E, Sec. 12, Osier L.O., jct. Rd. 737B Ending Point: T40N R12E, Sec. 22, jct. Tr. 478

Last maintenance period was 2019, by contract. Partially cleared by users in 2021.

Tr. #478 Pollock Ridge (11.5 miles)

Starting Point: T39N R11E, Sec. 10, jct. Rd. 255 Ending Point: T40N R12E, Sec. 10, jct. Tr. 419 Trail was partially maintained in 2021, by contract and users.

NORTH FORK DISTRICT ITEM # 5 for 2023

Work items include: 982(01) Log out 984(01) Loose Rock Removal 991(01) Drainage Maintenance

Note: Last Maintenance Period is intended to identify the last time FS records reflect any work performed on the trail; it does not necessarily mean that all maintenance work items were

• Motorcycles are allowed on some trails

Total: 32.3 miles

Tr. #144 Pot Mtn. (19.4 miles) Starting Point: T38N R8E, Sec. 18, at the Bungalow, jct. Rd. 250F Ending Point: T40N R8E, Sec. 36, jct. Rd. #711 Partially logged out by partners in 2022.

Tr. #169 Pot Mountain Ridge (12.9 miles) Starting Point: T39N R9E, Sec. 6, jct. Rd. 711 Ending Point: T41N R10E, Sec. 31, jct. Rd. 715 Partially logged out by partners in 2022.

Motorcycles are allowed from Mush Saddle to Cold Springs Peak Cabin

PALOUSE DISTRICT ITEM # 6 For 2023

Note: Last Maintenance Period is intended to identify the last time FS records reflect any work performed on the trail; it does not necessarily mean that all maintenance work items were

• Motorcycles are not allowed

Total: 16.4 miles

Trail #735 Falls Reservoir Link (3.3 miles) Starting Point: T40N R2E, Sec. 35, jct. Rd. #4769 at Elk Creek Campground Ending Point: T39N R2E Sec. 2,, jct. Tr. 1452A, near Elk Creek Falls Last maintenance period was 2022 by partners

Trail #747 Upper Basin (4.9 miles) Starting Point: T41N R3E, Sec. 2, jct. Rd. #382 Ending Point: T41N R3E, Sec. 1, jct. Rd. #382 Last maintenance period was 2022 by partners

Trail # 740 Elk Creek Falls (.9 miles) Starting point: T39N R2E Sec. 11, Jct Road #1452 Falls Road Ending Point: T39N R2E Sec. 11, Trail # 740-A Upper Falls Loop Last maintenance period was 2022 by Forest Service Crew Motorcycles are not allowed.

Trail # 740-A Upper Falls Loop (.3 miles) Starting point: T39N R2E Sec. 11, Trail # 740 Elk Creek Falls Ending Point: T39N R2E Sec. 11, Trail # 740 and Trail # 740-B Middle Falls Overlook Jct.

Last maintenance period was 2022 by Forest Service Crew Motorcycles are not allowed.

Trail # 740-B Middle Falls (.4 miles) Starting point: T39N R2E Sec. 11, Trail # 740 Elk Creek Falls Ending Point: T39N R2E Sec. 11, Trail # 740-D Lower Falls Overlook Last maintenance period was 2022 by Forest Service Crew Motorcycles are not allowed.

Trail # 740- C Middle Falls Overlook (.1 miles) Starting point: T39N R2E Sec. 11, Trail # 740 Elk Creek Falls Ending Point: T39N R2E Sec. 11, Dead Ends at Middle Falls Overlook Last maintenance period was 2022 by Forest Service Crew Motorcycles are not allowed.

Trail # 740-D Lower Falls Overlook (1.1 miles)

Starting point: T39N R2E Sec. 11, Trail # 740 Elk Creek Falls Ending Point: T39N R2E Sec. 11, Dead Ends at Lower Falls Overlook Last maintenance period was 2022 by Forest Service Crew Motorcycles are not allowed.

Trail # 740-E Upper Falls Overlook (.1 miles) Starting point: T39N R2E Sec. 11, Trail # 740-A Upper Falls Loop Ending Point: T39N R2E Sec. 11, Dead Ends at Upper Falls Overlook Last maintenance period was 2022 by Forest Service Crew Motorcycles are not allowed.

Trail #765 Potlatch Canyon Loop (5.3 miles) Starting Point: T40N R1W, Sec. 27, Jct Road #1963 mouth of Meadow Cr.

Ending Point: T40N R1W, Sec. 27, Jct Road #1963 mouth of Meadow Cr.

Last maintenance period was 2022 by partners

Central Zone Trail Maintenance -- Items 7-10

CZ MCRD ITEM # 7 For 2023

• Power Tools are not allowed on all trails except 1 mile of #693

• Motorcycles are not allowed on all trails

Non-Wilderness Miles: 1.0 Wilderness Miles: 18.2 Total: 19.2 miles

Tr. #693 Big Rock (1 non-Wilderness mile, 9.7 Wilderness miles) Starting Point: T32N R10E Sec. 15 - Big Fog Saddle TH / Jct. FSR 319, Ending Point: T33N R11E Sec. 30 - Jct. Tr. #405

Tr. #405 Three Links (8.5 Wilderness miles)

Starting Point: T33N R11E Sec 30 - Jct. Tr. #693, Ending Point: T32N R11E Sec 22 - Jct. Tr. #4, CZ LPRD ITEM # 8 For 2023

• Power Tools are not allowed on all trails except trail #49-A, and 2.2 miles of #49

Non-Wilderness Miles: 3.6 Wilderness Miles: 40.3 Total: 43.9 miles

Tr. #49 Warm Springs: 14.5 miles (2.2 non-Wilderness miles, 12.3 Wilderness miles) Starting Point: T36N R13E Sec 7 - Warm Springs TH/Jct. Hwy 12, Ending Point: T35N R13E Sec 26 - Jct. Tr. #60, Tr. #49-A Warm Springs Stock By-Pass: 1.4 miles (non-Wilderness) Starting Point: T36N R13E Sec 7 - Jct. Tr. #49 near Warm Springs TH Ending Point: T34N R16E Sec 17 - Jct. Tr. #49 above the hotsprings Last maintenance period was 2022, log out.

Tr. #60 Army Mule: 10.6 miles (Wilderness) Starting Point: T35N R13E Sec 26 - Jct. Tr. #49, Ending Point: T35N R12E Sec 22 - Jct. Tr. #211 Last maintenance period was 2020, log out.

Tr. #917 Pedro Ridge: 5 miles (Wilderness) Starting Point: T35N R13E Sec 4 - Jct. Tr. #49 Ending Point: T35N R12E Sec 22 - Jct. Tr. #60 Last maintenance period was 2020, log out.

Tr. #24 Wind Lakes: 6.9 miles (Wilderness) Starting Point: T35N R13E Sec 4 - Jct. Tr. #49 Ending Point: T35N R14E Sec 08 - Jct. Tr. #89 Last maintenance period was 2020, log out.

Tr. #89 Saturday Ridge: 5.5 miles (Wilderness) Starting Point: T35N R13E Sec 26 - Jct. Tr. #49 Ending Point: T35N R14E Sec 08 - Jct. Tr. #24 Last maintenance period was 2020, log out.

CZ LPRD and MCRD ITEM # 9 For 2023

• Power Tools are not allowed in Designated Wilderness

Non-Wilderness Miles: 10 Wilderness Miles: 38.3 Total: 48.3

Tr. #206 Eagle Mountain: 48.3 miles (10 non-Wilderness miles, 38.3 Wilderness miles) Starting Point: T32N R8E Sec 1 - Jct. FSR #317, Ending Point: T36N R11E Sec 30 - Eagle Mtn TH / Jct. Hwy 12, Last maintenance period was 2020, log out. Portions of the trail were maintained in 2021 and 2022.

CZ LPRD ITEM # 10 For 2023

• Power Tools are not allowed in Designated Wilderness

Non-Wilderness Miles: 5

Wilderness Miles: 5.8 Total: 10.8

Tr. #133 Split Creek: 10.8 miles (5 miles non-Wilderness, 5.8 miles Wilderness) Starting Point: T33N R9E Sec 23 - Jct. Tr. #206 Ending Point: T33N R8E Sec 2 - Split Creek TH / Jct. Hwy 12 Last maintenance period was 2021, log out.

South Zone Trail Maintenance -- Items 11-13

SZ RRRD ITEM # 11 For 2023

• Power Tools are allowed on all except .55 mile of GHW #806

Total: 42.15 miles

Tr. #411 Sourdough/Wing Creek (4.7 miles) Starting Point: T28N R6E NWSW Sec. 17, jct. w/Tr. #412 Ending Point: T28N R5E NENW Sec. 35, jct. w/Rd. #492, Tr. #412 Reed Bar (7.12 miles) Starting Point: T28N R6E SWNE Sec. 3, jct. w/Rd. #1875 Ending Point: T28N R6E NE Sec. 21, jct. w/Rd. #492

Tr. #414 Twentymile (2.9 miles) Starting Point: T28N R6E SWNW Sec. 28, jct. w/Rd. #492 Ending Point: T27N R6E NWSW Sec. 4, jct. w/Tr. #881

Tr. #812 W. Fork Twenymile (2.11 miles) Starting Point: T28N, R6E NW20 Sec 20, jct. w/Tr. #412

Ending Point: T28N, R6E SW Sec 30, jct. w/Rd. #492

Tr. #881 Driveway Extension (4.6 miles) Starting Point: T28N R5E SW Sec. 35 jct. w/ Rd. 492 Ending Point: T27N R6E SW Sec. 4, jct. w/Tr. #414

Tr. #804 Lost Lake (0.54miles) Starting Point: T27N R6E NW Sec. 5, jct. w/Tr. #881, Ending Point: T28N R6E NE Sec. 32, Lost Lake

Tr. #806 Twentymile Lake (0.55 miles) Starting Point: Jct. w/ Tr. #881, T27N R6E NW Sec. 5 Ending Point: Twentymile Lake, T27N R6E SW Sec. 5 Last maintenance period was 2021, log out. Wilderness no power tools

Tr. #884 Twenymile Cutoff (1.73 miles) Starting Point: Jct. w/ Rd. 492, T28N, R6E NE Sec 21 Ending Point: Jct. w/ Tr. #414, T28N R6E NW Sec 28

Tr. #401 Frank Brown (8.1 miles) Starting Point: Sourdough Peak Ending Point: Jct. w/Tr. #407 Last maintenance period was 2021, log out.

Tr. #407 Snoose Creek (5.8 miles) Starting Point: jct. w/Tr. #401 Ending Point: jct. w/Tr.431 Last maintenance period was 2021, log out.

Tr. #431 Driveway (4 miles) Starting Point: Jct. w/Tr. #407 Ending Point: Sourdough Peak

SZ RRRD ITEM # 12 For 2023 performed on the trail; it does not necessarily mean that all maintenance work items were

Total: 19.5 miles

Tr. #836 American River (8.3 miles) Starting Point: Jct. with Rd # 443, T30N R8E SWNW Sec 34 Ending Point: Jct. w/ Rd. 464, T31N R8E NE Sec. 28

Tr. #811 Lick Creek (3.8 miles) Starting Point: Jct. w/ Tr. #836, T30N R8E NW Sec.21 Ending Point: jct. w/Rd. #464, T30N R8E NW Sec 5 Last maintenance period was 2021, log out, Tr. #813 Limber Luke (1.9 miles) Starting Point: Jct. w/Rd. #443, T30N R8E SWSE Sec. 2 Ending Point: Jct. w/Tr. #836, T30N R8E SESW Sec. 10

Tr. #510 Flint Creek (5.5 miles) Starting Point: Jct. w/Rd. #443, T30N R8E SWNW Sec. 34 Ending Point: Jct. w/Tr. #835, T30N R9E NENW Sec. 18

SZ SRRD ITEM # 13 For 2023

Total: 17.0 miles

Tr. #59 Rapid River (0.25 miles) Starting Point: T23N R1W, Sec. 2, intersection with Tr. 166, Wyant Camp Ending Point: T23N R1W, Sec. 2, intersection with Tr. 71

Tr. #61 Frank Wurl (3.2 miles) Starting Point: T23N R1W, Sec. 29, intersection with Tr. 113 Ending Point: T23N R2W, Sec.19, intersection with Tr. 101 Last maintenance period was 2021, log out, brushing.

Tr. #62 Dodge Ridge (2.7 miles) Starting Point: T23N R1W, Sec. 31, intersection with Tr. 113 Ending Point: T23N R2W, Sec.36, intersection with Tr. 101

Tr. #71 Oxbow Trail (6.95 miles) Starting Point: T23N R1W, Sec. 31, intersection with Tr. 113 Ending Point: T23N R1W, Sec. 2, intersection with Tr. 59, Wyant Camp

Tr. #113 West Fork Rapid Rive (3.9 miles) Starting Point: T23N R1W, Sec. 29, intersection with Tr. 61, McCrea Cabin Ending Point: T23N R1W, Sec.1, Wilderness Boundary

B.1. he locations of the trails are outlined in detail on the maps attached separately and the Item Descriptions/Item Summary for each Item, see the attachments for details. Orofino, Idaho (North Zone) office is located approximately 82.5 miles North of White Bird, Idaho (South Zone – Salmon River R.D.) or 1hr 35mins and approximately 99.1 miles North/NW from Elk City, Idaho (South Zone – Red River R.D.) or 2hrs 20mins. The South Zone offices (Salmon River and Red River) are approximately 78.5 miles or 1hr 55mins from each other.

a. North Zone District Office Address:

North Fork Ranger District 12740 Highway 12 Orofino, ID 83544

b. South Zone District Office Address(es):

Salmon River Ranger District 304 Slate Creek Road White Bird, ID 83554

c. Central Zone District Office Address:

AND

Red River Ranger District 300 American River Road Elk City, ID 83525

C-3 REQUIREMENTS (982, Logging Out, 984 Loose Rock Removal, and 991 Drainage Maintenance)

Section 982 – Logging Out Description

982.01 Work. This work consists of removing brush, logs, and down trees from the clearing limits.

Requirements

982.02 Clearing Out. Cut and remove all logs that extend across or into the clearing limits as SHOWN ON THE DRAWINGS or 1 ft. above the top of the cut-slope of all ditches, catch basins, and trail structures, whichever is greater. This includes all previously cut logs within the defined clearing limits.

All limbs from fallen trees that extend into the clearing limits must be cut flush to the bole of the tree and removed. The portions of cut logs that remain on the upper side of the trail shall be either firmly anchored to prevent sliding or rolling onto the trail way or moved across the trail to the lower side and scattered outside the clearing limits.

Fell all trees over 3 inches in diameter that are leaning into the clearing limits and that are within 10 feet above the trail bed as SHOWN ON THE DRAWINGS. Stump height of leaning trees that are cut outside the clearing limits shall be cut flush on the uphill side of the stump. Disposal and payment for the leaning trees described above will be the same as for down logs and trees.

Remove roots, root wads, and stumps from trees within the clearing limits that have been uprooted. Fill any holes within the clearing limits with suitable material and compact.

Rerouting the trail around windfalls, uprooted trees, and other obstacles will not be permitted. Repair sections of the trail tread that have been damaged by uprooted stumps as necessary to provide safe passage on the trail. Payment for such work will be incidental to the specified work item, and no extra payment will be made.

Remove sticks or wood chunks exceeding 2 inches in diameter or 1 foot in length that have fallen on to the trail bed.

Scatter the down trees on the lower side of the trail way outside the clearing limits. Do not place such materials in stream channels, drainage ways, ditches, culvert catch basins, or other locations where they would prevent the free flow of water away from the trail bed.

Measurement

982.03 Method. Determine the quantity of logging out units by measuring the slope distance along the trail centerline.

Payment

982.04 Basis Make payment, for all units inspected and accepted, at the unit prices SHOWN IN THE

SCHEDULE OF ITEMS.

Make payment under:

PAY ITEM PAY UNIT

982(01) Logging Out mile

Section 984 – Loose Rock Removal Description

984.01 Work. This work consists of removal and disposal of loose rock from the trail tread

Requirements

984.02 General. Remove loose rocks that are larger than two (2) inches at their greatest dimension from the trail bed. Remove any loose rock in drainage dips or ditches that may impede water flow off the trail.

Loose rocks are rocks that are not firmly embedded in the trail and can be removed by hand. Where the trail bed consists predominantly of rock with little or no soil present, remove all loose rock larger than 3 inches.

Fill any holes remaining from rock removal with suitable material and compact. If the rock removed is not needed for other items of maintenance work, scatter the rock by side casting to the lower side of trail way beyond the clearing limits, and distribute rock to ensure that no blockage of drainage or creation of a windrow occurs. Do not dispose of waste materials in watercourses.

Measurement

984.03 Method. Determine the quantity of loose rock removal units by measuring the slope distance along the trail centerline.

Payment

984.04 Basis. Make payment, for all units inspected and accepted, at the unit price SHOWN IN THE

SCHEDULE OF ITEMS.

Make payment under:

984 (01) Loose Rock Removal mile

Section 991 – Drainage Maintenance Description

991.01 Work. This work consists of cleaning all drainage structures such as: culverts, water bars, drainage dips, ditches, stream fords, gully crossings, puncheons and bridges. Drainage maintenance also includes removal of vegetation and debris from the disturbed (constructed) surface area of the drainage structure, such as ditches, catch basins, water bar spillways, sumps, etc.

Materials

991.02 Requirements. Use materials meeting the requirements of the following sections:

961 -- Rock, Grid Pavement Units, and Aggregate 962 – Materials for Timber Structures

Requirements

991.03 General. Where trail drainage facilities have been plugged and the water has been diverted from the intended channel, remove the debris causing the diversion and return the drainage to the channel.

Divert water off and away from the trail bed.

Clean ditches to permit the free flow of water into culverts and away from the trail. Remove all woody vegetation that is within 1 ft. of the top of the cut-slope of all ditches and catch basins.

Scatter all unusable or unneeded material that is cleared from the drainage structures 3 feet or more beyond and below the trail or drainage facility and out of watercourses.

991.04 Culverts. Remove debris and soil from catch basins and inlet and outlet ditches and inside culverts to permit the unobstructed flow of water into, through, and away from the culvert.

991.05 Water bars. Clean the upgrade side of all existing water bars and maintain them as SHOWN ON THE DRAWINGS. Use and compact suitable material removed from the upgrade side of wood and rock water bars to bring the trail tread flush with the top of those water bars on the downgrade side. Rubber belted water bars should have all debris removed from the upgrade and downgrade sides of the rubber belting in order to allow the rubber to flex as intended. Remove all accumulated soil and debris from the leadoff area and outlet ditches of all water bars until the drain is a minimum of 4 in. deep and ditches are a minimum of 12 in. wide with angled cut slopes as SHOWN ON THE DRAWINGS. All leadoff ditches must maintain a sustained negative grade until water flows freely down the hill slope.

991.06 Drainage Dips. Clean deposited material and restore drainage dips as SHOWN ON THE DRAWINGS. Remove all debris from the leadoff area of dips until the drain is a minimum of 4 in. deep and ditches are a minimum of 12 in. wide with angled cut slopes as SHOWN ON THE DRAWINGS. All leadoff ditches must maintain a sustained negative grade until water flows freely down the hill slope.

Use suitable material obtained by cleaning dips for fill on the downgrade side, removing rock more than 2 inches at its greatest dimension. Compact all material placed in the trail tread.

991.07 Trail Structures. Clean all debris off of the surface of all lumber decked trail structures, such as bridges and puncheons. Dispose of debris on the down slope side of trail out of clearing limits. Do not place such materials in stream channels, drainage ways, ditches, culvert catch basins, or other locations where they would prevent the free flow of water away from the trail bed.

991.08 Stream fords and Gully Crossings. Remove debris and loose rocks over 2 inches from existing stream crossings to provide the tread width. Level and smooth the stream bottom with gravel or rock less than 2 inches in greatest dimension to provide a crossing.

Measurement

991.09 Method. Determine the quantity of drainage maintenance units by measuring the slope distance along the centerline. Measure other items by a count of those designated.

Payment

991.10 Basis. Make payment for all units inspected and accepted, at the unit price SHOWN IN THE

SCHEDULE OF ITEMS.

Make payment under:

991(01) Drainage Maintenance mile

C-4 PERFORMANCE DEADLINES

The starting dates in the table below are estimates of when work may begin on an Item; however, not all trail segments within an Item are expected to be open on that date. Regardless of actual starting date, all Trail Maintenance Items shall be completed no later than the dates shown in the table below for the year in which award or renewal was made.

The Contractor shall make progress at a rate that will assure completion of work by the required completion date for each Item. Award of more than one Item to a Contractor will not change the required performance period for each Item. If multiple Items are awarded to one Contractor, the respective performance times will run concurrently, not consecutively. Work may be performed on each Item in succession provided a rate of progress is maintained to ensure completion of all work by the required deadlines.

ITEM

NO.

DESCRIPTON ESTIMATED

STARTING

DATE

RREQUESTED

COMPLETION

DATE

Option Year 1

Option Year 2

1 NZ Trails #191, #531, #691

6/15/2023 9/30/2023 6/15/2024 to

07/30/2024

6/15/2025 to

07/30/2025

2 NZ Trails #167, #634

6/15/2023 9/30/2023 6/15/2024 to

07/30/2024

6/15/2025 to

07/30/2025

3 NZ Trail #567

5/15/2023 9/30/2023 6/15/2024 to

07/30/2024

6/15/2025 to

07/30/2025

NZ Trails #419-A, #414, #429, #478

6/15/2023 9/30/2023 6/15/2024 to

07/30/2024

6/15/2025 to

07/30/2025

5 NZ Trails #144, #169

6/15/2023 9/30/2023 6/15/2024 to

07/30/2024

6/15/2025 to

07/30/2025

NZ Trails #735, #747, #740, #740-A, #740-B, #740-C

5/15/2023 9/30/2023 6/15/2024 to

07/30/2024

6/15/2025 to

07/30/2025

7 CZ Trails #405, #693

6/15/2023 9/30/2023 6/15/2024 to

07/30/2024

6/15/2025 to

07/30/2025

CZ Trails #49, #49-A, #60, #917, #24, #89

6/15/2023 9/30/2023 6/15/2024 to

07/30/2024

6/15/2025 to

07/30/2025

9 CZ Trail #206

6/15/2023 9/30/2023 6/15/2024 to

07/30/2024

6/15/2025 to

07/30/2025

10 CZ Trail #133

6/15/2023 9/30/2023 6/15/2024 to

07/30/2024

6/15/2025 to

07/30/2025

11 SZ Sourdough Trails

7/01/2023 10/10/2023 6/15/2024 to

08/30/2024

6/15/2025 to

08/30/2025 12 SZ American River Trails 5/01/2023 10/1/2023 6/15/2024 6/15/2025 to 08/30/2024 to 08/30/2025

13 SZ Rapid River Trails

7/01/2023 10/15/2023 6/15/2024 to

08/30/2024

6/15/2025 to

08/30/2025

Prior to commencement of work, the COR will arrange a meeting with the Contractor to discuss the contract terms and work performance requirements. Also at this meeting such things as work progress schedule and fire prevention and suppression plans shall be discussed. The Contractor may begin work under the contract when conditions are suitable and upon issuance of a Notice to Proceed (see FAR 52.211-10 Alt I).

C-5 GOVERNMENT FURNISHED PROPERTY NONE

C-6 USE OF MOTORIZED EQUIPMENT AND VEHICLES

It is the responsibility of the successful bidder to ensure that motorized equipment and/or transport/use is commensurate with the management directions for the areas in which the trails are located. The Nez Perce-Clearwater National Forest Motor Vehicle Use Map (MVUM) for the Clearwater NF and Forest Access guide for the Nez Perce NF provide information on roads and trails with motorized use restrictions. These guides are available from Nez Perce-Clearwater National Forest Supervisor’s and Ranger District Offices. All areas outside of wilderness provide for the use of chainsaws.

C-7 STOCK LIMITATIONS

In order to decrease chances for site degradation, the use of saddle and pack stock will be kept at the minimum necessary to accomplish the project. A maximum 6 head per trip addresses the initial camp and tool supply. Once tools and camp are transported into the job site, use of stock will be limited to 3 head* during the length of the project. At the end of the project and for complete camp movement during the project, stock shall not exceed 6 head. Stock not in use shall be removed from the National Forest until such time as they are required.

*Based on a 2 person crew – 2 riding and 1 pack animal. (Requests for additional stock will be submitted in writing and approved by the CO prior to use.)

C-8 CAMPING

There are a limited number of campsites in some trail areas. Campsites shall be addressed and designated at the pre-work meeting. The Contractor's campsite will be subject to weekly inspections by a Government Inspector to assure that minimum impact requirements are met. (See Attachment 1 - Minimum Impact Camping Guidelines)

C-9 CLEANUP OF WORK AND CAMP AREAS

The project area(s) shall be restored to as close to its original natural appearance as possible. The work area impact must be kept to a minimum. All debris and litter shall be removed from site. Litter shall be packed out, and the native debris shall be scattered outside the trail clearing limit. No debris shall be scattered into any stream, lake, snow pond, meadow, or other water course. (See Attachment 1 -

Minimum Impact Camping Guidelines)

Noxious Weed Closure Order. The contractor shall comply with the Special Order issued for all National Forest System Lands within the State of Idaho which prohibits the possession or storage of hay, straw or mulch that is not certified by an authorized official as being Noxious weed or Noxious Weed Seed Free. A Contractor possessing hay, straw or mulch in the National Forest shall present the weed free certificate upon request.

Access and Equipment Drops in Wilderness:

Use of motor vehicles (including trail motorcycles, ATV’s) and motorized/mechanized equipment (such as chainsaws, generators, or bicycles) are prohibited in designated Wilderness Areas.

Use of helicopters for equipment/supply drops or for ferrying personnel into a Wilderness area will not be allowed.

In general, storing equipment, personal property or supplies at one cache site for more than 14 consecutive days within a 45-day period is prohibited in both Wilderness and Non-Wilderness areas, subject to specific Wilderness stay limits.

SECTION D--PACKAGING AND MARKING

D-1 PACKING AND MARKING

All shipments of materials, equipment and/or supplies shall be addressed to the Contractor and not to the Government.

D-2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE

The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.

SECTION E--INSPECTION AND ACCEPTANCE

E-1 CLAUSES

SECTION F--DELIVERIES OR PERFORMANCE

F-1 CLAUSES

52.211-13 Time Extensions (SEP 2000) 52.242-14 Suspension of Work (APR 1984)

52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 60 days after receipt of the notice to proceed. The time stated for completion shall include final cleanup of the premises.

SECTION G--CONTRACT ADMINISTRATION DATA

G-1 CLAUSES

G-2 OTHER REQUIREMENTS

Post Award Conference (NOV 1996) A post award conference with the successful offeror is required. It will be scheduled and held after contract award. The conference date, time, and location will be determined after award.

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H-1 CLAUSES

H-2 OTHER REQUIREMENTS

KEY PERSONNEL

(a) The Contractor shall assign to this contract the following key personnel: Project Foreman.

(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.

USE OF PREMISES

(a) Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened, or operated on USDA land or lands administered by the USDA, the Contractor shall obtain written permission from the Contracting Officer. A camp is interpreted to include a campsite or trailer parking area of any employee working on the project for the Contractor.

(b) Unless excepted elsewhere in the contract, the Contractor shall (i) provide and maintain sanitation facilities for the work force at the site and (ii) dispose of solid waste in accordance with applicable Federal, State, and local regulations.

ARCHAEOLOGICAL OR HISTORIC SITES

If a previously unidentified archaeological or historic site(s) is encountered, the Contractor shall discontinue work in the general area of the site(s) and notify the Contracting Officer immediately.

CONTROL OF EROSION, SEDIMENTATION, AND POLLUTION

(a) Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).

(b) Pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials shall not be discharged on the ground; into or nearby rivers, streams, or impoundments; or into natural or man-made channels. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

(c) Mechanized equipment shall not be operated in flowing streams without written approval by the Contracting Officer.

INSURANCE COVERAGE

Pursuant to FAR clause 52.228-5, Insurance-Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:

(a) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.

(b) General Liability. (1) The Contractor shall have bodily injury liability coverage written on a comprehensive form of policy of at least $500,000 per occurrence. (2) The Contractor shall have property damage liability insurance shall be required in the amount of $500,000 per occurrence.

(c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.

(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor shall have aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury.

Coverage for passenger injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I-1 CLAUSES

52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

Federal Acquisition Regulation (FAR) Clauses:

https://www.acquisition.gov/browse/index/far (FAR clauses begin with 52) Department of Agriculture Acquisition Regulation (AGAR) Clauses:

https://www.acquisition.gov/agar (AGAR clauses begin with 452) Deviations to clauses may be viewed at:

https://www.dm.usda.gov/procurement/policy/FARClassDeviations.htm

52.203-16 Preventing Personal Conflicts of Interest (JUN 2020)

52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of Whistleblower Rights (JUN 2020)

52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY 2011)

52.204-13 System for Award Management Maintenance (OCT 2018)

52.212-4 Contract Terms and Conditions – Commercial Products and Commercial Services

(NOV 2021)

Addenda to 52.212-4:

(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 18 U.S.C 431 relating to officials not to benefit; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C. chapter 87, Kickbacks; 41 U.S.C 4712 and 10 U.S.C 2409 10 U.S.C. 2409 relating to whistleblower protections; 49 U.S.C. 40118, Fly American; and 41 U.S.C chapter 21 relating to procurement integrity.

52.212-5 Contract Terms and Conditions Required to Implement Statutes or Executive Orders– Commercial Products and Commercial Services (MAY 2022) (DEVIATION JUL 2020) https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/agar https://www.dm.usda.gov/procurement/policy/FARClassDeviations.htm

(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:

(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).

(2) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (Nov 2021) (Section 1634 of Pub. L.

115-91).

(3) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (Nov 2021) (Section 889(a)(1)(A) of Pub. L. 115-232).

(4) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015)

(5) 52.233-3, Protest After Award (Aug 1996) (31 U.S.C. 3553).

(6) 52.233-4, Applicable Law for Breach of Contract Claim (Oct 2004) (Public Laws 108-77 and 108-78 (19 U.S.C. 3805note)).

(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:

[Contracting Officer check as appropriate.] ☐ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (June 2020), with

Alternate I (Oct 1995) (41 U.S.C. 4704 and 10 U.S.C. 2402).

☐ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (Nov 2021) (41 U.S.C.

3509)).

☐ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment

Act of 2009 (Jun 2010) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)

☐ (4) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (Jun 2020) (Pub. L. 109-282) (31 U.S.C. 6101 note).

☐ (5) [Reserved].

☐ (6) 52.204-14, Service Contract Reporting Requirements (Oct 2016) (Pub. L. 111-117, section

743 of Div. C).

☐ (7) 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts

(Oct 2016) (Pub. L. 111-117, section 743 of Div. C).

☒ (8) 52.209-6, Protecting the Government’s Interest When Subcontracting with Contractors

Debarred, Suspended, or Proposed for Debarment. (Nov 2021) (31 U.S.C. 6101note).

☐ (9) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters

(Oct 2018) (41 U.S.C. 2313).

☐ (10) [Reserved].

☐ (11) (i) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (Sep 2021) (15

U.S.C.657a).

☐ (12) (i) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business

Concerns (Sep 2021) 15 U.S.C. 657a).

☐ (13) [Reserved] ☒ (14) (i) 52.219-6, Notice of Total Small Business Set-Aside (Nov 2020) (15 U.S.C.644).

☐ (ii) Alternate I (Mar 2020) of 52.219-6.

☐ (15) (i) 52.219-7, Notice of Partial Small Business Set-Aside (Nov 2020) (15 U.S.C. 644).

☐ (ii) Alternate I (Mar 2020) of 52.219-7.

☒ (16) 52.219-8, Utilization of Small Business Concerns (Oct 2018) (15 U.S.C. 637(d)(2) and

(3)).

☐ (17) (i) 52.219-9, Small Business Subcontracting Plan (Nov 2021) (15 U.S.C. 637(d)(4)).

☐ (ii) Alternate I (Nov 2016) of 52.219-9.

☐ (iii) Alternate II (Nov 2016) of 52.219-9.

☐ (iv) Alternate III (Jun 2020) of 52.219-9.

☐ (v) Alternate IV (Sep 2021) of 52.219-9.

☐ (18) (i) 52.219-13, Notice of Set-Aside of Orders (Mar 2020) (15 U.S.C. 644(r)).

☐ (ii) Alternate I (MAR 2020) of 52.219-13

☐ (19) 52.219-14, Limitations on Subcontracting (Sep 2021) (15 U.S.C.637s) [Contracting Officer check as appropriate.]

☐ By the end of the base term of the contract and then by the end of each subsequent option period; or ☐ By the end of the performance period for each order issued under the contract.

☐ (20) 52.219-16, Liquidated Damages-Subcontracting Plan (Sep 2021) (15 U.S.C.

637(d)(4)(F)(i)).

☐ (21) 52.219-27, Notice of Service-Disabled Veteran-Owned Small Business Set-Aside (Sep 2021) (15 U.S.C. 657f).

☐ (22) (i) 52.219-28, Post Award Small Business Program Rerepresentation (Sep 2021) (15 U.S.C. 632(a)(2)).

☐ (ii) Alternate I (MAR 2020) of 52.219-28.

☐ (23) 52.219-29, Notice of Set-Aside for, or Sole Source Award to, Economically Disadvantaged Women-Owned Small Business Concerns (Sep 2021) (15 U.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .