This document is a five-year Capital Improvement Plan (CIP) for the Bacon County Airport (AMG) in Alma, Georgia. The CIP outlines various projects planned for fiscal years 2025 through 2029, including the construction of runway and taxiway lighting replacement, beacon rehabilitation, and apron lighting; design and construction of an aboveground fuel facility; design and construction of a T-hangar taxiway and building; crack sealing and pavement rejuvenation of the taxiway; and design and construction of a corporate hangar. The total estimated cost for the five-year CIP is $8,225,291, with funding sources including the Federal Aviation Administration's Airport Improvement Program, the Georgia Department of Transportation's Aviation Programs, and local funds.

Additionally, the document references a related state and local contract opportunity for airport consulting engineering services. The Bacon County Board of Commissioners is seeking a qualified aviation consulting firm to provide professional on-call engineering, architectural, and construction inspection/administration services for projects at the Bacon County Airport. Responding firms must possess current pre-qualification by the Georgia Department of Transportation in specific aviation design and airport construction administration and observation areas. Statements of Qualifications must be submitted by 2:00 PM on Friday, August 30th, 2024.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BACON COUNTY AIRPORT (AMG)

ALMA, GEORGIA

FY 2025-2029 CIP

10/30/2023

9:11 PM

NPE AIP BIL

2025 1. CONSTRUCT RUNWAY AND TAXIWAY LIGHTING REPLACEMENT, BEACON REHABILITATION, AND APRON LIGHTING, INCLUDING CA/CI SERVICES 950,000$ 438,838$ 80,162$ 336,000$ 47,500$ 47,500$

2. DESIGN ABOVEGROUND AVGAS AND JETA FUEL FACILITY WITH CANOPY AND DECOMMISSION THE EXISTING

UNDERGROUND TANKS 60,000$ -$ 54,000$ -$ 3,000$ 3,000$

3. REIMBURSEMENT FOR 3-YEAR DBE PLAN UPDATE (FY2024-2026) (LOCAL SHARES PAID 2024) 9,791$ 8,812$ -$ -$ -$ 979$

TOTAL, FY 2025 1,019,791$ 447,650$ 134,162$ 336,000$ 50,500$ 51,479$

2026 1. CONSTRUCT ABOVEGROUND AVGAS AND JETA FUEL FACILITY WITH CANOPY AND DECOMMISSION THE EXISTING UNDERGROUND TANKS, INCLUDING CA/CI SERVICES 600,000$ 150,000$ 280,000$ 110,000$ 30,000$ 30,000$

2. DESIGN T-HANGAR TAXIWAY & CONCRETE SLAB FOR 8-UNIT T-HANGAR BUILDING 70,000$ -$ -$ -$ 52,500$ 17,500$

3. CONSTRUCT CORPORATE/MAINTENANCE HANGAR WITH AIRPORT OFFICE; INCLUDES DEMOLITION, SITE WORK, AND

CA/CI SERVICES 2,807,000$ -$ -$ -$ 1,000,000$ 1,807,000$

TOTAL, FY 2026 3,477,000$ 150,000$ 280,000$ 110,000$ 1,082,500$ 1,854,500$

2027 1. DESIGN AND CONSTRUCT CRACK SEAL AND PAVEMENT REJUVENATION OF TAXIWAY AND REMARK AIRFIELD, INCLUDING CA/CI SERVICES 265,000$ 150,000$ -$ 88,500$ 13,250$ 13,250$

2. CONSTRUCT T-HANGAR TAXIWAY & CONCRETE SLAB FOR 8-UNIT T-HANGAR BUILDING, INLCUDING CA/CI SERVICES 800,000$ -$ -$ 600,000$ 200,000$

3. DESIGN-BUILD 8-UNIT T-HANGAR BUILDING, INCLUDING CA/CI SERVICES 550,000$ -$ 473,500$ 21,500$ 27,500$ 27,500$

4. UPDATE 3-YEAR DBE PLAN (FY 2027-2029) 13,500$ -$ -$ -$ -$ 13,500$

TOTAL, FY 2027 1,628,500$ 150,000$ 473,500$ 110,000$ 640,750$ 254,250$

2028 1. AIRPORT LAYOUT PLAN UPDATE 160,000$ 144,000$ -$ -$ 8,000$ 8,000$

2. DESIGN TAXIWAY AND SITE WORK FOR CORPORATE HANGAR 80,000$ -$ -$ -$ 60,000$ 20,000$

3. REIMBURSEMENT FOR 3-YEAR DBE PLAN UPDATE (FY2027-2029) (LOCAL SHARES PAID 2027) 13,500$ 6,000$ 6,150$ -$ -$ 1,350$

TOTAL, FY2028 253,500$ 150,000$ 6,150$ -$ 68,000$ 29,350$

2029 1. CONSTRUCT TAXIWAY AND SITE WORK FOR CORPORATE HANGAR, INCLUDING CA/CI SERVICES 1,000,000$ -$ -$ -$ 750,000$ 250,000$

2. DESIGN-BUILD CORPORATE HANGAR (100'x100') WITH 80'x22' BI-FOLD HANGAR DOOR, INCLUDING CA/CI SERVICES 1,100,000$ 150,000$ 840,000$ -$ 55,000$ 55,000$

TOTAL, FY2029 2,100,000$ 150,000$ 840,000$ -$ 805,000$ 305,000$

TOTAL, FY 20245-2029 8,225,291$ 897,650$ 1,727,662$ 556,000$ 2,578,750$ 2,465,229$

Approved by: To be received by November 10, 2023 at:

Shane Taylor, Chairman Georgia Department of Transportation-Aviation Programs 600 W. Peachtree St NW, 2nd floor

Atlanta, Georgia 30308

LOCAL COSTFY PROGRAM DESCRIPTION TOTAL COST STATE COSTFEDERAL COST

Sheet1