Amendment of Solicitation/Modification of Contract
This Standard Form 30 is Amendment 001 to RFQ 19AS2026Q0017 issued by the US Embassy Canberra General Services Office on April 21, 2026, expanding the scope of work for the installation of a reinforced concrete slab. The amendment increases the construction area from 150 square meters to 195 square meters with a minimum slab thickness of 150 millimeters. The contractor must supply all labor, materials, equipment, and supervision necessary to complete the expanded project, which includes site preparation and excavation, subgrade preparation, formwork, reinforcement, concrete supply and placement, surface finishing, integration with existing works, site restoration, and final completion and acceptance. The amendment is effective April 21, 2026, with the original solicitation dated April 9, 2026, under requisition PR15906891. The amendment is not extended with respect to the offer receipt deadline. Updated drawings (AL-01) are provided showing the concrete slab and retaining wall configuration at the Embassy Canberra location on Perth Avenue in Yarralumla, ACT 2600. The purpose of this amendment is to address site functionality and operational requirements, improve durability and usability of external areas, and ensure proper integration with recently upgraded retaining wall systems. Paul Rau is identified as the contracting officer for this modification.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
Paul Rau
This amendment expands the scope of work to increase the reinforced concrete slab area from 150 square meters to 195 square meters based on updated site requirements.
The Contractor shall supply all labor, materials, equipment, and supervision necessary to construct a new reinforced concrete slab with a total area of 195 square meters and a minimum thickness of 150 mm.
US Embassy Canberra General Services Office 21 Moonah Place Yarralumla, ACT 2600
PR15906891
19AS2026Q0017
1 3
04/21/2026
04/09/2026
4/21/2026
RFQ NUMBER: 19AS2026Q0017 Installation of Concrete Slab
AMENDMENT OF SOLICITATION
SECTION B – STATEMENT OF WORK
Project: Area Preparation and Installation of New Concrete Slab Due to updated site requirements and following further assessment of existing conditions, the scope of works is hereby expanded to increase the construction of reinforced concrete slab area from 150 square meters to 195 square meters.
The Contractor shall supply all labor, materials, equipment, and supervision necessary to construct a new reinforced concrete slab with an approximate total area of 195 square meters, with a minimum slab thickness of 150 mm.
Scope of Additional Works
1. Site Preparation and Excavation
2. Subgrade Preparation
3. Formwork
4. Reinforcement
5. Concrete Supply and Placement
6. Surface Finishing
7. Integration with Existing Works
8. Site Restoration
9. Final Completion and Acceptance
Purpose of Amendment
This additional scope is required to:
Address site functionality and operational requirements • Improve durability and usability of external areas • Ensure proper integration with recently upgraded retaining wall systems
UPDATED DRAWINGS
File details come from the government source that posted it. Updated .