Amendment No_ 2.pdf

PDF 74 KB Posted

Attached to
Paulding County Weather Station Installation, Bid No. 25002-1502
Solicitation number
PE-77892-NONST-2025-000000021
Issued by
Paulding County, Georgia

About this file

This document is an Amendment to an advertised contract for the Weather Station Installation Project, Project Number 25002-1502, located in Paulding County. The amendment changes the bid opening time from 10:00 a.m. to 2:00 p.m. on July 26, 2024, while the bid date remains the same. The amendment also includes responses to contractor questions, clarifying that the requirements are for ESS Type 2 stations, which include solar power, and that the warranty requirements are as per GDOT's specification 694.3.05.

The document does not provide details on pricing terms, set asides, incumbents, funding requirements and sources, or any other salient commercial information beyond the scope and technical specifications of the project.

View the file

Other files

File Type Posted
Amendment No_ 1.pdf PDF
7 _ Advertisement.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

July 23, 2024

AMENDMENT TO ADVERTISED CONTRACT

PROJECT NAME: Weather Station Installation Project

PROJECT NUMBER: 25002-1502

COUNTY: PAULDING

AMENDMENT NUMBER: 2

LETTING DATE: July 26,2024 at 10:00 a.m. changed to 2:00 p.m.

THE FOLLOWING AMENDMENTS ARE HEREBY MADE TO THIS CONTRACT.

THE BIDDER IS RESPONSIBLE FOR MAKING ANY NECESSARY CHANGES IN

INK IN THE PROPOSAL. BIDDER SHALL ACKNOWLEDGE THIS AMENDMENT

BY CHECKING THE APPROPRIATE SPACE ON THE AMENDMENT

CERTIFICATION PAGE.

Included in this Amendment:

• Bid opening time changed from 10:00 a.m. to 2:00 p.m. The date remains the same.

• Responses to contractor questions as follows: Questions in black, responses in red.

Are these stations required to run on solar? The existing poles appear to have power supplied. If AC power is available, is an ESS Type 1 station preferred to Type 2?- As per bid documents, the requirements are for ESS type 2, which include solar power.

Is the warranty requirement 5 years?- Please refer to GDOT’s specification 694.3.05 for warranty requirements.