Amendment 5 - ITB789 - Adminstration Document.docx
DOCX document 97 KB Posted
- Attached to
- One and Two Way Snowplows
- Solicitation number
- 789
- Issued by
- Idaho
About this file
Summary of Amendment 5 - ITB 789: One and Two Way Snowplows
This document is Amendment 5 to Invitation to Bid (ITB) 789 issued by the State of Idaho Division of Purchasing on behalf of the Idaho Transportation Department (ITD) for the procurement of one and two way snowplows. The solicitation requests bids from qualified vendors for the purchase and delivery of snowplow equipment meeting specified technical requirements. While specific quantity estimates are referenced as annual figures for evaluation purposes, no minimum or maximum order quantities are guaranteed, with ITD retaining the right to place additional orders exceeding estimated amounts. The ITB closing date and question deadline are posted in IPRO Powered by Luma, with a public bid opening scheduled for the business day following the submission deadline at 10:30 a.m. Mountain Time via Microsoft Teams. ITD desires delivery within 120 calendar days after receipt of each order. The initial contract term is two years, with the potential for two additional two-year renewal periods for an anticipated total contract term of six years. Prior to manufacturing remaining equipment, a pilot inspection of the first completed plows must be conducted and approved by ITD. A pre-build conference must occur within 15 calendar days after contract award to review requirements and specifications.
Award will be made on an "all to one" basis to the responsive, responsible bidder with the lowest total cost as indicated on the bid schedule. Bidders must be authorized distributors or manufacturers of the snowplows offered, with written agreements from manufacturers required. Contract pricing must remain firm for six months from the effective date, after which the contractor may request price adjustments up to two times annually, subject to ITD approval and verification with supporting manufacturer documentation. Price decreases must be passed to ITD immediately upon availability. Tariff costs resulting from federal import duties may be added to invoices up to 50 percent of actual incurred costs, subject to prior written approval by ITD. The contractor must maintain comprehensive records for three years following contract termination and grant state and federal auditors access to all contract-related records. Insurance requirements are specified in Appendix B in IPRO. All bids must be submitted electronically through IPRO in Microsoft Word and Excel formats only, with the state's signature page, cost information on the prescribed bid schedule, product information sheets, and warranty documentation required as submission components. No set-asides are identified in this solicitation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exhibit 1 - Drawings.pdf | ||
| Attachment 3 - Bid Schedule.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF IDAHO
DIVISION OF PURCHASING
FOR
IDAHO TRANSPORTATION DEPARTMENT
Amendment 5 - Invitation to Bid (ITB) # 789 One and Two Way Snowplows
TABLE OF CONTENTS
| 1 | PURPOSE | 2 |
| 2 | GENERAL INFORMATION, solicitation instructions and standard terms and conditions | 2 |
| 3 | INQUIRIES | 2 |
| 4 | SPECIFICATIONS | 2 |
| 5 | Pre-build conference | 2 |
| 6 | Pilot Inspection | 3 |
| 7 | quantity | 3 |
| 8 | COST | 3 |
| 9 | BILLING | 3 |
| 10 | SUBMISSION REQUIREMENTS | 4 |
| 11 | AWARD | 5 |
| 12 | Acceptance | 5 |
| 13 | Warranty | 5 |
| 14 | ORDERs | 5 |
| 15 | changes/amendments | 5 |
| 16 | dELIVERY | 6 |
| 17 | ASSEMBLY | 6 |
| 18 | AUTHORIZED DISTRIBUTOR | 6 |
| 19 | Records Maintenance | 6 |
| 20 | Audit Rights | 6 |
| 21 | price adjustment clause | 7 |
| 22 | Tariff Costs | 7 |
| 23 | contract closeout | 7 |
| 24 | RESPONSIBILITIES PURSUANT TO IDAPA 38.05.01.081 | 8 |
| 25 | INSURANCE REQUIREMENTS | 8 |
| 26 | DISPUTE RESOLUTION | 8 |
| 27 | NON-COMPLIANCE AND REMEDIES | 8 |
| ATTACHMENT 1 – BIDDER QUESTIONS | 10 | |
| ATTACHMENT 2 – Specifications | 12 | |
| ATTACHMENT 3 – BID SCHEDULE | 14 | |
| Attachment 4 – Product Information | 15 | |
| EXHIBIT 1 – Drawings | 16 | |
| EXHIBIT 2 – CHANGE REQUEST FORM | 17 |
ITB 789 One and Two Way Snowplows Page 1
ITB Administrative Information
| ITB Title: |
| One and Two Way Snowplows |
| ITB Project Description: |
| The State of Idaho Transportation Department (“ITD”), through the Idaho Division of Purchasing (“DOP”), is requesting Bids from qualified Vendors for the purchase and delivery of One and Two Way Snowplows |
ITB Lead:
Alex Limber, Buyer Division of Purchasing 650 W State St, RM 100, Boise ID, 83720 Alex.Limber@adm.idaho.gov 208-332-1605
| Submit sealed Bid electronically via IPRO: |
| Electronic Submission |
IPRO LOGIN
| Deadline To Receive Questions: |
| See Dates in IPRO |
| ITB Closing Date: |
| See Dates in IPRO |
ITB Public Bid Opening Date:
Link:
Dial-in:
ID:
Password:
A public bid opening will be held Tthe following business day after closing at 10:30 am MT. The bid opening will be conducted virtually, with the access link provided below.
Microsoft Teams Meeting +1 208-985-2810 973 427 521# N/A
| Delivery Date: |
| ITD desires delivery within 120 days ARO (after receipt of order). |
| Term |
| The initial term of the contract will be two (2) years. Upon mutual, written agreement, the Contract may be extended for two (2) additional periods of two (2) year increments, with an anticipated total Contract term of six (6) years. |
PURPOSE
The State of Idaho Transportation Department (“ITD”), through the Idaho Division of Purchasing (“DOP”), is requesting Bids from qualified Vendors for the purchase and delivery of one and two way snowplows (Plows) in accordance with the specifications provided below.
GENERAL INFORMATION, solicitation instructions and standard terms and conditions This Solicitation is issued by the state of Idaho (the “State”) via IPRO Powered by Luma (IPRO). The ITB Lead is the only contact for this Solicitation. All correspondence regarding this ITB shall be in writing. In the event that it becomes necessary to revise any part of this ITB, amendments will be posted at IPRO. It is the responsibility of the Bidder to monitor IPRO for any updates or amendments. Any oral interpretations or clarifications of this ITB shall not be relied upon. All changes to this ITB must be in writing and posted at IPRO to be valid. Alternate Bids are not allowed.
INQUIRIES
Questions or other correspondence must be submitted in writing to the ITB Lead listed below. QUESTIONS MUST BE RECEIVED BY 11:59:59 P.M. Mountain Time ON THE DATE LISTED IN IPRO POWERED BY LUMA. Written questions must be submitted using Attachment 1, Bidder Questions. Official answers to all written questions will be posted on IPRO as an amendment to this ITB.
ITB Lead: Alex Limber, Buyer Phone: 208-332-1605 E-mail: Alex.Limber@adm.idaho.gov
Any questions regarding the State of Idaho Standard Contract Terms and Conditions found within the questions tab of IPRO must also be submitted in writing, using Attachment 1, Bidder Questions, by the deadline identified in IPRO Powered by LUMA. The State will not consider proposed modifications to these requirements after the date and time set for receiving questions. Questions regarding these requirements must contain the following:
1. The rationale for the specific requirement being unacceptable to the party submitting the question (define the deficiency).
2. Recommended verbiage for the State’s consideration that is consistent in content, context, and form with the State’s requirement that is being questioned.
3. Explanation of how the State’s acceptance of the recommended verbiage is fair and equitable to both the State and to the party submitting the question.
Bids which condition the Bid based upon the State accepting other terms and conditions not found in the ITB, or which take exception to the State’s terms and conditions, will be found non-responsive, and no further consideration of the Bid will be given.
SPECIFICATIONS
See Attachment 2 Specifications.
Pre-build conference The Contractor must coordinate and conduct a pre-build conference with ITD’s Maintenance Services Manager, or designee, virtually via a TEAMS link. This conference must be conducted within fifteen (15) calendar days after award of the Contract. The purpose of this conference will be to review the requirements of the Contract and the detailed specifications.
Pilot Inspection Upon completion of the first Plows on the first year order, ITD shall conduct a virtual inspection of the equipment to ensure the minimum specifications are met. Manufacturing of the remaining first year order must not begin until the inspection has been conducted and approved by ITD.
quantity While the quantities for the Plows provided in this solicitation are annual estimates, and will be used for evaluation and award purposes, no minimum or maximum order quantities are guaranteed. If ITD needs to exceed the estimated quantities in this ITB, ITD may place additional order(s), exceeding the annual estimated amount.
COST
Provide your fully burdened Total Cost on the Bid Schedule (Attachment 3).
BILLING
Invoices must be submitted as further detailed below. Invoices submitted prior to Acceptance, or without the required information listed below will be returned to the Contractor for correction and resubmission. Resubmitted invoices must be sent with a new invoice date, which will restart the timeline required for payment.
Invoices must be submitted as follows:
One (1) invoice per unit after acceptance by ITD.
Invoices must include the following information:
| 1 | Contractor Company & Contact Information; |
| 2 | Contract Name & Number; |
| 3 | Order Number; |
| 4 | Invoice Number & Date; |
| 5 | Itemization of the Property provided and accepted to include: description matching the contract, quantity, unit of measure, unit price, extended price, and total invoice amount; |
| 6 | T number of each plow being invoiced (ITD will provide this at the time of order); and |
| 7 | Delivery Location. |
Invoices must be emailed to:
HQAP@itd.idaho.gov HQFLEET@itd.idaho.gov
ITD’s Contract Management Team (CMT) will review each invoice prior to forwarding to ITD’s accounts payable to process the payment.
SUBMISSION REQUIREMENTS
Required Bid Submission Items Your Bid Submission must consist of the following:
Bid Schedule Provide your cost information on Attachment 3, Bid Schedule, attached. Do not submit your Bid on any other form. Submitting your Bid on a form different than the Bid Schedule may cause your Bid to be rejected as non-responsive.
Attachment 4 – Product Information Sheet.
State of Idaho Signature Page The State of Idaho Signature Page must be completed and submitted as part of your Bid. The State of Idaho Signature Page is attached in IPRO.
Supporting documentation if offering equal as indicated in Attachment 2 – Specifications.
Warranty Documentation and Acceptance Letter as required by Section 14.3.
Electronic Bid Submission Bids must be submitted electronically via IPRO. Do not fax or e-mail your Bid. Your Bid must be received at the Division of Purchasing by the date and time specified on the IPRO header document. The official time, for bid closing purposes, is the Division of Purchasing’s time clock.
Upload all of the Required Bid Submission Items (See Section 10.1) and enter your cost in IPRO for each line item; as the “Total Cost” on the Bid Schedule OR $0.01 as your cost in IPRO.
Upload all Required Bid Submission Items using Microsoft products such as Word and Excel. Do not submit items in .pdf format, unless provided otherwise in this ITB.
Be advised that that the Bidder for Bid evaluation and award purposes is the entity profile under which you submit in IPRO, which must be the same legal entity presented in your uploaded response materials. If the entity identified on the state supplied Signature Page differs from the entity under which you submit your Bid in IPRO, the information provided on the Signature Page prevails.
All Bidders participating in this Solicitation must establish an account in the IPRO system as it is necessary in order to process and/or award the resulting Contract(s). It is free to establish an account and only takes a few minutes.
Bidders are further advised to upload response materials with descriptive file names, organized and consolidated in a manner which allows the State to efficiently navigate the Bidder’s response; as the State will print uploaded documents for evaluation in the manner received via IPRO.
Trade Secrets If your Bid contains trade secret information which you have identified, you must also submit a redacted copy of the Bid (in electronic format, with the word “redacted” in the file name) with all trade secret information removed or blacked out; as well as a separate document containing a complete list (per the instructions in the three (3) paragraphs directly below) of all trade secret information which was removed or blacked out in the redacted copy.
Paragraph 28 of the Solicitation Instructions to Vendors describes trade secrets to “include a formula, pattern, compilation, program, computer program, device, method, technique or process that derives economic value, actual or potential, from not being generally known to, and not being readily ascertainable by proper means by other persons and is subject to the efforts that are reasonable under the circumstances to maintain its secrecy.” In addition to marking each page of the document with a trade secret notation (as applicable; and as provided in Paragraph 28 of the Solicitation Instructions to Vendors), Bidders must also:
Identify with particularity the precise text, illustration, or other information contained within each page marked “trade secret” (it is not sufficient to simply mark the entire page). The specific information you deem “trade secret” within each noted page must be highlighted, italicized, identified by asterisks, contained within a text border, or otherwise clearly delineated from other text/information and specifically identified as a “trade secret.”
Provide a separate document entitled “List of Redacted Trade Secret Information” which provides a succinct list of all trade secret information noted in your Bid; listed in the order it appears in your submittal documents, identified by Page #, Section #/Paragraph #, Title of Section/Paragraph, specific portions of text/illustrations; or in a manner otherwise sufficient to allow the State’s procurement personnel to determine the precise text/material subject to the notation. Additionally, this list must identify with each notation the specific basis for your position that the material be treated as exempt from disclosure.
AWARD
Award will be made “all to one” to the responsive responsible Bidder with the lowest Total Cost, as provided on Attachment 3 - Bid Schedule attached in IPRO. ITD reserves the right to award in the best interest of the State.
Acceptance Upon receipt, the Plows shall be inspected by the ITD Maintenance Services Manager or designee to ensure the minimum specifications are met. Acceptance shall occur fourteen (14) calendar days after delivery, unless ITD has notified the Contractor in writing that the product delivered does not meet the minimum specifications. If ITD determines that the Plows are not in accordance with the specifications, ITD shall provide the Contractor with a written notification. The Contractor must pick-up, correct any discrepancies, and re-deliver to the ITD specified location at the Contractor’s expense. The timeframe for completion of corrective action must not exceed thirty (30) calendar days from receipt of written notification from ITD.
Warranty Warranty for each Snowplow must be for a minimum period of one (1) year after ITD’s Acceptance. The paint for each Snowplow must be warranted against fading and peeling for three (3) years, with the exception of normal wear and tear under normal working conditions. If the Plow continuously malfunctions and causes it to be out of service on multiple occasions, the Agency reserves the right to require the Contractor to pick-up, repair, and return the Plows at no additional cost to the Agency. In the event of a major repair(s) the timeframe must be mutually agreed upon by the Contractor and ITD.
If any warranty work is to be performed, the Contractor may elect to have a dealer of its choice perform the work in accordance with the manufacturer’s standards.
Bidders must submit warranty documentation and an acceptance letter agreeing to warranty provisions of the Plows (See IPRO powered by Luma).
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
ORDERs Orders will be placed on an as needed basis by ITD via an ITD purchase order (Order). The Contractor must confirm receipt of each Order and provide an estimated delivery date within forty-eight (48) hours after receiving the Order from ITD. Each Order will indicate the quantity and Delivery Location for the Plow(s).
changes/amendments Either party may, at any time by a written request, request changes to the Contract. The party requesting the change must complete the Change Request Form (see Exhibit 2, below), providing all details for the change. The party receiving the Change Request Form must confirm receipt and provide feedback regarding any desired changes to the request.
If the Change Request consists solely of plan, timeline, schedule, or key personnel changes; or which otherwise acts to clarify the roles and responsibilities or modify the activities within the scope of the Contract, without an impact on cost, the ITD CMT is authorized to negotiate and execute the Change Request Form with the Contractor.
If the Change Request directly or indirectly increases the monetary obligations of the State, expands the scope of the Contract, changes contract requirements or terms and conditions or extends the Contract term, a formal Amendment will be issued by the State. The ITD CMT will submit the drafted Change Request Form to the State’s Contract Administration Team (CAT) for review. Any Amendment must be in writing and mutually agreed upon by both parties. No amendment will be effective until executed by the Department of Administration. An Amendment not executed in compliance with the section may be void pursuant to Idaho Code, Section 67-9213, and may cause the entire Contract to be void.
dELIVERY ITD desires delivery of the Plows within one hundred twenty (120) calendar days after receipt of each Order. Deliveries must be made Monday through Thursday, 8:00 am to 3:00 pm local time (per Delivery Location), excluding state of Idaho recognized holidays, unless otherwise approved by ITD. ITD will be responsible for offloading the Plows at the Delivery Locations.
Delivery Locations (the “Ship To” will be indicated on each Order):
ITD District 1 Yard, 600 W. Prairie Ave., Coeur d’Alene, ID 83815
ITD District 2 Yard, 2600 Frontage Rd., Lewiston, ID 83501
ITD District 3 Yard, 8150 Chinden Blvd., Boise, ID 83714
ITD District 4 Yard, 216 South Date St., Shoshone, ID 83352
ITD District 5 Yard, 5151 South 5th Ave, Pocatello, ID 83204
ITD District 6 Yard, 206 N. Yellowstone, Rigby, ID 83442
ASSEMBLY
The Plows must be assembled and adjusted when delivered to the ITD location specified. All equipment, including standard and supplemental equipment, must be installed as per the manufacturer’s specifications, and serviced and ready for continuous operation at the time of delivery, unless otherwise stated in this ITB.
AUTHORIZED DISTRIBUTOR
Submitting vendors must be an authorized distributor or manufacturer of the Plows offered. An authorized distributor shall be defined as a company or organization that has a written agreement with the manufacturer to sell or service its products. Bids from Contractors who are not an authorized distributor by the manufacturer shall not be considered.
Records Maintenance Contractor shall maintain or supervise the maintenance of all records necessary to properly account for all payments made to the Contractor pursuant to the Contract. These records shall be retained by the Contractor for at least three (3) years after the Contract terminates, or until all audits initiated within the three (3) years have been completed, whichever is later.
Audit Rights The Contractor agrees to allow State and Federal auditors and State purchasing staff access to all the records relating to this Contract, for audit, inspection, and monitoring of services or performance. Such access will be during normal business hours or by appointment.
price adjustment clause Prices must be firm for six (6) months from the effective date of the Contract. The Contractor may request a price adjustment up to two (2) times per year thereafter. If a price increase is requested, it will be the responsibility of the Contractor to notify DOP thirty (30) calendar days in advance of the desired effective date and provide supporting documentation showing industry wide increases justifying the request. DOP will notify Contractor whether the request is approved within fourteen (14) calendar days of receipt of the request.
If price decreases become effective for the Contractor, ITD will be given immediate benefit of the price decrease on the date the price decrease becomes available to the Contractor.
At any time during the Contract, ITD may request supporting documentation from the Contractor for price verification of the Plows. The requested documentation must be provided directly from the manufacturer. This requirement will help ensure that the ITD is receiving the most current pricing offered.
Contractor(s) will have fourteen (14) calendar days to provide current price information, for verification by ITD, prior to any price increase. If the Contractor cannot meet this deadline, the current contract prices will govern and remain in effect until pricing can be verified.
Contract pricing will be adjusted via an amendment to the Contract.
Tariff Costs If the President of the United States, the United States Congress, Customs and Border Protection, or any other federal entity authorized by law, imposes an import duty or tariff (a “tariff”) on an imported good that results in an increase in Contractor’s costs to a level that renders performance under this Agreement impracticable, Contractor may be permitted to add up to fifty percent (50%) of the actual cost it incurs due to tariffs to its invoices submitted to the State, subject to the following conditions:
Contractor shall notify the Agency of the maximum cost of tariffs and obtain the Agency’s written approval. The Agency shall not be obligated to pay costs associated with tariffs for which the Agency did not provide prior written approval, or which exceeds the approved maximum. Contractor may provide notification of maximum tariffs on a case-by-case basis (for each order) or may provide blanket or time-bound notification (e.g., maximum for any orders placed for the next six (6) months).
Contractor shall take reasonable steps to avoid or minimize incurring tariffs and may be asked to provide a certification confirming its efforts to the State.
Contractor may only invoice for the actual costs incurred due to tariffs, even if that amount is less than the agreed upon maximum.
Contractor shall provide evidence documenting the actual cost and applicability of tariffs, which may include country of origin, order/delivery dates, official tariff rates, declared value, etc.
Any material misrepresentation of fact by Contractor relating in any way to an increase in pricing due to tariffs is a default under this Contract and shall be subject to the remedies set forth herein, in addition to any other claim or remedy available to the State. Furthermore, any material misrepresentation of fact by Contractor relating in any way to the State’s payment of additional sums due to tariffs shall be fraud against the taxpayers of the State and grounds for the Contractor to be deemed non-responsible and/or disqualified from participation in future solicitations administered by the State.
contract closeout ITD’s CMT will initiate its contract closeout procedures upon completion of the total Contract term. The closeout procedure will consist of ITD completing a closeout checklist to ensure all obligations have been fulfilled, all disputes are resolved, and all payments have been complete.
ITD’s CMT will provide an initial closeout letter to the Contractor with at least a thirty (30) calendar day advance notification. This notification will serve as a reminder that the contract is reaching its completion, giving an opportunity for the Contractor to return complete any outstanding Orders.
All Orders sent to the Contractor prior to the end of the Contract term must be delivered, even if services are performed beyond the Contract term. Any Orders placed prior to the expiration will still be subject to the same terms and conditions applicable to the Contract at the time of expiration or termination.
Upon completion of the contract term, and after ITD confirms that all obligations have been met, all Orders have been delivered, disputes are resolved, and all payments are complete, ITD’s CMT will provide a final closeout letter confirming that the contract is complete and has been closed out. Copies of the letters will be provided to the Contractor and the State’s CAT for documentation and record keeping purposes.
RESPONSIBILITIES PURSUANT TO IDAPA 38.05.01.081
The ITB Lead may, in the State’s sole discretion, require the apparent lowest responsive Bidder’s to provide documentation to demonstrate its responsibility. The ITB Lead may request documentation including, but not limited to credit or financial reports, and references. Failure to provide requested documentation may result in the Bidder’s being deemed non-responsible. Nothing herein shall prevent the State from using other means to determine Bidder’s responsibility.
INSURANCE REQUIREMENTS
See Appendix B – Insurance Requirements on the Questions Tab in IPRO.
DISPUTE RESOLUTION
During the performance of the Contract, the parties agree that it is in their mutual interest to resolve disputes informally. Any claims by the Vendor shall be submitted in writing to ITD’s Contract Manager for resolution. Any claims by the State shall be submitted in writing to the Vendor’s Project Manager for resolution. The Parties shall agree to negotiate in good faith and use all reasonable efforts to resolve such dispute(s). During the time the Parties are attempting to resolve any dispute, each shall proceed diligently to perform their respective duties and responsibilities under this Contract. The Parties shall agree on a reasonable amount of time to resolve a dispute. If a dispute cannot be resolved between the Parties within the agreed upon period, either Party may elect to exercise any other remedies available under the Contract, or at law. This provision, when agreed in the Contract, shall not constitute an agreement by either party to mediate or arbitrate any dispute.
NON-COMPLIANCE AND REMEDIES
ITD’s service location contact will be responsible for documenting non-compliance, in writing, via email. This notice will include the details of each discrepancy that requires corrective action. Invoicing must not occur until non-compliance has been corrected.
Correcting Non-Compliance - After receipt of written notice from ITD, the Contractor must respond, in writing, explaining how and when each discrepancy will be corrected. All discrepancies must be corrected and brought back into compliance with the Contract within fourteen (14) calendar days after receipt of the notice from ITD. If the Contractor does not correct the discrepancies within this timeframe, ITD reserves the right to take further remedial action.
In addition to any remedies available to the State under law or equity, the State may it its sole discretion require one (1) or more of the following remedial actions if any of the service does not conform to the Contract requirements: 1) require the Contractor to take corrective action to ensure that performance conforms to the Contract requirements, 2) require the Contractor to subcontract all or part of the Contract at no additional cost to the State, 3) withhold payment or require payment of actual damages caused by the non-compliance, 4) terminate the Contract, in addition to any remedies imposed by the State.
If ITD must perform or hire a separate contractor to perform any of the Contract’s requirements, which is the responsibility of the Contractor under the terms of the Contract, ITD may withhold the actual cost to ITD from the Contractor’s payment(s).
ATTACHMENT 1 – BIDDER QUESTIONS
ITB 789 One and Two Way Snowplows
PLEASE DO NOT IDENTIFY YOUR NAME OR YOUR COMPANY’S NAME OR PRODUCT NAMES OF INTELLECTUAL PROPERTY IN YOUR QUESTIONS.
ADD ROWS BY HITTING THE TAB KEY WHILE WITHIN THE TABLE AND WITHIN THE FINAL ROW.
The following instructions must be followed when submitting questions using the question format on the following page.
1. DO NOT CHANGE THE FORMAT OR FONT. Do not bold your questions or change the color of the font.
2. Enter the ITB section number that the question is for in the “ITB Section” field (column 2). If the question is a general question not related to a specific ITB section, enter “General” in column 2. If the question is in regards to a State Term or Condition or a Special Term or Condition, state the clause number in column 2. If the question is in regard to an attachment, enter the attachment identifier (example “Attachment A”) in the “ITB Section” (column 2), and the attachment page number in the “ITB page” field (column 3).
3. Do not enter text in the “Response” field (column 5). This is for the State’s use only.
4. Once completed, this form is to be e-mailed per the instructions in the ITB. The e-mail subject line is to state the ITB number followed by “Questions.”
ITB 789 One and Two Way Snowplows Page 1
ITB 789 One and Two Way Snowplows
| ITB Section |
| ITB Page |
| Question |
| Response |
ATTACHMENT 2 – Specifications ITB789 One and Two Way Snowplows
These specifications are the minimum mandatory specifications that your Bid must meet in order for the State to consider your Bid for award. Restate each specification listed in this section in which your bid deviates, followed by your response demonstrating that your Bid meets or exceeds the required specifications; provide model, part #, or description, as appropriate.
The specifications and brand names specified in this solicitation are intended to be descriptive, but not restrictive; indicative of the quality and characteristics of items that meet the minimum requirements. Bidders offering an “equal” must include documentation which demonstrates, to the State’s satisfaction, that the offered item(s) meets the requirement of the solicitation. Failure to provide “equal” documentation does not exempt the Bidder from providing the exact specification as provided in Attachment 2 Specifications. Failure to provide satisfactory documentation may eliminate the Bidder from further consideration, if the State cannot determine to its satisfaction that the offered property is “equal”.
1. Model and Assembly
1.1. The Snowplows must be the latest model of the manufacturer's standard production, as offered to commercial trade.
1.2. Though they are not specifically covered herein, all parts necessary to provide complete and functional Snowplows must be provided.
1.3. All parts must conform in design, strength, quality of materials, and workmanship to current engineering practices and accepted standards of the industry.
1.4. All parts must be the manufacturer’s standard unless otherwise specified in this ITB.
1.5. The Snowplows must be assembled and adjusted, per the manufacturer’s standards, and be ready for operation upon delivery.
2. General 1.
2.
2.1. Drawings – Each Snowplow (including push frame and related components) must be constructed in accordance with Exhibit 1 – Drawings for One (1) and Two (2) Way Snowplows.
2.2. Material – All material must be American Society for Testing and Materials (ASTM) A-thirty-six (A-36) steel unless otherwise specified.
2.3. Moldboard – Continuous, smooth-rolled or broken section type, ten (10)-gauge steel with a yield point of fifty thousand (50,000) pounds per square inch (PSI) and tensile strength of sixty-five thousand (65,000) PSI.
2.3.1. Moldboard blanks must be constructed from either a one-piece seamless ninety-six (96)-inch, ten (10)-gauge single sheet or a maximum of two (2) pieces of steel seamed to form a single sheet from which moldboard blanks must be cut.
2.3.2. Each blank must have no more than one (1) seam per moldboard section.
2.3.3. Broken section type moldboard requirements:
2.3.3.1. Broken section type moldboard not to exceed a one (1) inch center-to-center spacing between breaks on smaller end of mold board sheet.
2.3.3.2. The seaming process must be an automatic tungsten inert gas (TIG) welding process, including argon & helium gases, using ER80S wire and must be computerized in order to keep the voltage constant across the entire length of the weld.
2.3.3.3. Metal inert gas (MIG) welding is not acceptable for the broken section type moldboard seaming process.
2.3.3.4. The material must be inserted into a mandrel which has a recessed copper bar designed to accommodate the specific material thickness. The material must be held in position by means of continuous copper fingers pressurized with thirty (30) – forty (40) Pounds per Square Inch (PSI) of air pressure.
2.3.3.5. The automatic weld must be a consistent three-eights (3/8) in. – one half (1/2) in. thick and must have full penetration from a single side application and have no undercutting.
2.3.3.6. The automatic weld must be set at a constant speed to provide a consistent weld from sheet to sheet. Each weld process must be certifiable by an American Welding Society (AWS) metallurgist.
2.4. Blade Punching – Standard American Association of State Highway and Transportation Officials (AASHTO) punching on twelve (12)-inch centers as shown in attached drawings must accept three (3) four (4)-foot blades. Cutting edges are not required as part of this ITB.
2.5. Welding – All welds must be full seam and must conform to American Welding Society (AWS)and American National Standards Institute (ANSI) standards.
2.6. Construction – Each assembly described on Exhibit 1 must be a welded assembly unless otherwise noted.
2.7. Lift Chain or Cable Attachment – Four (4) each of item thirty (30) Exhibit 1 on the one (1)-way Snowplow and four (4) each of item thirty-six (36) Exhibit 1 – Drawings on the two (2)-way Snowplow must be installed on each plow with locations to be determined by the Contractor to lift the plow. The lift cable or chain is not required as part of this ITB.
2.8. Hydraulic Relief Valve – Cross Model RC11BB (or equal), Relief valve setting must be one thousand (1,000) PSI.
2.9. Hoses – Three-eighths (3/8) inch, two thousand (2,000) PSI working pressure of length required from hydraulic cylinder to relief valve with male American National Standard Pipe Thread (NPT) fittings.
2.10. Jack–One (1) weld on jack with sidewind handle, mounted on street side of push frame. Must include footplate. Exact location determined by ITD at Pre-Build Conference.
3. Paint
3.1. Each Snowplow must be cleaned, prime coated or acid metal etched with phosphate and then painted or power coated with construction safety orange and/or textured black to achieve an anti-glare coating, per the paint manufacturer’s process for the application.
3.2. The final product paint must be a minimum dry thickness of four (4) mils total (two (2) mil. prime coat and two (2) mil. topcoat, or four (4) mil. powder coat).
3.3. The front of the plow, outer surface of the end ribs, outer surface of end plates, outer surface to top angle, push frames and other items behind the mold board must be painted orange. The entire back outside of the moldboard must be painted in anti-glare black. The Snowplows must be smooth and free of rust, runs, overspray, peeling, weld splatter, and other defects.
3.4. The Contractor must provide color chip samples to ITD, within thirty (30) calendar days after award of the Contract, for approval before any snowplows are painted.
4. Two-Way Plow Hydraulic Rams, Item Eighty-Five (85) Exhibit 1 – Drawings
4.1. Barrel – Three and one-half (3-1/2) inch inner diameter (ID), made of one-quarter (1/4) inch C-1026 Drawn Over Mandrel (DOM) tubing honed and polished.
4.2. Rod End – Screw-on collar;
4.3. Blind End – One-half (1/2) inch steel;
4.4. Rod – Two (2) in. made of CD-1045 steel, hard chromed to three thousandths (0.003) inch or nitrosteel;
4.5. Stroke – Seventeen (17) inches;
4.6. Rating – Three thousand (3,000) PSI;
4.7. Piston – Single action piston head with wear ring and secured with lock nut.
4.8. Ports – 8 O-Ring Boss (ORB) three quarter (3/4) inch -sixteen (16) thread;
4.9. Rod Guide – For stability when extended; and
4.10. Seal – Polyurethane U-cup or equivalent;
ATTACHMENT 3 – BID SCHEDULE
BID SCHEDULE IS ATTACHED SEPERATELY IN THE ATTACHMENTS SECTION OF IPRO.
Attachment 4 – Product Information
Bidder Name:
Provide your product information in the fields below:
One and Two Way Snowplows
Manufacturer Name:
Manufacturer Location:
Moldboard Type, Smooth Rolled or Broken?
Completion Time for Pilot Models:
Estimated Delivery from Time of Order:
List Deviations to Specifications/Drawings:
Do you meet the specifications provided in Attachment 2 - Specifications?
YES *NO
*If your product offered does not meet or if it exceeds any of the specifications, Bidder must provide an explanation of how the product offered is functionally equivalent to the stated specification as well as descriptive literature that supports the product offered.
If awarded the contract, what is your estimated delivery timeline to the locations listed in Section 17, Delivery, after Receipt of Order (ARO) form ITD? _______ Calendar days ARO
THIS ATTACHMENT MUST BE COMPLETED AND RETURNED WITH YOUR BID RESPONSE
EXHIBIT 1 – Drawings
EXHIBIT 1 IS ATTACHED SEPERATELY IN THE ATTACHMENTS SECTION OF IPRO.
EXHIBIT 2 – CHANGE REQUEST FORM
| Date |
| Change Number |
| Requesting Party |
| Requestor Name |
Description of Change:
Reason for Change:
Cost and Schedule Impact:
| Requestor Signature and Date |
| *Approving Party Signature and Date |
* If the Change Request directly or indirectly increases the monetary obligations of the State, expands the scope of the Contract, or extends the Contract term, a formal Amendment will be issued by the State. The ITD CMT will submit the drafted Change Request Form to the State’s CAT for review. Only the State’s CAT is authorized to execute an Amendment on behalf of the State. An Amendment not executed in compliance with the section may be void pursuant to Idaho Code, Section 67-9213.