This is an Amendment document containing questions and answers for RFP No. 250000001155, issued for HMA Skip Paving on M-24 in Oakland County. The document clarifies work schedule parameters, confirming that contractors can work daily from 5:00 AM to 7:00 PM with a single lane closure, rather than being restricted to weekends only as is typical for heavy traffic trunklines.
The amendment addresses payment terms for earth excavation work, specifying that all excavation for shoulder widening will be included under Schedule B, Line Item #3 (Shoulder widening, rem). The document requires bidders to acknowledge receipt by attaching it to their Solicitation Response in SIGMA and entering their company name.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP 250000001155 M-24 skip paving.docx | DOCX document | |
| Attachment 1 - Prevailing Wage Rate Schedule.pdf | ||
| Schedule B - Pricing.xlsx | XLSX spreadsheet | |
| Attachment 2 - Prevailing Wage Informational Sheets.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT 1 – REVISED QUESTIONS & ANSWERS
Request for Proposal (RFP) No. 250000001155 HMA Skip Paving – M-24 in Oakland County
| Bidder’s Question | Would you please confirm that work may be performed any day of the week from 5:00 am to 7:00 pm as stated in Schedule A, Section 3.2.B, Table 2. Typically a heavy traffic trunkline would be limited to weekend only. |
| State’s Answer | The time frame stated in Table 2 is correct; the Contractor can work daily from 5:00 am to 7:00 pm with a single lane closure. |
| Bidder’s Question | Earth excavation may be required in the widen areas that pave removal doesn’t address. How will this be paid? |
| State’s Answer | All excavation for shoulder widening would be inclusive under the Schedule B, Line Item #3, Shoulder widening, rem. |