AMENDMENT 1 - Revised Questions and Answers.docx

DOCX document 15 KB Posted

Attached to
HMA Skip Paving, M-24 in Oakland County
Solicitation number
RFP-591-250000001155-3
Issued by
Benzie County, Michigan

About this file

This is an Amendment document containing questions and answers for RFP No. 250000001155, issued for HMA Skip Paving on M-24 in Oakland County. The document clarifies work schedule parameters, confirming that contractors can work daily from 5:00 AM to 7:00 PM with a single lane closure, rather than being restricted to weekends only as is typical for heavy traffic trunklines.

The amendment addresses payment terms for earth excavation work, specifying that all excavation for shoulder widening will be included under Schedule B, Line Item #3 (Shoulder widening, rem). The document requires bidders to acknowledge receipt by attaching it to their Solicitation Response in SIGMA and entering their company name.

View the file

Other files

File Type Posted
RFP 250000001155 M-24 skip paving.docx DOCX document
Attachment 1 - Prevailing Wage Rate Schedule.pdf PDF
Schedule B - Pricing.xlsx XLSX spreadsheet
Attachment 2 - Prevailing Wage Informational Sheets.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT 1 – REVISED QUESTIONS & ANSWERS

Request for Proposal (RFP) No. 250000001155 HMA Skip Paving – M-24 in Oakland County

Bidder’s QuestionWould you please confirm that work may be performed any day of the week from 5:00 am to 7:00 pm as stated in Schedule A, Section 3.2.B, Table 2. Typically a heavy traffic trunkline would be limited to weekend only.
State’s AnswerThe time frame stated in Table 2 is correct; the Contractor can work daily from 5:00 am to 7:00 pm with a single lane closure.
Bidder’s QuestionEarth excavation may be required in the widen areas that pave removal doesn’t address. How will this be paid?
State’s AnswerAll excavation for shoulder widening would be inclusive under the Schedule B, Line Item #3, Shoulder widening, rem.

Bidder Acknowledgement The Bidder acknowledges receipt and has read Amendment 1 – Revised Questions & Answers. Attach this document to the Solicitation Response in SIGMA.

Contractor must enter company name here.

File details come from the government source that posted it. Updated .