This is Amendment #1 to a tree removal contract for the South Carolina Department of Transportation (SCDOT) on Interstate 20 in Aiken County. The amendment modifies the original contract terms and conditions related to tree removal operations along the specified corridor. The document outlines adjustments to the scope of work, project requirements, and contractual obligations between SCDOT and the selected contractor. Key modifications include revised specifications for tree removal methodologies, site clearing procedures, and debris management protocols to ensure compliance with updated safety standards and environmental regulations.
The amendment addresses pricing adjustments, payment terms, and any modifications to the original contract value necessitated by scope changes or market conditions. The document specifies funding sources and budget allocations for the amended work, ensuring clarity on financial responsibility and reimbursement procedures. Additional provisions may include updated insurance requirements, bonding specifications, and performance schedules to accommodate the revised project timeline. Any changes to contractor obligations, equipment specifications, or site access requirements are detailed to maintain alignment with SCDOT's operational standards and Interstate maintenance protocols.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Notice of Revised Posting Date.pdf | ||
| Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DESCRIPTION: * Tree Removal on Interstate 20- Aiken County
USING GOVERNMENTAL UNIT: SC Department of Transportation
SUBMIT YOUR OFFER ON-LINE AT THE FOLLOWING URL: http://www.procurement.sc.gov
SUBMIT OFFER BY (Opening Date/Time): 04/08/2019 4/12/2019 14:30 PM (See “Deadline For Submission Of Offer” provision)
QUESTIONS MUST BE RECEIVED BY: 03/26/2019 12:00PM - EXPIRED (Send questions to golstoncl@scdot.org)
(See “Questions From Offerors” provision)
NUMBER OF COPIES TO BE SUBMITTED: SEE PAGE 3 OF SOLICITATION
CONFERENCE TYPE: Not Applicable
DATE & TIME:
(As appropriate, see “Conferences – Pre-Bid/Proposal” & “Site Visit” provisions)
LOCATION: Not Applicable
AWARD &
AMENDMENTS
Award will be posted on 04/19/2019. The award, this solicitation, any amendments, and any related notices will be posted at the following web address: http://www.procurement.sc.gov
You must submit a signed copy of this form with Your Offer. By signing, You agree to be bound by the terms of the
Solicitation. You agree to hold Your Offer open for a minimum of thirty (30) calendar days after the Opening Date. (See
“Signing Your Offer” provision.)
NAME OF OFFEROR
(full legal name of business submitting the offer)
Any award issued will be issued to, and the contract will be formed with, the entity identified as the Offeror. The entity named as the offeror must be a single and distinct legal entity. Do not use the name of a branch office or a division of a larger entity if the branch or division is not a separate legal entity, i.e., a separate corporation, partnership, sole proprietorship, etc.
AUTHORIZED SIGNATURE
(Person must be authorized to submit binding offer to contract on behalf of Offeror.)
DATE SIGNED
TITLE
(business title of person signing above)
STATE VENDOR NO.
(Register to Obtain S.C. Vendor No. at www.procurement.sc.gov )
PRINTED NAME
(printed name of person signing above)
STATE OF INCORPORATION
(If you are a corporation, identify the state of incorporation.)
OFFEROR’S TYPE OF ENTITY: (Check one) (See “Signing Your Offer” provision.)
___ Sole Proprietorship ___ Partnership ___ Other_____________________________
___ Corporate entity (not tax-exempt) ___ Corporation (tax-exempt) ___ Government entity (federal, state, or local)
COVER PAGE – ON-LINE ONLY (MAR. 2015)
P
State of South Carolina
Amendment # 1
Solicitation:
Date Issued:
Procurement Officer:
Phone:
E-Mail Address:
Mailing Address:
5400017466
04/02/2019 Candis Golston
803-737-9868
GolstonCL@scdot.org
SCDOT Procurement Office
955 Park Street
Columbia, SC 29201 http://www.procurement.sc.gov/ mailto:golstoncl@scdot.org http://www.procurement.sc.gov/ http://www.procurement.sc.gov/ mailto:GolstonCL@scdot.org
QUESTIONS FROM OFFERORS - AMENDMENT
THE SOLICITATION IS AMENDED AS PROVIDED HEREIN. INFORMATION OR CHANGES RESULTING
FROM QUESTIONS WILL BE SHOWN IN A QUESTION-AND-ANSWER FORMAT. ALL QUESTIONS
RECEIVED HAVE BEEN REPRINTED BELOW. THE “STATE’S RESPONSE” SHOULD BE READ
WITHOUT REFERENCE TO THE QUESTIONS. THE QUESTIONS ARE INCLUDED SOLELY TO PROVIDE
A CROSS-REFERENCE TO THE POTENTIAL OFFEROR THAT SUBMITTED THE QUESTION.
QUESTIONS DO NOT FORM A PART OF THE CONTRACT; THE “STATE’S RESPONSE” DOES. ANY
RESTATEMENT OF PART OR ALL OF AN EXISTING PROVISION OF THE SOLICITATION IN AN
ANSWER DOES NOT MODIFY THE ORIGINAL PROVISION EXCEPT AS FOLLOWS: UNDERLINED
TEXT IS ADDED TO THE ORIGINAL PROVISON. STRICKEN TEXT IS DELETED.
QUESTIONS & ANSWERS:
Q-1 It talks about performance time being within 10 days of notice but in another section it shows a one year contract time. Since we are bidding on 50 acres do we only have 10 days to get it done or the one year?
A-1 Please see the DELIVERY DATE- PURCHASE ORDER clause below as amended.
Q-2 In section 3.2 it says payment is on a Per Tree basis but the bid schedule is by the acre.
A-2 Please see the amended language below for Section 3.2 in SECTION III. SCOPE OF WORK
Q-3 In regards to "Non Compliance for Inclement Weather" it shows a $500 fine but no explanation of how it would be assessed if the DOT are the ones deciding on what days would adhere to that category.
A-3 Please see Section 4.4 of the Solicitation in SECTION III. SCOPE OF WORK
The following changes to the solicitation have been made as amended.
2.5 Work Progression and Completion
Section 108.03 of the Standard Specifications shall apply. Work shall be performed diligently with sufficient personnel and equipment to ensure the completion of the activity (and associated activities) within 10 business days of being notified of Tree(s) Removal. Suspension of work by the Contractor, for reasons other than inclement weather constitutes noncompliance. Failure to complete the activity within the time allowed constitutes non-compliance and will result in a nonrefundable deduction as outlined Section 3 of these specifications.
Section 108.03 of the Standard Specifications shall apply. Work shall be performed diligently with sufficient personnel and equipment to ensure the completion of the activity (and associated activates). The work shall begin within 10 business days of being notified of Tree Removal. Suspension of work by the Contractor, for reasons other than inclement weather constitutes noncompliance. Failure to complete the activity within the time allowed constitutes noncompliance and will result in a nonrefundable deduction as outlined Section 3 of these specifications.
3.2 Payment
Payment to the Contractor for the work covered in this contract will be per Acreage TREE per size for all work satisfactorily completed as outlined in Scope of Work and determined by the Engineer. Upon completion of the tree removal the contractor will be paid the contract unit price per Acreage tree per size of the work completed and accepted by the Engineer, per the line item items described in Bid Schedule.
DELIVERY DATE -- PURCHASE ORDER
Services shall be performed within ten (10) days after receipt of purchase order.
DELIVERY DATE - SPECIFIED
Delivery shall be made no later than June 30, 2019. Contractor may request approval to deliver items prior to the delivery date.