This is Amendment #1 to an Invitation for Bid (IFB) issued by the South Carolina Department of Transportation (SCDOT) for median tree cutting operations on I-20 in Kershaw County. The project involves clearing operations within the I-20 median, with work requiring adherence to strict traffic control protocols. Questions from offerors were due by February 9, 2022, at 12:00 PM, and sealed bids were due online by February 28, 2022, at 2:30 PM. Award notification was scheduled for March 21, 2022. The solicitation document references standard SCDOT drawings for daytime and nighttime lane closure requirements, as well as interstate shoulder closure specifications. No site visit or pre-bid conference information is specified in this amendment.

The amendment addresses critical operational requirements clarified through bidder questions, including the mandatory provision of crash trucks during clearing operations, lane closure requirements when work occurs within 10 feet of adjacent travel lanes, and shoulder closure sufficiency for work outside that buffer zone. Contractors are solely responsible for providing appropriate traffic control based on SCDOT standards; the department will not provide pace cars or supplementary traffic management. Equipment storage must maintain a minimum 30-foot distance from adjacent travel lanes. Only two traffic control options are permitted: shoulder closures or lane closures, with no alternative configurations allowed. Specific pricing, funding amounts, or set-aside information is not detailed in this amendment document.

View the file

Other files

File Type Posted
Notice Regarding Award 2.pdf PDF
Attachment A.pdf PDF
Attachment C.pdf PDF
Notice Regarding Award.pdf PDF
Attachment B.pdf PDF
Solicitation.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

-9+8*****/SAP

State of South Carolina

Invitation For Bid

*EXEMPT*

AMENDMENT #1

Solicitation:

Date Issued:

Procurement Officer:

Phone:

E-Mail Address:

Mailing Address:

5400022493 02/11/2022

LATRICIA TRAPP

803-737-8380 TrappLA@scdot.org SCDOT Procurement Office 955 Park Street Columbia SC 29201

DESCRIPTION: *I20 Median Tree Cutting - Kershaw*

USING GOVERNMENTAL UNIT: SC Department of Transportation

SUBMIT YOUR OFFER ON-LINE AT THE FOLLOWING URL: http://www.procurement.sc.gov

SUBMIT OFFER BY (Opening Date/Time): 02/28/2022 @ 14:30:00 (See "Deadline For Submission Of Offer" provision)

QUESTIONS MUST BE RECEIVED BY: 02/09/2022 EXPIRED @ 12:00:00 (Send questions to trappla@scdot.org)

(See "Questions From Offerors" provision)

NUMBER OF COPIES TO BE SUBMITTED: SEE PAGE 3 OF SOLICITATION

CONFERENCE TYPE:

DATE & TIME: (As appropriate, see "Conferences - Pre-Bid/Proposal" & "Site Visit" provisions)

LOCATION:

AWARD &

AMENDMENTS

Award will be posted on 03/21/2022. The award, this solicitation, any amendments, and any related notices will be posted at the following web address: http://www.procurement.sc.gov

You must submit a signed copy of this form with Your Offer. By signing, You agree to be bound by the terms of the

Solicitation. You agree to hold Your Offer open for a minimum of thirty (30) calendar days after the Opening Date. (See

"Signing Your Offer" provision.)

NAME OF OFFEROR

(full legal name of business submitting the offer)

Any award issued will be issued to, and the contract will be formed with, the entity identified as the Offeror. The entity named as the offeror must be a single and distinct legal entity. Do not use the name of a branch office or a division of a larger entity if the branch or division is not a separate legal entity, i.e., a separate corporation, partnership, sole proprietorship, etc.

AUTHORIZED SIGNATURE

(Person must be authorized to submit binding offer to contract on behalf of Offeror.)

DATE SIGNED

TITLE

(business title of person signing above)

STATE VENDOR NO.

(Register to Obtain S.C. Vendor No. at www.procurement.sc.gov)

PRINTED NAME

(printed name of person signing above)

STATE OF INCORPORATION

(If you are a corporation, identify the state of incorporation.)

OFFEROR'S TYPE OF ENTITY: (Check one) (See "Signing Your Offer" provision.)

___ Sole Proprietorship ___ Partnership ___ Other_____________________________

___ Corporate entity (not tax-exempt) ___ Corporation (tax-exempt) ___ Government entity (federal, state, or local)

COVER PAGE - ON-LINE ONLY (MAR. 2015)

http://www.procurement.sc.gov/ mailto:trappla@scdot.org http://www.procurement.sc.gov/

SAP

SAP

SAPAMENDMENTS TO SOLICITATION (JAN 2004)

(a) The Solicitation may be amended at any time prior to opening. All actual and prospective Offerors should monitor the following web site for the issuance of Amendments: www.procurement.sc.gov (b) Offerors shall acknowledge receipt of any amendment to this solicitation (1) by signing and returning the amendment, (2) by identifying the amendment number and date in the space provided for this purpose on Page Two, (3) by letter, or (4) by submitting a bid that indicates in some way that the bidder received the amendment. (c) If this solicitation is amended, then all terms and conditions which are not modified remain unchanged. [02-2A005-1]

QUESTIONS FROM OFFERORS - AMENDMENT (JUN 2017)

Information or changes resulting from questions will be shown in a question-and-answer format. All questions received have been reprinted below. The “state’s response” should be read without reference to the questions. The questions are included solely to provide a cross-reference to the potential offeror that submitted the question. Questions do not form a part of the contract; the “state’s response” does. Any restatement of part or all of an existing provision of the solicitation in an answer does not modify the original provision except as follows: underlined text is added to the original provision.

Stricken text is deleted. [02-2A097-1]

Q-1 Does a crash truck need to be provided during clearing operations?

A-1 Yes, they will need to have a crash truck. See standard drawing 610-105-01 for Daytime lane closure requirements & 610-110-01 for Nighttime lane closure requirements. See standard drawings 610-

310-00, 610-315-00, 610-320-00 & 610-325-00 for Interstate shoulder closures.

**** Traffic control that impedes the natural flow of traffic will have to adhere to the lane closure restriction for this section of Interstate. ****

Q-2 Does the SCDOT require lane closures for mulching work inside a median of an interstate?

A-2 Yes when the work is taking place within 10 FT of the edge of an adjacent travel lane. If work is taking place outside of the 10 Ft of the adjacent travel lane then a shoulder closure will be sufficient.

See 2007 standard specification for highway construction 610.4.3.2

Q-3 It is stated that "the primary route highway will not be affected by this work and no lanes on the primary rout will be closed during the activity." How should we plan to unload/load equipment on to the site? Will the SCDOT provide pace cars to slow traffic or how will this be handled?

A-3 It will be the contractor’s responsibility to provide the correct traffic control based on the mentioned information above. SCDOT will not provide any type of traffic control.

Q-5 What is the minimum distance from edge of pavement of an interstate that machines can work and be stored?

A-5 Minimum distance machines can work, refer to above. Machines have to be stored at minimum 30

Ft from the adjacent travel lane.

Q-6 What kind of traffic control is anticipated if lane closures are not an option?

A-6 There are only two options allowed. Shoulder closure or Lane closure there are no other traffic control options available for this work.