Alternate Bid Specifications -Attachment 1.pdf

PDF 242 KB Posted

Attached to
BITUMINOUS SEAL COATING WITH WASHED CRUSHED GRANITE QUARRY STONE OR EQUVILIENT AGGREGATE
Solicitation number
21-PW20
Issued by
Wisconsin

About this file

This is an Alternate Bid Specifications attachment for Request for Bid #21-PW20 issued by the City of Sun Prairie Public Works Department in Wisconsin for bituminous seal coating work. The alternate specifications outline requirements for chip seal application using boiler slag aggregate as an alternative to the primary bid specifications. The work includes application of CRS-2P bituminous emulsion at a rate of 0.28 gallons per square yard, followed by placement of dry lightweight wet bottom black boiler slag aggregate at a rate of 18 ± 1 pounds per square yard. The contractor must perform street sweeping using motorized truck or vacuum equipment within 24 hours of material application across the full pavement width. The specifications note that only the material, aggregate, sweeping, and auxiliary equipment sections differ from the main RFB 21-PW20 document, with all other specifications and requirements to comply with the primary bid requirements.

The contractor is required to supply all necessary auxiliary equipment including loaders, power brooms, power blowers, hand brooms, hand squeegees, shovels, and other items needed to perform the work. The aggregate gradation requirements are specified by sieve size, with requirements ranging from 100 percent passing for 3/4" and 3/8" sieves to 0-3 percent passing the #200 sieve. The bituminous material must be applied at appropriate temperatures based on the specific grade. This alternate bid specification provides an option for material selection while maintaining compliance with all other terms and conditions of the primary RFB 21-PW20 document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Alternate Bid Specifications for

RFB #-21-PW20

Prepared by:

City of Sun Prairie Public Works

300 East Main Street Sun Prairie, Wisconsin 53590

ATTACHMENT 1

ALTERNATE BID SPECIFICATIONS OF AGGREGATE AND BITUMINIOUS MATERIAL

FOR RFB 21-PW20

G. MATERIAL

Materials furnished and used in the work shall conform to the requirements of Section 401.

a. BITUMINOUS MATERIAL: The bituminous material to be furnished and applied shall be

CRS-2P Emulsion. The emulsion shall be applied at a rate of .28 gallons per square yard. The bitumen shall be applied at the appropriate temperature for the particular grade.

H. AGGREGATE

The cover aggregate shall be a dry lightweight wet bottom black boiler slag. The aggregate shall be applied at a rate of 18 +/- 1 pounds per square yard.

The following table shows gradation requirements of the bottom slag aggregate and the percent passing.

SIEVE 3/4” 3/8” #4” #8 #16 #200

STREETS 100 100 90-100 45-85 0-8 0-3

I. SWEEPING

Contractor to provide sweeping of streets over the full pavement width with motorized truck or vacuum type of street sweeper 24 HOURS after applications of material.

J. AUXILIARY EQUIPMENT

The contractor shall supply loaders, power brooms, power blowers, hand brooms, hand squeegees, shovels and other equipment to perform the work as necessary.

Only items G, H, I, and J, under SCOPE AND LOCATION OF WORK are different. All other specifications and requirements are to comply with main RFB 21-PW20 document.

Alternate Bid Specifications cover sheet - Attachment 1
Attachment 1 - Alternate Chip Seal bid Boiler Slag Specifications