PDF 135 KB Posted
- Attached to
- Herbicide Treatment of AlligatorweedOn Alligator
- Solicitation number
- 140FS323Q0222
About this file
This Quality Assurance Surveillance Plan outlines monitoring requirements for a ground herbicide treatment contract to control Phragmites. The contractor will be required to use only approved chemicals applied at the proper rates and in adherence with best management practices. Monitoring will include verification of approved water and chemical sources prior to spraying, as well as proper mixing, handling, and spill equipment. Notification must be provided 48 hours before each application. The contracting officer's representative will monitor application areas and plant response two to four weeks after treatment through on-site observations and GPS/GIS comparisons to contractor-supplied treatment polygons. Adherence to application requirements, coordination procedures, and achievement of control objectives will be assessed.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PWS_Alligatorweed_Spraying.pdf | ||
| Sol_140FS323Q0222.pdf | ||
| Clauses.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUALITY ASSURANCE SURVEILLANCE PLAN
GROUND HERBICIDE TREATMENT OF PHRAGMITES
CONTRACT NO.: Specify contract number
CONTRACTOR: Specify name of contractor
CONTRACTING OFFICER: Specify name of Contracting Officer
INSPECTOR(S): Kelley Van Druten
TASK /
DESCRIPTION
WHAT
WHO
WHEN
WHERE
METHOD
Provide clean water • Water supply POC • Prior to start of spraying
• Staging site • direct observation;
random selection Use of approved chemicals
• Brand
• Rate
• Adherence to
BMPs
POC • Prior to start of spraying
• Prior to start of spraying
• Random during application
• Staging site
• Verbally
• Treatment site
• Direct observation;
random selection
• Direct observation
• Direct observation;
random selection
Proper mixing and handling
• Spill equipment Tank cleanliness
POC Prior to start of spraying
Staging site Direct observation
Coordination Notification prior to spraying
POC 48 hours prior to application
Verbal or phone text
Direct observation
Herbicide application Area Treated/ Plant response
POC 2-4 weeks after treatment
Treatment sites Direct observation and measurement with GPS/GIS; comparison to contractor supplied treatment polygons