This Statement of Work (SOW) details a fire main piping crop and renew project for the USCGC ALDER (WLB 216) located at Guard Sector San Francisco. The contractor (KTR) must perform comprehensive piping system modifications, including cropping out and renewing necessary lengths of fire protection risers and associated supply piping with diameters ranging from 1/4" to 6", fabricating and installing new piping arrangements, and ensuring proper insulation, labeling, and leak testing. The work is to be completed between 15 April and 15 May at 1 Yerba Buena Island, San Francisco, CA.

Key requirements include providing a Marine Chemist for hot work certification, managing fire watches, maintaining protective measures, preventing contamination, and handling fluid disposal in compliance with federal, state, and local regulations. The contractor must also provide vehicle and personnel identification details, install new pipe hangers and insulation, perform touch-up preservation, and ensure zero visible leakage during system testing. The project emphasizes meticulous technical execution consistent with Coast Guard Drawing 225-WLB-521-001 and various standard specifications.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

USCGC ALDER (WLB 216)

Fire Main Piping Crop & Renew

1. Purpose and Scope

• KTR shall SOW

2. Deliverables and Performance Requirements

• Protective measures: The KTR must furnish and install all protective measures IAW SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

• Interferences: The KTR must handle all interferences IAW SFLC Std Spec0000, (Interferences).

• Contamination prevention: The KTR must take all precautions to prevent contamination of personnel and spaces IAW all applicable Federal, state, and local regulations.

• Fluid handling: The KTR must remove and dispose of removed fluids from the affected piping system, IAW all applicable Federal, state, and local regulations. Do not drain any fluids into any spaced, bilge, or exterior location.

• Piping renewal particulars: The KTR must accomplish the following tasks, using Coast Guard Drawing 225–WLB–521–001, REV F as guidance:

o Crop out necessary length of #1 FP riser to OVBD piping (6” ID), to include all necessary FPL supply (4” ID), pressure regulating supply (4” ID), pressure regulating bypass supply(4” ID), and pressure gauge/sensor supply (1/4” ID) piping.

o Fabricate necessary piping arrangement previously cropped IAW CG Drawing.

o Install all fabricated piping to include all required gaskets/seals IAW CG

Drawing.

o KTR must provide a means of sealing any open piping while any portion of the system is open (i.e.: upstream valve blind flange).

• Pipe hangers: Furnish, fit, and install new pipe hangers, as necessary.

• Pipe labeling: The KTR must label affected piping as follows:

o Name of the piping system service.

o Destination, where feasible.

o Direction of flow, indicated by an arrow three inches long pointing away from the lettering.

• Leak Test: After completing all authorized mechanical (i.e. threaded, bolted, etc.)

joint repairs, the Contractor must test the affected piping system's operation using the system fluid at normal operating pressure. Ensure zero visible leakage from or deformation of mechanical parts by repairing all leaks and discrepancies.

• Touch-up preservation: The KTR must prepare and coat all new and disturbed surfaces to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, (Touch-ups and minor coating repairs.)

• Piping insulation installation: The KTR must install new insulation materials over the exposed pipe surfaces at thicknesses appropriate to the application and temperature ranges specified in ASTM F683 Tables.

o Associated pipe hangers o Valves o Fittings o Flanges

3. Period of Performance

• 15 April – 15 May

4. Location and Method of Performance

• Guard Sector San Fransisco

1 Yerba Buena Island San Francisco, CA 94130

5. Roles and Responsibilities

• KTR shall provide Marine Chemist to include certification and all associated documentation for initial certification for hot work.

• KTR shall provide competent person to include certification and all associated documentation for recertification for hot work.

• KTR shall notify USCGC ALDER POC of any planned hot work prior to COB the day prior to planned hot work.

• USCGC ALDER shall provide all necessary fire watches during working hours (0700- 1500).

• KTR shall provide all necessary fire watches after working hours.

6. Acceptance Criteria

• N/A

7. Security and Confidentiality

• KTR shall provide:

o State Issued Identification numbers to include issuing state for all personnel o Vehicle license plate number to include issuing state for all KTR vehicles o Each vehicle year, make, and model

8. Reporting Requirements

9. Legal Compliance

• KTR shall comply with all applicable Federal, State, and Local laws and regulations.

10. Performance Monitoring

12. Points of Contact.

10.1. USCG-SFLC-IBCTPL Asset Management: EMCS Daniell Hurtado.

Daniell.e.hurtado@uscg.mil Phone: (510) 290-8808

10.2. USCGC ALDER: CWO2 Chris P. Laterza, email: Christopher.P.Laterza@uscg.mil Phone:

(801) 390-8106