- Solicitation number
- PE-66394-NONST-2027-000000012
- Issued by
- Mitchell County, Georgia
About this file
This Request for Bids is issued by the City of Alamo, Georgia for demolition and construction services to replace the Alamo Event Center located at 3 Railroad Avenue, Alamo, GA 30411, which was damaged by Hurricane Helene. The project involves demolishing the existing concrete slab and foundation and constructing a new single-story masonry building approximately 80 feet by 80 feet with a mezzanine and an ICC 500/FEMA P-361 tornado safe room. The facility will include an event hall (59' x 78'-4"), lobby with mezzanine, office/safe room, storage room, mechanical room, two restrooms, and exterior features including face brick veneer, metal canopy, and metal storefront entry. Sealed bids must be submitted electronically through the DFS Procurement Portal at dfs.bonfirehub.com no later than Monday, December 14, 2026 at 9:00 A.M. EST, with bids to be opened at 10:00 A.M. the same day at Alamo City Hall. Bidders may request site visits by contacting City Manager Jeff Floyd at 912-423-9341 during office hours, contingent upon availability. Questions must be submitted within the Portal and cannot be answered if submitted within 72 hours of the deadline. The contract will be awarded to the lowest responsive and responsible bidder on a firm fixed-price basis. No work shall commence until FEMA's review is finalized, the contract is executed, and a Notice to Proceed is issued by the City.
The bid includes a 10 percent bid guarantee, and successful bidders must provide Performance and Payment Bonds for 100 percent of the contract award amount prior to work commencement. Bidders must submit proof of insurance coverage including Commercial General Liability ($2,000,000 aggregate/$1,000,000 per occurrence), Comprehensive Automobile Liability ($1,000,000 per occurrence), Worker's Compensation ($500,000 per occurrence), and Umbrella/Excess Liability ($1,000,000-$5,000,000). Unit and lump sum pricing must be all-inclusive of labor, materials, equipment, permits, testing, and disposal. The project is partially funded through FEMA's Public Assistance Program, and award is contingent upon FEMA's formal approval, obligation, and availability of grant funds as well as appropriation of required local matching funds. The City reserves the right to delay the award, modify the scope of work, or cancel the solicitation without penalty if FEMA funding is denied, delayed, or reduced. Payment follows only after work completion, receipt of all documentation, reconciliation by the Grants Management Team, and City approval. All bidders must comply with federal, state, and local laws, including E-Verify requirements under O.C.G.A. 13-10-91, and must submit required certifications and affidavits regarding non-collusion, lobbying, debarment, conflict of interest, drug-free workplace, and contractor authorization.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ALAMO EVENT CENTER 11_13_26 Full Arch _ Eng S.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF ALAMO, GEORGIA
7 West Main Street, Alamo, GA 30411
REQUEST FOR BIDS
4830 - 952160 - Alamo Event Center - Demolition & Construction Services
The City of Alamo, Georgia (hereinafter “City”) is seeking sealed bids for construction services to replace the Alamo Event Center, located at 3 Railroad Ave, Alamo, GA 30411, which was damaged as a result of Hurricane Helene. This project will be partially funded through FEMA’s
Public Assistance Program with the purpose of demolishing the existing concrete slab and foundation and constructing a new Alamo Event Center as shown on the design plans: an approximately 80'-0" x 80'-0" single-story masonry building (reinforced CMU with brick veneer at the front elevation) with a mezzanine and an ICC 500 / FEMA P-361 tornado safe room.
BID SUBMISSION INFORMATION
Bids and all required documents must be submitted online to the DFS Procurement Portal
(hereinafter “DFS Portal” or “Portal”) at dfs.bonfirehub.com no later than Monday, December
14, 2026 at 9:00 A.M., local time (EST).
● Bids received after the due date and time will be considered non-responsive and will not be considered.
● Multiple bid submissions from the same entity will not be accepted.
● Submission is electronic only through the online DFS Portal. Hard copy bids or offers by telephone, fax, or email will not be accepted.
● All requested information fields in the Portal must be filled out and all requested documentation must be provided as instructed to be considered a valid bid, including all
Confirmations and Declarations provided in Appendix B of this RFB.
Bids will be opened and read aloud at the Alamo City Hall on Monday, December 14, 2026 at
10:00 AM at the Alamo City Hall, located at 7 West Main St, Alamo, GA 30411.
Bidders must provide insurance policies in the DFS Procurement Portal showing proof of coverage, as described in Attachment 8, upon submission.
Bidders shall submit a bid guarantee in the amount of 10% of the total bid price, which shall be in the form of a firm commitment such as a bid bond, postal money order, certified check, cashier’s check, or irrevocable letter of credit as either a hard (paper) or soft (digital) copy by the submission deadline. Bid guarantees other than bid bonds will be returned (a) to
4830 - 952160 — ALAMO EVENT CENTER - DEMOLITION & CONSTRUCTION SERVICES 1/26
http://dfs.bonfirehub.com unsuccessful bidders after the opening of bids; and (b) to the successful bidder upon execution of such further contractual documents (i.e., insurance coverage) and bonds as may be required by the bid. Hard copies shall be delivered to the City of Alamo City Hall, at 7 West Main St, Alamo, GA 30411. Soft copies shall be uploaded to the DFS Procurement Portal.
Questions regarding this RFB are to be submitted within the Portal at dfs.bonfirehub.com.
Answers will be provided within the Portal, and all answered questions will be made public within the Portal. Questions submitted outside of the Portal by email or phone will not be answered. Questions submitted within 72 hours of the submission deadline will not be answered. For questions regarding Portal registration or navigation, please email:
procurement@erassist.com.
Site visits may be requested by contacting the City Manager, Jeff Floyd at 912-423-9341 during office hours. Site visits are not guaranteed and are contingent upon availability.
Bidders are hereby notified that this project is anticipated to be funded, in whole or in part, through federal financial assistance provided by the Federal Emergency Management Agency
(FEMA). The issuance of this Request for Bids (RFB) does not commit the City of Alamo to award a contract or to pay any costs incurred in the preparation of a bid. Any contract award resulting from this solicitation is strictly contingent upon the formal approval, obligation, and availability of FEMA grant funds, as well as the appropriation of any required local matching funds. The City of Alamo reserves the right to delay the award, modify the scope of work, or cancel this solicitation in its entirety without penalty or liability if FEMA funding is denied, delayed, or reduced. No work shall commence, and no costs shall be incurred by the successful bidder, until a formal contract is executed and a written Notice to Proceed (NTP) is issued by the
City of Alamo.
GENERAL TERMS & INFORMATION
A. Submission of any bid signifies the Contractor’s agreement that their bid and the content thereof, are valid for one hundred eighty (180) calendar days following the submission deadline and will become part of the contract between the City of Alamo and the successful bidder. All prices submitted with the bid shall remain in effect for the one hundred eighty (180) day period.
B. Award will be made to the lowest responsive and responsible bidder based on the Total
Base Bid. A firm fixed-price contract will be executed.
C. Work cannot start until FEMA’s review of this project is finalized, the contract agreement is fully executed, and the contractor has received a Notice to Proceed from the City.
D. The successful bidder must provide a Performance Bond and a Payment Bond for 100% of the contract work award amount prior to the start of work and the amount shall be increased if the contract amount is increased.
4830 - 952160 — ALAMO EVENT CENTER - DEMOLITION & CONSTRUCTION SERVICES 2/26
http://dfs.bonfirehub.com mailto:procurement@erassist.com
E. Work will not be considered complete until all invoice documents are provided and invoice validation is complete. Final invoice with all required documents must be provided in a single transmission (email or link to a Dropbox, Google Drive, or other file sharing service). Multi-part transmission of invoice documentation will cause a delay in validation which will affect payment processing timelines and designation of completion.
F. The Scope of Work, location details, and a sample Bid Table are provided in Appendix A of this RFB. The full design plan set is available for download in the Portal and linked in Appendix A.
G. Contractor shall be responsible for all expenses incurred while performing services under this Agreement. This includes automobile, truck, and other travel expenses; vehicle maintenance and repair costs; vehicle and other license fees and permits; insurance premiums; road, fuel, and other taxes; fines; radio, pager, or cell phone expenses; meals;
and all salary, expenses, and other compensation paid to employees or contract personnel the Contractor hires to complete the work under this Agreement.
H. The contractor will restore any landscaping, asphalt, concrete, etc. disturbed during construction to its original state or approved alternative. Any damage to the City’s property caused during construction will be repaired at the contractor’s expense.
I. Contractors will be responsible for determining all requirements and permits needed to complete the reconstruction work and any associated components needed to ensure the proper, efficient, and safe completion of this project. The awarded contractor will also be responsible for obtaining any and all engineering approvals mandated and required by federal, state, or local codes or regulations. All permits, inspections, engineering approvals and associated requirements are the responsibility of the selected Contractor. Copies of required permits and approvals must be provided to the City upon receipt.
J. This work is for a specific site/project with quantities listed on a FEMA grant; as such documentation supporting the quantities of materials and/or work must be provided (e.g.
receipts, quarry tickets, or load counts/truck capacities). Invoices must list the haul off location of any debris, spoils, or waste (example: permitted landfill, recycling location, or road dept for reuse).
K. Any contract resulting from this RFB will contain the required “FEMA clauses.” These may be found on FEMA’s website at the following link: contract provisions template | fema.
L. Payment will follow only after work is completed, all documentation is received from the Contractor and reconciled by the Grants Management Team, and approval by the City.
(Documentation to include items such as before/after photos (always required), quantity documentation (itemized receipts/invoices), and documentation of disposal, as applicable.
M. Change Orders may be issued if changes to the Scope of Work are necessary in the performance of the awarded contract. No changes shall be made by the contractor without a change order signed by all parties.
N. Successful bidders, assigns, subcontractors must be compliant with all applicable Federal, State and Local laws.
4830 - 952160 — ALAMO EVENT CENTER - DEMOLITION & CONSTRUCTION SERVICES 3/26
https://www.fema.gov/sites/default/files/2020-07/fema_procurement_contract-provisions-template.pdf
O. The City of Alamo reserves the right to accept or reject any or all bids. The right is also reserved to waive any minor irregularities, and to award the bidder whose offer is most advantageous to the City and in the best interests of the City.
P. The City of Alamo is an Equal Opportunity Employer. All companies, including women, minority, and veteran owned businesses are encouraged to submit a bid.
4830 - 952160 — ALAMO EVENT CENTER - DEMOLITION & CONSTRUCTION SERVICES 4/26
Appendix A
SCOPE OF WORK
1. Project Description
The City of Alamo, Georgia (the "City") is seeking a qualified general contractor to furnish all labor, materials, equipment, supervision, and services necessary to construct the Alamo Event Center at 3
Railroad Avenue, Alamo, GA 30411, complete and ready for use, in accordance with the Contract
Documents. The Work includes demolition and removal of the existing concrete slab and foundation and construction of a new single-story masonry event building with a mezzanine and an ICC 500 / FEMA
P-361 tornado safe room, as shown on the design plans.
As shown on the plans, the building is approximately 80'-0" x 80'-0" in plan, Type VA construction, with
Assembly (A), Business (B), and Storage (S-1) occupancies. It has the following spaces:
● Event Hall: 59' x 78'-4"
● Lobby: 19'-4" x 49'-6", with a Mezzanine above (19'-4" x 49'-6") reached by two stair runs with a
42" metal railing
● Office / Safe Room: 14' x 14', built as a reinforced CMU storm shelter, with breakroom casework
● Storage room (4' x 7') and Mechanical room (4' x 7')
● Two single-user accessible restrooms, a mop sink room, drinking fountains, and the water heater location
● Exterior: 8" CMU walls, with face brick veneer, soldier-course banding and herringbone niche infill on the front elevation; a metal-frame canopy; metal storefront entry and windows; a metal roll-up overhead door; a white Class "A" roof membrane with parapet coping, gutters and downspouts; and 5'x5'x4" concrete pads at exterior doors
2. Contract Documents
The Work shall conform to the design plan set titled "Alamo Event Center 11-13-26 Full Arch & Eng Set"
(41 sheets), and to all notes, schedules, details and specifications on those sheets. The set includes:
● Architectural (Sheets A0, A1, LS, A2–A5) by Dean Architecture and Design, LLC, Vidalia, GA, dated
04/30/2026 and revised 06/23/2026, with Sheets A0, A3 and A4 revised 11/13/2026.
● Structural, Safe Room / Storm Shelter, Plumbing, Electrical and Mechanical (Sheets S1.0–S1.3, D1.0–D2.0, SS2.0–SS2.3, P1.0–P1.4 and P1.4.1, E1.0–E1.10, M1.0–M1.6) by Dillett Engineering
Group, P.L.L.C. (Structural, Safe Room, Plumbing and Mechanical sheets revised 11/6/26;
Electrical and Fire Alarm sheets dated 11/11/26).
Where the drawings conflict, or a dimension or detail is missing or unclear, the Contractor shall submit a
Question within the Portal. Where notes, specifications and plans conflict, the more stringent requirement governs unless the Architect/Engineer directs otherwise in writing.
4830 - 952160 — ALAMO EVENT CENTER - DEMOLITION & CONSTRUCTION SERVICES 5/26
3. Work to Be Performed
The Work includes, but is not limited to, the following. All items are to be performed per plans, and quantities are as shown on the plans unless otherwise noted.
3.1 General Requirements and Site Preparation
● Mobilize, set up temporary facilities (field office/storage, sanitary facilities, temporary power and water as needed), provide construction fencing and site protection, and demobilize at completion.
● Demolish, remove and lawfully dispose of the existing concrete slab and foundation (Project
Note 2, Sheet A0).
● Perform site preparation, excavation, compacted subgrade/structural fill, backfill and finish grading. Slope grade so surface water drains away from the foundation and does not pond next to the structure (Site Drainage Recommendations, Sheet S1.0).
● Coordinate new utility services (power, water, sewer) with the utility providers and the City.
3.2 Concrete and Foundations
● Construct continuous and spread footings (CF1, CF2, F2.0, F3.0), turndown/deepened footings and column pad footings per the Footing Layout Plan (S1.1), Footing Schedule and Details (D1.0), with Grade 60 reinforcing, anchor bolts, plate washers and hold-down hardware. Safe-room footings are covered in Section 3.4.
● Place a 4" concrete slab on grade with #4 @ 16" O.C. each way (2,500 psi per the S1.1 slab note), over 15-mil vapor barrier (ASTM E1745), over 4" sand/clean aggregate base. Install slab joints at
12'-0" O.C. maximum and apply a concrete sealer finish where the Finish Schedule calls for it.
Concrete strengths by element, as shown: footings and structural concrete 3,000 psi (S1.0
Reinforced Concrete Notes; S1.1 Material Grade); storm shelter footings and wall grout 3,000 psi, and shelter slab and roof 4,000 psi (S1.0 Storm Shelter Material Notes); masonry f'm = 2,000 psi (S1.0, SS2.1).
● Construct 6" diameter reinforced concrete columns ((4) #5 vertical bars, #3 ties @ 5" O.C.) per plans and details.
● Place 5'x5'x4" concrete pads outside the exterior doors and 4" housekeeping pads for floor-mounted mechanical equipment.
3.3 Masonry
● Construct 8" reinforced CMU exterior walls (#5 vertical J-bars @ 16" O.C., #4 horizontal @ 16"
O.C.) with grout, bond beams and Castcrete precast U-lintels (8F16-1B-1T) per the Lintel
Schedule, Type S mortar, ASTM C90 units.
● Install face brick veneer on the front elevation: M/S Heirloom Salem by Cherokee Brick & Tile Co.
(Product No. 53-08-333, ASTM C216 Grade SW, Type FBS) or an approved equal, with soldier-course banding, herringbone-pattern brick niches, ties, flashing and weeps.
3.4 Office / Safe Room (ICC 500 / FEMA P-361 Storm Shelter)
● Build the Office/Safe Room as a tornado storm shelter per ANSI/ICC 500-2023 and FEMA P-361, designed for a 250 mph ultimate tornado wind speed and the ICC 500 missile impact criteria, per
4830 - 952160 — ALAMO EVENT CENTER - DEMOLITION & CONSTRUCTION SERVICES 6/26
Sheet S1.0 (Storm Shelter Notes) and Sheets SS2.0–SS2.3. The work includes 8" normal-weight
CMU walls, fully grouted, with vertical reinforcement per plans, ladder reinforcing @ 16" O.C. or bond beams @ 48" O.C. and a continuous top bond beam; shelter footings 24" wide x 12" deep with (3) #5 continuous and #5 x 1'-6" transverse @ 12" O.C. (S1.0, 2/SS2.2); #5 dowels to the footings and slab; a 4" minimum shelter slab on grade with #4 @ 12" O.C. each way (SS2.3); the door beam (8/SS2.3); and a 6" cast-in-place reinforced concrete roof slab with #5 bars @ 6" O.C.
each way, 4,000 psi, continuously connected to the CMU bond beam for uplift (S1.0 Roof Notes
26–28; 3/SS2.2).
● Furnish and install an ICC 500 tested and certified, outswinging storm shelter door assembly with a minimum 36" clear width, multi-point latching hardware, and a frame anchored into reinforced
CMU cells per the manufacturer (S1.0 Door Notes 30–34; SS2.3).
● Keep all shelter penetrations to a minimum and make them ICC 500 compliant. Provide shelter ventilation per ICC 500. Do not modify any storm shelter construction without written approval of the Engineer of Record. Reinforcement shall be inspected before grouting or concrete placement (S1.0 Notes 35–41).
3.5 Wood Framing, Mezzanine and Roof Structure
● Frame the roof with 2x12 YP rafters/joists @ 16" O.C., (4)-ply 1-3/4" x 14" LVL beams on columns, plywood roof sheathing, blocking, and Simpson Strong-Tie (or equal) connectors and uplift ties per S1.3, D1.0 and D2.0.
● Frame the mezzanine floor with 2x12 YP floor joists @ 16" O.C., LVL beams, 4x6 posts and 3/4"
T&G plywood subfloor (glued and nailed). Build the stairs (8 risers @ 6-3/4" per run) with landing, handrails and the 42"-high metal guard railing (S1.2, D2.0). The metal guard railing is included in this Work.
● Build 2x4 wood-stud interior partitions @ 16" O.C. per plans.
● Coat all wood structural elements with "Flame Off" (or equal) water-based intumescent fire-resistant paint compliant with ASTM E119/UL 263, to a minimum 1-hour fire rating (Project
Note 3, Sheet A0).
3.6 Roofing, Insulation and Sheet Metal
● Install a Class "A" roof membrane system, GAFGLAS EnergyCap (white, SRI-100, reflectivity 0.80) or equal, sloped 1/2" per foot, with base flashing, cant strips and accessories per the manufacturer and Detail 1/A2.
● Install R-38 spray foam roof insulation.
● Install painted galvanized metal parapet coping and flashing per Detail 1/A2, and aluminum gutters and downspouts.
● Furnish and install the steel/metal-frame canopy at the front elevation.
3.7 Doors, Windows and Hardware
● Furnish and install doors, frames and hardware per the Door Legend (Sheet A5): Type A, Metal
Roll-Up Overhead Door 12'-0" x 10'-0" (1); Type B, Metal Entry pair 6'-0" x 8'-0" with 1" insulated tempered glazing, interior panic and exterior lockset (1); Type C, Interior Metal pair 6'-0" x 8'-0"
4830 - 952160 — ALAMO EVENT CENTER - DEMOLITION & CONSTRUCTION SERVICES 7/26
with lockset (2); Type D, Metal 3'-0" x 6'-8" with passage hardware (6). Hardware shall be ADA compliant.
● Furnish and install Type 1 metal storefront windows, 5'-4" x 6'-0", 1" insulated tempered glazing, U-0.32, SHGC 0.25, DP 30–40 (4).
3.8 Interior Finishes and Specialties
● Install 1/2" gypsum wallboard, and paint walls and ceilings per the Material & Finish Schedule.
Paint exposed framing at the Event Hall and Mezzanine.
● Finish floors per the Material & Finish Schedule: sealed concrete (Lobby, Event Hall, Office/Safe
Room, Storage/Mech, Hallway), ceramic tile (Restrooms) and plywood (Mezzanine). Install 4" vinyl cove base, restroom wall tile to 48" AFF, and acoustical tile ceilings in the Restrooms.
● Furnish and install breakroom casework in the Office: plastic laminate base and wall cabinets and countertop, with a space for a 24" refrigerator, per the Breakroom Cabinet Elevation.
● Furnish and install ADA toilet room accessories and grab bars, ADA door and wall signage, and fire extinguisher cabinets with extinguishers per the Life Safety Plan and ADA Details.
3.9 Plumbing
● Furnish and install plumbing fixtures per Sheets P1.0–P1.2: (2) tank-type water closets, (3) lavatories, (1) mop sink and (2) drinking fountains as shown on the plans (A1, P1.1), with ADA lever-type faucets and insulated hot water and drain lines, per the Plumbing Details (P1.4).
● Install domestic water distribution from the utility meter: 1" water service with main shut-off, 1"
PRV set @ 65 psi and ball valves (P1.1), and hot/cold distribution in PEX-A / Type L copper. Install sanitary waste and vent piping (3" sanitary riser, 2" vent riser), condensate drains, pipe insulation per the Pipe Insulation Schedule, and connections to utilities (P1.0–P1.3).
● Furnish and install water heater WH-1, Rheem XE40T10H45U1 hybrid electric heat pump, 40 gal nominal, 4,500 W, 208–240V/1Ø, 30 A MCA, per the Water Heater Schedule (P1.0) and Water
Heater Detail 11/P1.4.1, including a condensate drain and the air path the manufacturer requires
(a space larger than 700 ft³, a full louvered door or two louvers, or inlet/outlet ducting, per
P1.4.1).
3.10 Heating, Ventilation and Air Conditioning (HVAC)
● Furnish and install split-system HVAC: outdoor unit HP-01 (Trane TTA1504, 12.5 tons) and indoor air handler AHU-01 (Trane TWE150, 5,000 CFM), with refrigerant piping, condensate piping, supports, controls and a 7-day programmable thermostat (M1.0–M1.6).
● Furnish and install ventilation and exhaust equipment: in-line supply fans SF-01 (Greenheck
SQ-7) and SF-02 (Greenheck SQ-90), restroom exhaust fans EF-01 (Greenheck SP-B50, qty 2) with backdraft dampers, and outside-air louvers LV-01 (28"x24") and LV-02 (18"x12").
● Furnish and install galvanized sheet metal (spiral and rectangular) supply, return, outside-air and exhaust ductwork with insulation, sealing, hangers, volume dampers, and grilles/registers per the Inlets & Outlets Schedule (SG-01 typ. 21, SG-02 typ. 6, RG-01, EG-01).
● Provide testing, adjusting and balancing (TAB) by an independent NEBB- or AABC-certified agency, controls verification, and submission of the TAB report.
4830 - 952160 — ALAMO EVENT CENTER - DEMOLITION & CONSTRUCTION SERVICES 8/26
3.11 Electrical
● Install the electrical service and distribution: utility coordination; 400A meter and disconnects;
400A, 208/120V, 3Ø, 4W, NEMA 3R main distribution panel (MDP) with feeders; (2) 200A panelboards, DP-1 (lighting and receptacles) and DP-2 (mechanical); and the grounding electrode system (concrete-encased/Ufer electrode, ground rods, bonding) per Sheets E1.1 and E1.2, with feeders per plans (E1.2).
● Install branch circuit wiring in conduit, wiring devices (switches, 3-way and dimmer switches, occupancy sensors, receptacles, GFCI), and equipment connections for HVAC, fans, water heater and other equipment, per Sheets E1.0 and E1.3–E1.6.
● Furnish and install light fixtures per the Lighting Fixture Schedule on E1.2 and the cut sheets on
E1.7 (Types A, B, C, D, E, F, H, E-1 and EM-1), as shown on E1.3 and E1.4: Type A LED high-bay
(20), Type B 6" recessed downlights (14), Type C 2x4 LED panel (1), Type D LED strip lights (19, including 17 at the Mezzanine and stair), Type E vanity lights (2), Type F Barn Light Electric
Marathon ceiling fixtures at the front canopy (3), Type H Barn Light Electric Marathon gooseneck wall fixtures (7), LED exit/emergency combo units (E-1) and emergency lighting units (EM-1).
● Furnish and install a complete addressable fire alarm system per Sheets E1.8–E1.10 and NFPA
72: fire alarm control panel (FACP) in Storage with 24 VDC secondary batteries, remote annunciator, IP/cellular communicator, addressable smoke detectors, manual pull stations, horn/strobes, end-of-line devices, duct smoke detector at the AHU-01 supply with AHU-01 shutdown interface (RY-01), dedicated FACP circuit from DP-1, and wiring per the E1.10 Wire
Legend, with connection to central-station monitoring. Include battery calculations, shop drawings and cut sheets, the fire alarm permit and AHJ/State Fire Marshal approval, programming, NFPA 72 acceptance testing and certification, and Owner training.
3.12 Bid Alternate
● Alternate No. 1, Fire Sprinkler System: Design, permit, furnish and install an automatic fire sprinkler system for the building per NFPA 13 (Project Note 4, Sheet A0), including hydraulic calculations, shop drawings sealed as required, fire-line/backflow requirements, and acceptance testing. Price the Alternate separately. It is not part of the Total Base Bid.
4. General Requirements
Work per Plans and Specifications. Perform all work in accordance with the Contract Documents, approved submittals, manufacturers' installation instructions, and good construction practice, so the facility is complete and fully operational. Work and materials that are reasonably inferable from the
Contract Documents as necessary for a complete installation are included even if not specifically shown.
Codes and Standards. Comply with all applicable federal, state and local codes, ordinances and regulations, including those listed on Sheet A0 (2024 IBC, IRC, IFC, IMC, IPC and IFGC with Georgia
Amendments; 2023 NEC with Georgia Amendments; 2015 IECC with Georgia Amendments) and the storm shelter standards on Sheets S1.0 and SS2.0 (ICC 500, FEMA P-361, TMS 402/602, ACI 318), the ADA
/ ICC A117.1, NFPA requirements, and the requirements of the State Fire Marshal and the local Authority
Having Jurisdiction.
4830 - 952160 — ALAMO EVENT CENTER - DEMOLITION & CONSTRUCTION SERVICES 9/26
Permits, Fees and Inspections. Obtain and pay for all permits, licenses, fees and inspections required for the Work, and schedule all required inspections. Do not conceal any work before it is inspected and approved. Give the City copies of all permits, inspection reports and approvals.
Special Inspections and Testing. Provide the special inspection agency and testing (including concrete, reinforcing, masonry/grout, roof diaphragm nailing and storm shelter construction) required by the
Contract Documents and the Building Official, and submit the agency and its qualifications to the
Building Official before construction.
Existing Conditions. Visit the site and verify all existing conditions, dimensions and utility locations before bidding and before starting work. Report any discrepancy in writing to the Architect/Engineer before proceeding. Call Georgia 811 for utility locates before excavating.
Submittals. Submit product data, shop drawings and samples to the Architect/Engineer for approval before ordering or fabricating, including all items the drawings require (e.g., structural components, storm shelter door, wiring/raceways/devices, panelboards, light fixtures, fire alarm system, HVAC equipment, plumbing fixtures, roofing system, doors/windows/hardware, finishes). Substitutions require written approval.
Coordination and Utilities. Coordinate all trades, and coordinate utility service work with the serving utilities. Coordinate work hours, deliveries, staging and site access with the City.
Protection of Property and Safety. Protect adjacent property, streets, utilities, landscaping and the public. Provide all bracing, shoring and temporary protection needed during construction. Comply with
OSHA and all applicable safety requirements. Repair any damage caused by the Contractor at no cost to the City.
Debris Removal and Disposal. Remove all demolition debris, construction waste and spoils from the site, and dispose of them lawfully at a permitted facility. Document the disposal location and quantities (load tickets/receipts) for the City's FEMA records.
Site Cleanup. Keep the site clean and orderly, and remove debris regularly. When the Work is finished, perform a final cleaning of the building and site, restore any areas disturbed by construction, and leave the premises broom-clean and ready for occupancy.
Documentation for FEMA Public Assistance. This project is funded in part through FEMA's Public
Assistance Program. Provide dated before, during and after photographs, and itemized documentation supporting quantities of materials and work performed (invoices, receipts, delivery/load tickets), with each pay application as the City requires.
Record Drawings, O&M Manuals and Closeout. Maintain a current set of as-built record drawings on site and deliver final record drawings (including final panel schedules), operation and maintenance manuals, equipment warranties, TAB reports and test reports at closeout.
Warranty. Warrant all labor and materials for a minimum of one (1) year from the date of substantial completion/City acceptance, in addition to manufacturers' warranties.
Changes. Do not make any change to the Scope of Work, plans or specifications without a written
Change Order executed by the City.
4830 - 952160 — ALAMO EVENT CENTER - DEMOLITION & CONSTRUCTION SERVICES 10/26
Bid Pricing. Unit and lump sum prices shall be all-inclusive: labor, materials, equipment, supervision, overhead, profit, permits, testing, removal and disposal, and all other costs needed to complete each item.
Quantities. Quantities listed are approximate and provided for bidding purposes only. Bidders are responsible for verifying all quantities, including any shown as "Per plans," from the plans (Contract
Documents) and site conditions. No additional compensation will be allowed for quantity discrepancies on lump sum items.
Facility Name: Alamo Event Center
Facility Address: 3 Railroad Avenue, Alamo, GA 30411
GPS Coordinates: 32.148156, -82.778786
Photos of Hurricane Damage: Provided in Portal files and linked HERE
Architectural Design Plans: Provided in Portal files and linked HERE
4830 - 952160 — ALAMO EVENT CENTER - DEMOLITION & CONSTRUCTION SERVICES 11/26
https://www.google.com/maps/place/32%C2%B008'53.4%22N+82%C2%B046'43.6%22W/@32.148156,-82.778786,863m/data=!3m2!1e3!4b1!4m4!3m3!8m2!3d32.148156!4d-82.778786?entry=ttu&g_ep=EgoyMDI2MTAxNC4wIKXMDSoASAFQAw%3D%3D https://erassist-files.s3.amazonaws.com/media/uploads/DR4830GA_WO_102266_DI_1472659_Photo_Sheet.pdf https://erassist-files.s3.amazonaws.com/media/uploads/ALAMO_EVENT_CENTER_11-13-26_Full_Arch__Eng_Set.pdf
Sample Bid Table All Bid Prices shall be entered into the Bid Table in the Portal. This list is provided for reference only.
Unit pricing shall be all-inclusive and include demolition, removal and disposal of existing construction and debris as well as all labor (including equipment programming), equipment, material, contingency, and supply costs and shall not be increased or changed for any reason other than changes requested or approved by the City.
Line Item#
Line Item Description Qty Unit of
Measure Unit Price
Total Price
A. GENERAL REQUIREMENTS
Mobilization, general conditions, bonds, insurance, permits and fees, temporary facilities, site protection, final cleanup and demobilization
1 LS
Special inspections and testing (concrete, reinforcing, masonry/grout, roof diaphragm nailing, storm shelter) and closeout documents (record drawings, O&M manuals, warranties)
1 LS
B. DEMOLITION AND SITEWORK
Demolition, removal and disposal of existing concrete slab and foundation (Project Note 2, Sheet A0)
1 LS
Site preparation, excavation, compacted subgrade/fill, backfill and finish grading for drainage away from the building
6,400 SF
C. CONCRETE AND FOUNDATIONS
Concrete footings: CF1 and CF2 continuous footings, F2.0 and F3.0 spread footings, and turndown/deepened footings, with reinforcing, anchor bolts and hold-downs (S1.1, D1.0;
3,000 psi per S1.0/S1.1)
58 CY
4" concrete slab on grade with #4 @ 16" O.C. E.W., 15-mil vapor barrier, 4" sand base, joints, and concrete sealer finish where scheduled (S1.1; 2,500 psi per S1.1)
6,190 SF
7 6" dia. reinforced concrete columns 6 EA
8 Exterior 5'x5'x4" concrete pads at exterior doors 2 EA
D. MASONRY
8" reinforced CMU exterior walls, grout, bond beams and precast lintels (net of openings)
4,550 SF
Face brick veneer at front elevation, Cherokee M/S Heirloom Salem or equal, with soldier-course banding, herringbone niches, ties and flashing (net of openings)
1,100 SF
E. OFFICE / SAFE ROOM (ICC 500 STORM SHELTER)
4830 - 952160 — ALAMO EVENT CENTER - DEMOLITION & CONSTRUCTION SERVICES 12/26
All Bid Prices shall be entered into the Bid Table in the Portal. This list is provided for reference only.
Unit pricing shall be all-inclusive and include demolition, removal and disposal of existing construction and debris as well as all labor (including equipment programming), equipment, material, contingency, and supply costs and shall not be increased or changed for any reason other than changes requested or approved by the City.
Line Item#
Line Item Description Qty Unit of
Measure Unit Price
Total Price
Safe room structure per S1.0 and SS2.0–SS2.3: 8" fully grouted reinforced CMU walls (reinforcement per plans) and bond beams, 24"x12" shelter footings with (3) #5 (3,000 psi), 4" min. shelter slab with #4 @ 12" O.C. E.W., door beam, 6" CIP concrete roof slab with #5 @ 6" O.C. E.W. (4,000 psi) connected to the bond beam, ICC 500 penetrations and ventilation
196 SF
ICC 500 tested and certified storm shelter door assembly, 36" min. clear, outswing, multi-point latch, frame and anchorage (S1.0 Door Notes; SS2.3)
1 EA
F. WOOD FRAMING, MEZZANINE AND ROOF STRUCTURE
Roof framing: 2x12 YP rafters @ 16" O.C., (4)-ply 1-3/4"x14" LVL beams, roof sheathing, blocking and connectors
6,190 SF
Mezzanine floor framing: 2x12 floor joists, LVL beams, 4x6 posts and 3/4" T&G plywood floor (S1.2, D2.0)
957 SF
Mezzanine stair, two flights of 8 risers @ 6-3/4" with landing and handrails
1 EA
16 42" high metal guard railing at mezzanine 66 LF
17 Interior 2x4 wood-stud partitions @ 16" O.C. with 1/2" GWB 80 LF
Intumescent fire-resistant coating ("Flame Off" or equal, ASTM E119/UL 263, 1-hour) on all wood structural elements
7,150 SF
G. ROOFING, INSULATION AND SHEET METAL
Class "A" roof membrane system, GAFGLAS EnergyCap (white) or equal, with base flashings, cant strips and accessories
6,190 SF
20 R-38 spray foam roof insulation 6,190 SF
Painted galvanized parapet coping and flashing per Detail 1/A2
320 LF
22 Aluminum gutters with downspouts 80 LF
23 Steel/metal-frame canopy at front elevation 110 SF
H. DOORS, WINDOWS AND HARDWARE
24 Type A: Metal roll-up overhead door, 12'-0" x 10'-0" 1 EA
4830 - 952160 — ALAMO EVENT CENTER - DEMOLITION & CONSTRUCTION SERVICES 13/26
All Bid Prices shall be entered into the Bid Table in the Portal. This list is provided for reference only.
Unit pricing shall be all-inclusive and include demolition, removal and disposal of existing construction and debris as well as all labor (including equipment programming), equipment, material, contingency, and supply costs and shall not be increased or changed for any reason other than changes requested or approved by the City.
Line Item#
Line Item Description Qty Unit of
Measure Unit Price
Total Price
Type B: Metal entry door pair with frame, 6'-0" x 8'-0", 1" insulated tempered glazing, interior panic / exterior lockset
1 EA
Type C: Interior metal door pair with frame, 6'-0" x 8'-0", lockset
2 EA
Type D: Metal door with frame, 3'-0" x 6'-8", passage hardware (excludes the Office/Safe Room door in Item 12)
6 EA
Type 1: Metal storefront windows, 5'-4" x 6'-0", 1" insulated tempered glazing
4 EA
I. INTERIOR FINISHES AND SPECIALTIES
1/2" gypsum wallboard, taped and painted, at walls and ceilings per Material & Finish Schedule
6,850 SF
30 Paint exposed ceiling framing at Event Hall and Mezzanine 5,580 SF
31 Ceramic tile, restroom floors and wall tile to 48" AFF 300 SF
32 4" vinyl cove base 430 LF
33 Acoustical tile ceiling at restrooms 100 SF
Breakroom casework: plastic laminate base and wall cabinets and countertop
7 LF
35 Toilet room accessories and ADA grab bars, per restroom 2 EA
36 Fire extinguisher cabinets with extinguishers 5 EA
37 ADA room and door signage 1 LS
J. PLUMBING
Water closets, floor-mount tank type, ADA, with trim (P1.0–P1.2)
2 EA
39 Lavatories/sinks with ADA lever faucets and trim (P1.0–P1.2) 3 EA
40 Mop sink with faucet and trim (P1.0–P1.2) 1 EA
41 Drinking fountains (A1, P1.1) 2 EA
Domestic water, sanitary waste and vent, and condensate piping, with 1" water service (P1.1), PRV, valves, insulation and utility connections (P1.0–P1.3)
1 LS
4830 - 952160 — ALAMO EVENT CENTER - DEMOLITION & CONSTRUCTION SERVICES 14/26
All Bid Prices shall be entered into the Bid Table in the Portal. This list is provided for reference only.
Unit pricing shall be all-inclusive and include demolition, removal and disposal of existing construction and debris as well as all labor (including equipment programming), equipment, material, contingency, and supply costs and shall not be increased or changed for any reason other than changes requested or approved by the City.
Line Item#
Line Item Description Qty Unit of
Measure Unit Price
Total Price
Water heater WH-1, Rheem XE40T10H45U1 hybrid electric heat pump, 40 gal, 4,500 W, 30 A MCA (P1.0, P1.4.1), with condensate drain and louvered door/ducting per manufacturer
1 EA
K. HVAC
Split-system HVAC: HP-01 (Trane TTA1504, 12.5 ton) and AHU-01 (Trane TWE150), refrigerant and condensate piping, housekeeping pads, controls and programmable thermostat (M1.0–M1.6)
1 LS
Fans: in-line supply fans SF-01 and SF-02, and restroom exhaust fans EF-01
4 EA
46 Outside-air louvers LV-01 (28"x24") and LV-02 (18"x12") 2 EA
Supply, return and exhaust grilles/registers (SG-01, SG-02, RG-01, EG-01)
29 EA
Ductwork: galvanized spiral and rectangular supply, return, outside-air and exhaust ductwork with insulation, sealing, hangers and dampers
1 LS
Testing, adjusting and balancing (independent NEBB/AABC) and controls verification
1 LS
L. ELECTRICAL
Electrical service and distribution: 400A meter and disconnects, 400A 208/120V 3Ø MDP (NEMA 3R), 200A panelboards DP-1 and DP-2, feeders per plans, and grounding electrode system (E1.1, E1.2)
1 LS
Branch circuit wiring, conduit, wiring devices and equipment connections (E1.0, E1.3–E1.6)
1 LS
Light fixtures per Lighting Fixture Schedule (E1.2, E1.7), counted on E1.3/E1.4: Type A 20, B 14, C 1, D 19, E 2, F 3, H
66 EA
LED exit sign/emergency combo units and emergency lighting units (E1.3/E1.4: 6 E-1, 1 EM-1)
7 EA
4830 - 952160 — ALAMO EVENT CENTER - DEMOLITION & CONSTRUCTION SERVICES 15/26
All Bid Prices shall be entered into the Bid Table in the Portal. This list is provided for reference only.
Unit pricing shall be all-inclusive and include demolition, removal and disposal of existing construction and debris as well as all labor (including equipment programming), equipment, material, contingency, and supply costs and shall not be increased or changed for any reason other than changes requested or approved by the City.
Line Item#
Line Item Description Qty Unit of
Measure Unit Price
Total Price
Fire alarm system per E1.8–E1.10 and NFPA 72: addressable FACP, annunciator, communicator, detection and notification devices, AHU-01 duct detector/shutdown, wiring, permit, shop drawings and calculations, NFPA 72 acceptance testing, and central-station monitoring connection
1 LS
M. BID ALTERNATE (NOT INCLUDED IN TOTAL BASE BID)
ALT-1
Alternate No. 1: Automatic fire sprinkler system per NFPA 13, design-build, including permits, calculations and testing (Project Note 4, Sheet A0)
7,150 SF
TOTAL BID (Base Bid: Line Items 1–54; excludes Alternate No. 1)
Note: Quantities listed are approximate and provided for bidding purposes only. Bidders are responsible for verifying all quantities from the plans and site conditions. No additional compensation will be allowed for quantity discrepancies on lump sum items.
4830 - 952160 — ALAMO EVENT CENTER - DEMOLITION & CONSTRUCTION SERVICES 16/26
APPENDIX B
DFS Portal Confirmation and Declarations
The following forms are provided in this RFB for reference. Bidders must review each form and enter their response and/or upload the required documentation as directed in the Portal’s
Required Information section.
The confirmation/declaration statement or instructions for each form are provided in a gray box at the bottom of each form.
All responses must be true and accurate and shall be considered the equivalent of a legally-binding electronic signature.
1. Attachment 1: BID CERTIFICATION
2. Attachment 2: NON-COLLUSION DECLARATION
3. Attachment 3: CERTIFICATION REGARDING LOBBYING
4. Attachment 4: FORM 200.321 AFFIRMATIVE STEPS
5. Attachment 5: CERTIFICATION REGARDING DEBARMENT, SUSPENSION, INELIGIBILITY and VOLUNTARY EXCLUSION
6. Attachment 6: CONFLICT/NON-CONFLICT OF INTEREST STATEMENT
7. Attachment 7: DRUG-FREE WORKPLACE AFFIDAVIT
8. Attachment 8: INSURANCE COVERAGE DECLARATION
9. Attachment 9: CONTRACTOR AFFIDAVIT UNDER O.C.G.A. § 13-10-91(b)(1)
4830 - 952160 — ALAMO EVENT CENTER - DEMOLITION & CONSTRUCTION SERVICES 17/26
Attachment 1: Bid Certification
Bidding Certification: I have carefully examined the Request for Bids and any other documents accompanying or made a part of this Request for Bids.
I hereby propose to furnish the goods or services specified in the Request for Bids at the rates quoted in my Bid. I agree that my Bid will remain in effect for a period of up to one hundred eighty (180) days.
I agree to abide by all conditions of this Bid and understand that a background investigation may be conducted prior to award.
I certify that all information contained in this Bid is truthful to the best of my knowledge and belief. I further certify that I am duly authorized to submit this Bid on behalf of the Bidder as its act and deed and that the Bidder is ready, willing and able to perform if awarded the Contract.
I certify this Bid is made without prior understanding, agreement, connection, discussion, or collusion with any other person, firm or corporation submitting a Bid for the same product or service. I further certify that no officer, employee or agent of
City or of any other Bidder has a financial interest in this Bid. I further certify that the undersigned executed this Bidder's Certification with full knowledge and understanding of the matters therein contained and was duly authorized to do so.
DFS Portal Confirmation / Declaration:
By completing and submitting the Bid Table in the DFS Portal, you are certifying all of the above as well as the prices and data entered in the Bid Table. The previous Sample Bid Table is provided for reference only.
4830 - 952160 — ALAMO EVENT CENTER - DEMOLITION & CONSTRUCTION SERVICES 18/26
Attachment 2: NON-COLLUSION DECLARATION
The bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation. The bid is genuine and not collusive or sham. The bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid. The bidder has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or that anyone shall refrain from bidding. The bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder.
All statements contained in the bid are true. The bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, to any corporation, partnership, company, association, organization, bid depository, or to any member or agent thereof to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose.
Any person executing this declaration on behalf of a bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the bidder.
I declare under penalty of perjury under the applicable laws that the foregoing is true and correct.
Do you confirm that you have read the Non-Collusion declaration and therefore declare under penalty of perjury under the applicable laws that the Non-Collusion Declaration is true and correct? (Y/N)
4830 - 952160 — ALAMO EVENT CENTER - DEMOLITION & CONSTRUCTION SERVICES 19/26
Attachment 3: CERTIFICATION REGARDING LOBBYING
The undersigned certifies that, to the best of their knowledge and belief, that:
1. No Federal appropriated funds have been paid or will be paid, by or on behalf of the undersigned, to any person for influencing or attempting to influence an officer or employee of an agency, a Member of Congress, an officer or employee of Congress, or an employee of a
Member of Congress in connection with the awarding of any Federal contract, the making of any Federal grant, the making of any Federal loan, the entering into of any cooperative agreement, and the extension, continuation, renewal, amendment, or modification of any
Federal contract, grant, loan, or cooperative agreement.
2. If any funds other than Federal appropriated funds have been paid or will be paid to any person for influencing or attempting to influence an officer or employee of any agency, a
Member of Congress, an officer or employee of Congress, or an employee of a Member of
Congress in connection with this Federal contract, grant, loan, or cooperative agreement, the undersigned shall complete and submit Standard Form-LLL, “Disclosure Form to Report
Lobbying,” in accordance with its instruction.
3. The undersigned shall require that the language of this certification be included in the award document for all subawards at all tiers (including subcontracts, subgrants, and contracts under grants, loans, and cooperative agreements) and that all subrecipients shall certify and disclose accordingly.
This certification is a material representation of fact upon which reliance was placed when this transaction was made or entered into. Submission of this certification is a prerequisite for making or entering into this transaction imposed by section 1352, title 31 U.S. Code. Any person who fails to file the required certification shall be subject to a civil penalty of not less than $10,000 and not more than $100,000 for each such failure.
Do you, the Contractor, confirm that you have read the Certification Regarding Lobbying form and certify or affirm the truthfulness and accuracy of each statement of its certification and disclosure, if any. In addition, the Contractor understands and agrees that the provisions of 31
U.S.C. Chap. 38, Administrative Remedies for False Claims and Statements, apply to this certification and disclosure, if any. (True/False)
4830 - 952160 — ALAMO EVENT CENTER - DEMOLITION & CONSTRUCTION SERVICES 20/26
Attachment 4: FORM 200.321 AFFIRMATIVE STEPS
CONTRACTING WITH SMALL AND MINORITY BUSINESSES, WOMEN’S BUSINESS
ENTERPRISES, AND LABOR SURPLUS AREA FIRMS §200.321
The City is required to take all necessary affirmative steps to assure that minority business, women's business enterprises, and labor surplus area firms are used when possible. If contractor uses subcontractors, they are also required to take the following affirmative steps:
1. Placing qualified enterprises on solicitation lists.
2. Assuring that enterprises are solicited whenever they are potential sources.
3. Dividing total requirements when economically feasible into smaller tasks or quantities to permit maximum participation by enterprises.
4. Establishing delivery schedules, where the requirement permits, which encourage participation by enterprises.
5. Using the services and assistance, as appropriate, of such organizations as the Small
Business Administration and the Minority Business Development Agency of the
Department of Commerce.
Do you confirm that you have read the 200.321 Affirmative Steps Confirmation and agree to take the listed affirmative steps when using subcontractors. (Y/N)
4830 - 952160 — ALAMO EVENT CENTER - DEMOLITION & CONSTRUCTION SERVICES 21/26
Attachment 5: CERTIFICATION REGARDING DEBARMENT, SUSPENSION, INELIGIBILITY and VOLUNTARY EXCLUSION
Neither the entity or its principals are presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from participation by any federal department or agency.
Do you confirm that neither the entity nor its principals are presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from participation by any federal department or agency? (Y/N)
4830 - 952160 — ALAMO EVENT CENTER - DEMOLITION & CONSTRUCTION SERVICES 22/26
Attachment 6: CONFLICT/NON-CONFLICT OF INTEREST STATEMENT
To the best of our knowledge the bidder has no potential conflict of interest due to any other clients, contracts, or property interest for this project. [ SELECT YES IF TRUE ]
OR
The bidder, by attachment, submits information which may be a potential conflict of interest due to other clients, contracts, or property interest for this project. [ SELECT NO IF TRUE &
UPLOAD DOCUMENTATION ]
Failure to answer appropriately may result in disqualification of your bid.
Do you confirm that to the best of your knowledge the undersigned bidder has no potential conflict of interest due to any other clients, contracts, or property interest for this project?
(Y/N)
If answered no, documentation must be uploaded containing information regarding what may be a potential conflict of interest due to other clients, contracts, or property interest for this project.
4830 - 952160 — ALAMO EVENT CENTER - DEMOLITION & CONSTRUCTION SERVICES 23/26
Attachment 7: DRUG-FREE WORKPLACE AFFIDAVIT
The undersigned certifies that the responding firm has taken steps to:
1. Publish a statement notifying employees that the unlawful manufacture, distribution, dispensing, possession, or use of a controlled substance is prohibited in the workplace and specifying the actions that will be taken against employees for violations of such prohibition.
2. Inform employees about the dangers of drug abuse in the workplace, the business's policy of maintaining a drug-free workplace, any available drug counseling, rehabilitation, and employee assistance programs, and the penalties that may be imposed upon employees for drug abuse violations.
3. Give each employee engaged in providing the commodities or contractual services that are proposed, a copy of the drug- free workplace statement.
4. In the statement specified in drug-free workplace statement, notify the employees that as a condition of working on the commodities or contractual services that are under bid the employee will abide by the terms of the statement and will notify the employer of any conviction of or plea of guilty or nolo contendere to any violation of any controlled substance law of the United States or any state for a violation occurring in the workplace no later than five (5) days after such conviction.
5. Impose a sanction on or require the satisfactory participation in a drug abuse assistance or rehabilitation program if such is available in the employee's community by any employee who is so convicted.
6. Make a good faith effort to continue to maintain a drug-free workplace through implementation of this section.
I certify that this firm complies fully with the above requirements.
Do you confirm that you have read the Drug-Free Workplace Affidavit and certify that the responding company…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .