Airpot_Fiber_Replacement_Plans_Final.pdf

PDF 19 MB Posted

Attached to
Dane County Regional Airport Perimeter Fiber Project
Solicitation number
2024-RFB-029-PR
Issued by
Dane County, Wisconsin

About this file

The document is a set of construction and engineering plans for the Dane County Regional Airport Perimeter Fiber Project in Wisconsin. The project involves replacing and upgrading the existing fiber optic cable infrastructure across the airport campus, specifically focusing on removing existing 12-count fiber optic cables and installing new 48-count fiber optic cables along various conduit routes. The plans detail comprehensive fiber optic network improvements, including the installation of new handholes, splice enclosures, termination panels, and conduits across multiple locations within the airport's perimeter.

The project scope includes detailed technical specifications for fiber optic cable replacement at multiple sites, such as vehicle gates, field cabinets, communication rooms, and other strategic locations. The plans specify furnishing and installing 2" HDPE conduits, 48-count fiber optic cables, above-ground splice enclosure cabinets, and associated termination equipment. Notably, the project requires careful coordination, with specific instructions to minimize downtime (not exceeding two hours between gate sections) and special considerations for working in areas like the National Guard property. The documents also emphasize the contractor's responsibility for locating existing infrastructure, protecting environmentally sensitive areas, and coordinating with airport engineering staff during the implementation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GOVERNOR

NELSON

T

T

C

M

M

Sun Prairie

Middleton

Monona

Waunakee

Maple Bluff

Shorewood

Creek Token

Burke

WESTPORT

BURKE

BLOOMING

GROVE

9 4 5

Madison

17 16

CV

BB AB

TT

138 240

135 97

102132

Lake Monona

Lake Mendota

Ya ha ra

R.

Mile Cr.

Cr.

Toke n

Title General Notes and Legend Estimate of Quantities Miscellaneous Quantities Right of Way Plat Plan and Profile Standard Detail Drawings Sign Plates Structure Plans Computer Earthwork Data Cross Sections

ORDER OF SHEETS

LAYOUT

SCALE

CORPORATE LIMITS

PROPERTY LINE

LOT LINE

EXISTING RIGHT OF WAY

SLOPE INTERCEPT

COMBUSTIBLE FLUIDS

POWER POLE

TELEPHONE POLE

ORIGINAL GROUND

MARSH OR ROCK PROFILE

UTILITY PEDESTAL

GAS

ELECTRIC

G

E

T

PROPOSED OR NEW R/W LINE

CAUTION

WOODED OR SHRUB AREA

MARSH AREA

EXISTING CULVERT

PROPOSED CULVERT

(Box or Pipe)

CULVERT (Profile View)

CONVENTIONAL SYMBOLS

ROCK

(To be noted as such)

SS

W

SANSANITARY SEWER

STORM SEWER

WATER

COUNTY:

PLOT NAME : H:\PROJECTS\12000\12598\CAD_BIM\SHEETSPLAN\AIRPORT\TITLE - GENERAL NOTES - PLAN SHEETS.DWGFILE NAME : 1/25/2024 11:21 AMPLOT DATE : PLOT BY : BRENT BOKEMPER

FOFIBER OPTIC

UTILITIESREFERENCE LINE

GRADE LINE

PROFILE

TELEPHONE

SPECIAL DITCH LABELLIMITED HIGHWAY EASEMENT

TOTAL SHEETS = 16

GRADE ELEVATION 95

.3

PLAN

Section No.

Section No.

Section No.

Section No.

Section No.

Section No.

Section No.

Section No.

Section No.

Section No.

Section No.

300'EB'

COORDINATES ON THIS PLAN ARE REFERENCED TO THE WISCONSIN

COUNTY COORDINATE SYSTEM, DANE COUNTY.

PROJECT LOCATION

DANE COUNTY REGIONAL AIRPORT

DANE COUNTY

2.0 MI.

E

DANE

WISDOT/CADDS SHEET 42

ECOUNTY: DANE

H:\PROJECTS\12000\12598\CAD_BIM\SHEETSPLAN\AIRPORT\TITLE - GENERAL NOTES - PLAN SHEETS.DWGFILE NAME : 1/25/2024 11:21 AMPLOT DATE : PLOT BY : BRENT BOKEMPER

PROJECT: DANE COUNTY REGIONAL AIRPORT

PLOT NAME :

SHEET

PLOT SCALE : 1 IN:100 FT

GENERAL NOTES

LAYOUT NAME - General Notes

DIGGERS HOTLINE

Dial or (800)242-8511 www.DiggersHotline.com

COMMUNICATIONS

THESE PLANS AND THE ASSOCIATED SPECIAL PROVISIONS REFLECT CONDITIONS KNOWN DURING THE DEVELOPMENT OF THE PLANS AND SPECIAL PROVISIONS. THE CONTRACTOR IS FULLY RESPONSIBLE FOR THE APPLICATION OF ALL WORK SHOWN IN THE PLANS TO THE ACTUAL PHYSICAL FIELD CONDITIONS IN ORDER TO PROVIDE A COMPLETE AND ACCEPTED PROJECT. IN THE EVENT THAT ACTUAL PHYSICAL FIELD CONDITIONS AFFECT OR PREVENT THE APPLICATION OR PROGRESSION OF ANY WORK SHOWN IN THE PLANS OR SPECIAL PROVISIONS, THE CONTRACTOR SHALL NOTIFY THE ENGINEER IMMEDIATELY, PRIOR TO ANY FURTHER

WORK BEING PERFORMED.

ANY CHANGES TO THE WORK SHOWN IN THE PLANS SHALL BE APPROVED IN WRITING BY THE ENGINEER PRIOR TO THE WORK

BEING PERFORMED.

THE LOCATIONS OF EXISTING AND PROPOSED UTILITY INSTALLATIONS SHOWN ON THE PLANS ARE APPROXIMATE. THERE MAY BE

OTHER UTILITY INSTALLATIONS WITHIN THE PROJECT AREA THAT ARE NOT SHOWN.

THE CONTRACTOR SHALL CONTACT DIGGERS HOTLINE TO LOCATE ALL PUBLIC UTILITIES. PUBLIC UTILITY LOCATORS WILL REQUIRE AN ESCORT WHILE INSIDE THE PERIMETER FENCE. FOR PRIVATE AND FAA UTILITY LOCATES, THE CONTRACTOR SHALL

COORDINATE WITH THE AIRPORT ENGINEER.

ALL EXISTING UNDERGROUND AND ABOVE GROUND STRUCTURES AND FACILITIES WITHIN THE SCOPE OF THIS PROJECT MAY NOT BE SHOWN IN THE PLANS. THE CONTRACTOR IS FULLY RESPONSIBLE FOR LOCATING ALL UNDERGROUND AND ABOVE GROUND

STRUCTURES AND FACILITIES.

TYPICAL EQUIPMENT FOR THIS WORK INCLUDES A PICKUP TRUCK, MINI EXCAVATOR, CONDUIT PLOW, BORING MACHINE, AND A

FIBER SPLICING TRAILER.

NOTIFY THE ENGINEER (PRIMARY 608-241-1064, SECONDARY 763-452-4714) AT LEAST TWO WEEKS PRIOR TO STAKING ANY

DEVICE LOCATIONS.

NOTIFY THE ENGINEER (PRIMARY 608-241-1064, SECONDARY 763-452-4714) AT LEAST FORTY-EIGHT HOURS PRIOR TO

PENETRATING BUILDINGS.

NOTIFY THE ENGINEER (PRIMARY 608-241-1064, SECONDARY 763-452-4714) AT LEAST FORTY-EIGHT HOURS IN ADVANCE OF ANY WORK ON CITY OF MADISON OWNED OR MAINTAINED FACILITIES TO ARRANGE FOR AN INSPECTOR TO BE PRESENT DURING ALL SUCH WORK. WORK SHALL NOT COMMENCE UNTIL THE CITY TRAFFIC ENGINEERING INSPECTOR IS PRESENT.

CALL MIKE BENZSCHAWEL (608-235-3649) AT THE CITY OF MADISON TRAFFIC ENGINEERING SHOP AT LEAST TWENTY-FOUR

HOURS IN ADVANCE OF WORK WITHIN THE CITY OF MADISON RIGHT-OF-WAY.

HAND DIG TRENCHES NEAR EXISTING CONDUITS AND CABLES. VERIFY DEPTHS OF EXISTING CONDUITS AND CABLES PRIOR TO

CROSSING BY DIRECTIONAL BORE.

ALL CABLE PULLING AND SPLICING OPERATIONS SHALL OCCUR AT ACCESS POINTS (HANDHOLES, COMMUNICATION VAULTS, ETC.)

SHOWN IN THE PLANS.

ALL SPLICING OPERATIONS SHALL BE COORDINATED WITH THE AIRPORT ENGINEER. THE FIBER NETWORK SHALL HAVE A

MAXIMUM DOWNTIME OF TWO HOURS OR AS APPROVED BY THE AIRPORT ENGINEER.

ALL FIBER OPTIC CONNECTORS SHALL BE LC UNLESS SPECIFIED OTHERWISE.

WETLANDS, WATERWAYS, AND OTHER ENVIRONMENTALLY SENSITIVE AREAS SHALL BE PROTECTED AT ALL TIMES. DO NOT STORE

EQUIPMENT OR MATERIALS NEAR THESE SITES UNLESS APPROVED BY THE ENGINEER.

NO TREES OR SHRUBS ARE TO BE REMOVED WITHOUT APPROVAL OF THE ENGINEER.

AREAS WITHIN THE RIGHT-OF-WAY DISTURBED DUE TO CONSTRUCTION OPERATIONS ARE TO BE RESTORED TO THE ORIGINAL CONDITION WITH TOPSOIL, FERTILIZER, SEED, AND MULCH. NO PAYMENT WILL BE MADE FOR RESTORING AREAS DISTURBED DUE

TO CONSTRUCTION OPERATIONS.

DANE COUNTY REGIONAL AIRPORT

JASON PEARCY

608-241-1064

PEARCY.JASON@MSNAIRPORT.COM

4000 INTERNATIONAL LANE

MADISON, WI 53704

SRF CONSULTING GROUP

ALYSSA SEGALL

763-452-4714

ASEGALL@SRFCONSULTING.COM

ERIK MINGE

763-249-6739

EMINGE@SRFCONSULTING.COM

3701 WAYZATA BLVD

MINNEAPOLIS, MN 55416-3791

STANDARD ABBREVIATIONS

EX ----- EXISTING

FO ----- FIBER OPTIC

HH ----- HANDHOLE

QP ----- QUANTITY POINT

SM ----- SINGLE MODE

SC ----- SPLICE/PATCH PANEL ENCLOSURE

LEGEND

DESCRIPTION SYMBOL

HANDHOLE -----------------------------------

SPLICE ENCLOSURE -----------------------

FIELD CABINET ------------------------------

CONDUIT -------------------------------------

QUANTITY POINT ---------------------------

VECHILE GATE -------------------------------

CCTV CAMERA -------------------------------

GENERAL NOTES

PLOT SCALE : 1 IN:1000 FT

WISDOT/CADDS SHEET 44

ECOUNTY: DANE

H:\PROJECTS\12000\12598\CAD_BIM\SHEETSPLAN\AIRPORT\PO.DWGFILE NAME : 1/25/2024 11:22 AMPLOT DATE : PLOT BY : BRENT BOKEMPER

PROJECT: DANE COUNTY REGIONAL AIRPORT

PLOT NAME :

SHEET PROJECT OVERVIEW

LAYOUT NAME - Project Overview

I-94

PROJECT LOCATION

US-151

I-90

W I-113

U S-51

SCALE

0 1,000 FT

H:\PROJECTS\12000\12598\CAD_BIM\SHEETSPLAN\AIRPORT\TYPE V HH.DWGFILE NAME : 1/25/2024 11:50 AMPLOT DATE : PLOT BY : BRENT BOKEMPER

PROJECT: DANE COUNTY REGIONAL AIRPORT

PLOT NAME :

SHEET

PLOT SCALE : Custom

COMMUNICATION SCHEMATICS

LAYOUT NAME - FO1

H:\PROJECTS\12000\12598\CAD_BIM\SHEETSPLAN\AIRPORT\TYPE V HH.DWGFILE NAME : 1/25/2024 11:54 AMPLOT DATE : PLOT BY : BRENT BOKEMPER

PROJECT: DANE COUNTY REGIONAL AIRPORT

PLOT NAME :

SHEET

PLOT SCALE : Custom

COMMUNICATION SCHEMATICS

LAYOUT NAME - FO2

H:\PROJECTS\12000\12598\CAD_BIM\SHEETSPLAN\AIRPORT\TYPE V HH.DWGFILE NAME : 1/25/2024 11:22 AMPLOT DATE : PLOT BY : BRENT BOKEMPER

PROJECT: DANE COUNTY REGIONAL AIRPORT

PLOT NAME :

SHEET

PLOT SCALE : Custom

COMMUNICATION SCHEMATICS

LAYOUT NAME - FO3

H:\PROJECTS\12000\12598\CAD_BIM\SHEETSPLAN\AIRPORT\TYPE V HH.DWGFILE NAME : 1/25/2024 11:22 AMPLOT DATE : PLOT BY : BRENT BOKEMPER

PROJECT: DANE COUNTY REGIONAL AIRPORT

PLOT NAME :

SHEET

PLOT SCALE : Custom

COMMUNICATION SCHEMATICS

LAYOUT NAME - FO4

H:\PROJECTS\12000\12598\CAD_BIM\SHEETSPLAN\AIRPORT\TYPE V HH.DWGFILE NAME : 1/25/2024 11:22 AMPLOT DATE : PLOT BY : BRENT BOKEMPER

PROJECT: DANE COUNTY REGIONAL AIRPORT

PLOT NAME :

SHEET

PLOT SCALE : Custom

COMMUNICATION SCHEMATICS

LAYOUT NAME - FO5

H:\PROJECTS\12000\12598\CAD_BIM\SHEETSPLAN\AIRPORT\TYPE V HH.DWGFILE NAME : 1/25/2024 11:22 AMPLOT DATE : PLOT BY : BRENT BOKEMPER

PROJECT: DANE COUNTY REGIONAL AIRPORT

PLOT NAME :

SHEET

PLOT SCALE : Custom

LAYOUT NAME - FO6

9COMMUNICATION SCHEMATICS

H:\PROJECTS\12000\12598\CAD_BIM\SHEETSPLAN\AIRPORT\TYPE V HH.DWGFILE NAME : 1/25/2024 11:22 AMPLOT DATE : PLOT BY : BRENT BOKEMPER

PROJECT: DANE COUNTY REGIONAL AIRPORT

PLOT NAME :

SHEET

PLOT SCALE : Custom

LAYOUT NAME - FO7

10COMMUNICATION SCHEMATICS

H:\PROJECTS\12000\12598\CAD_BIM\SHEETSPLAN\AIRPORT\TYPE V HH.DWGFILE NAME : 1/25/2024 11:22 AMPLOT DATE : PLOT BY : BRENT BOKEMPER

PROJECT: DANE COUNTY REGIONAL AIRPORT

PLOT NAME :

SHEET

PLOT SCALE : Custom

LAYOUT NAME - FO8

11COMMUNICATION SCHEMATICS

H:\PROJECTS\12000\12598\CAD_BIM\SHEETSPLAN\AIRPORT\CONSTRUCTION DETAIL PLAN SHEET.DWGFILE NAME : 1/25/2024 11:22 AMPLOT DATE : PLOT BY : BRENT BOKEMPER

PROJECT: DANE COUNTY AIRPORT

PLOT NAME :

SHEET

PLOT SCALE : 1 IN:100 FT

CONSTRUCTION PLANS

LAYOUT NAME - Construction Plans

M

ATCH

LIN

E A

MATCHLINE B

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

FIBER OPTIC CABLE 48-CT

EXISTING:

CONTROLLED VEHICLE GATE

VEHICLE GATE CABINET

FURNISH AND INSTALL:

TERMINATION PANEL

EXISTING:

CHILLER PLANT

COMMUNICATION ROOM 10

FURNISH & INSTALL:

1 FIBER OPTIC PANEL

24-FIBER OPTIC TERMINATIONS

14-FIBER OPTIC PATCH CORDS

ADD 50 FEET FIBER FOR

CONNECTION TO CHILLER PLANT

EXISTING:

1-4" CONDUIT

FIBER OPTIC CABLE 48-CT

COORDINATE WITH SOUTH TERMINAL

EXPANSION PROJECT ENGINEER FOR

EXACT CONDUIT LOCATION

NOTES:

1. EXISTING FIBER TO BE REMOVED BETWEEN ONE SET OF GATES AT A

TIME. DOWN TIME SHALL NOT EXCEED TWO HOURS.

2. SEE SPLICE/ PATCH PANEL DETAIL.

3. THIS AREA IS PROPERTY OF THE NATIONAL GUARD. PRIOR TO

BEGINNING WORK IN THIS AREA OR ACCESSING THIS AREA,

CONTRACTOR SHALL COORDINATE WITH THE AIRPORT AND THE

NATIONAL GUARD.

4. ALL EXISTING HAND HOLES WITHIN THE SCOPE OF THIS PROJECT

MAY NOT BE SHOWN IN THE PLANS. THE CONTRACTOR IS FULLY

RESPONSIBLE FOR LOCATING HAND HOLES.

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2" HDPE CONDUIT

2-FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

FIBER OPTIC CABLE 48-CT

FURNISH & INSTALL:

ABOVE-GROUND SPLICE ENCLOSURE

CABINET

SEE NOTE 2

EXISTING:

CONTROLLED VEHICLE GATE

VEHICLE GATE CABINET

FURNISH AND INSTALL:

TERMINATION PANEL

FURNISH & INSTALL:

ABOVE-GROUND SPLICE ENCLOSURE

CABINET

SEE NOTE 2

FURNISH & INSTALL:

ABOVE-GROUND SPLICE ENCLOSURE

CABINET

SEE NOTE 2

EXISTING:

CONTROLLED VEHICLE GATE

VEHICLE GATE CABINET

FURNISH AND INSTALL:

TERMINATION PANEL

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2" HDPE CONDUIT

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2" HDPE CONDUIT

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

FIBER OPTIC CABLE 48-CT

SEE NOTE 3

SCALE

0 400FT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2" HDPE CONDUIT

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2" HDPE CONDUIT

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2-FIBER OPTIC CABLE 48-CT

H:\PROJECTS\12000\12598\CAD_BIM\SHEETSPLAN\AIRPORT\CONSTRUCTION DETAIL PLAN SHEET.DWGFILE NAME : 1/25/2024 11:32 AMPLOT DATE : PLOT BY : BRENT BOKEMPER

PROJECT: DANE COUNTY AIRPORT

PLOT NAME :

SHEET

PLOT SCALE : 1 IN:100 FT

CONSTRUCTION PLANS

LAYOUT NAME - Construction Plans (2)

MATCHLINE C

M

AT

CH

LI

N E

A

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

FIBER OPTIC CABLE 48-CT

EXISTING:

CONTROLLED VEHICLE GATE

VEHICLE GATE CABINET

FURNISH AND INSTALL:

TERMINATION PANEL

EXISTING:

CONTROLLED VEHICLE GATE

VEHICLE GATE CABINET

FURNISH AND INSTALL:

TERMINATION PANEL

SEE NOTE 3

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2" HDPE CONDUIT

FIBER OPTIC CABLE 48-CT

EXISTING:

2-2" HDPE CONDUITS

FURNISH & INSTALL:

FIBER OPTIC CABLE 48-CT

EXISTING:

STAIR A J-BOX

FURNISH & INSTALL:

50' OF FIBER FOR

CONNECTION TO TERMINAL

EXISTING:

1 CCTV CAMERA

(POLE MOUNTED)

EXISTING:

FIELD WEST CABINET

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2" HDPE CONDUIT

FIBER OPTIC CABLE 48-CT

NOTES:

1. EXISTING FIBER TO BE REMOVED BETWEEN ONE SET OF GATES AT A

TIME. DOWN TIME SHALL NOT EXCEED TWO HOURS.

2. SEE SPLICE/ PATCH PANEL DETAIL.

3. CABINET IS INSIDE LAV. CART BUILDING AND CONNECTS TO VG-6.

4. CONTRACTOR SHALL COORDINATE WITH THE ENGINEER PRIOR TO

MOUNTING THE NEW SPLICE/PATCH PANEL ENCLOSURE INSIDE THE

LAV. CART BUILDING

5. ALL EXISTING HAND HOLES WITHIN THE SCOPE OF THIS PROJECT

MAY NOT BE SHOWN IN THE PLANS. THE CONTRACTOR IS FULLY

RESPONSIBLE FOR LOCATING HAND HOLES.

FURNISH & INSTALL:

ABOVE-GROUND SPLICE ENCLOSURE

CABINET

SEE NOTES 2 & 4

FURNISH & INSTALL:

ABOVE-GROUND SPLICE ENCLOSURE

CABINET

SEE NOTE 2

SCALE

0 400FT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2" HDPE CONDUIT

FIBER OPTIC CABLE 48-CT

FURNISH & INSTALL:

ABOVE-GROUND SPLICE ENCLOSURE

CABINET

SEE NOTE 2

FURNISH & INSTALL:

2" HDPE CONDUIT

2-FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2" HDPE CONDUIT

FIBER OPTIC CABLE 48-CT

H:\PROJECTS\12000\12598\CAD_BIM\SHEETSPLAN\AIRPORT\CONSTRUCTION DETAIL PLAN SHEET.DWGFILE NAME : 1/25/2024 12:30 PMPLOT DATE : PLOT BY : BRENT BOKEMPER

PROJECT: DANE COUNTY AIRPORT

PLOT NAME :

SHEET

PLOT SCALE : 1 IN:100 FT

CONSTRUCTION PLANS

LAYOUT NAME - Construction Plans (3)

M

AT

CH

LI

N E

D

MATCHLINE C

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

FIBER OPTIC CABLE 48-CT

EXISTING:

CONTROLLED VEHICLE GATE

VEHICLE GATE CABINET

FURNISH AND INSTALL:

TERMINATION PANEL

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FURNISH & INSTALL:

2-FIBER OPTIC CABLE 48-CT

EXISTING:

1 CCTV CAMERA (POLE MOUNTED)

EXISTING:

FIELD NORTH CABINET

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2" HDPE CONDUIT

FIBER OPTIC CABLE 48-CT

EXISTING:

CONTROLLED VEHICLE GATE

VEHICLE GATE CABINET

FURNISH AND INSTALL:

TERMINATION PANEL

EXISTING:

CONTROLLED VEHICLE GATE

VEHICLE GATE CABINET

FURNISH AND INSTALL:

TERMINATION PANEL

FURNISH & INSTALL:

ABOVE-GROUND SPLICE ENCLOSURE

CABINET

SEE NOTE 2

FURNISH & INSTALL:

ABOVE-GROUND SPLICE ENCLOSURE

CABINET

SEE NOTE 2

EXISTING:

CONTROLLED VEHICLE GATE

VEHICLE GATE CABINET

FURNISH AND INSTALL:

TERMINATION PANEL

FURNISH & INSTALL:

ABOVE-GROUND SPLICE ENCLOSURE

CABINET

SEE NOTE 2

NOTES:

1. EXISTING FIBER TO BE REMOVED BETWEEN ONE SET OF GATES AT A

TIME. DOWN TIME SHALL NOT EXCEED TWO HOURS.

2. SEE SPLICE/ PATCH PANEL DETAIL.

3. ALL EXISTING HAND HOLES WITHIN THE SCOPE OF THIS PROJECT

MAY NOT BE SHOWN IN THE PLANS. THE CONTRACTOR IS FULLY

RESPONSIBLE FOR LOCATING HAND HOLES.

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2" HDPE CONDUIT

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2" HDPE CONDUIT

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2" HDPE CONDUIT

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2" HDPE CONDUIT

2-FIBER OPTIC CABLE 48-CT

SCALE

0 400FT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2" HDPE CONDUIT

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2" HDPE CONDUIT

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2" HDPE CONDUIT

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2" HDPE CONDUIT

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2-FIBER OPTIC CABLE 48-CT

FURNISH & INSTALL:

ABOVE-GROUND SPLICE ENCLOSURE

CABINET

SEE NOTE 2

FURNISH & INSTALL:

2-FIBER OPTIC CABLE 48-CT

H:\PROJECTS\12000\12598\CAD_BIM\SHEETSPLAN\AIRPORT\CONSTRUCTION DETAIL PLAN SHEET.DWGFILE NAME : 1/25/2024 11:23 AMPLOT DATE : PLOT BY : BRENT BOKEMPER

PROJECT: DANE COUNTY AIRPORT

PLOT NAME :

SHEET

PLOT SCALE : 1 IN:100 FT

CONSTRUCTION PLANS

LAYOUT NAME - Construction Plans (4)

MATCHLINE B

M

ATCH

LIN

E D

EXISTING:

CONTROLLED VEHICLE GATE

VEHICLE GATE CABINET

FURNISH AND INSTALL:

TERMINATION PANEL

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

FIBER OPTIC CABLE 48-CT

SEE NOTE 3

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2" HDPE CONDUIT

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

FIBER OPTIC CABLE 48-CT

FURNISH & INSTALL:

ABOVE-GROUND SPLICE ENCLOSURE

CABINET

SEE NOTE 2

FURNISH & INSTALL:

ABOVE-GROUND SPLICE ENCLOSURE

CABINET

SEE NOTE 2

EXISTING:

CONTROLLED VEHICLE GATE

VEHICLE GATE CABINET

FURNISH AND INSTALL:

TERMINATION PANEL

FURNISH & INSTALL:

ABOVE-GROUND SPLICE ENCLOSURE

CABINET

SEE NOTE 2

EXISTING:

CONTROLLED VEHICLE GATE

VEHICLE GATE CABINET

FURNISH AND INSTALL:

TERMINATION PANEL

EXISTING:

CONTROLLED VEHICLE GATE

VEHICLE GATE CABINET

FURNISH AND INSTALL:

TERMINATION PANEL

FURNISH & INSTALL:

ABOVE-GROUND SPLICE ENCLOSURE

CABINET

SEE NOTE 2

EXISTING:

CONTROLLED VEHICLE GATE

VEHICLE GATE CABINET

FURNISH AND INSTALL:

TERMINATION PANEL

FURNISH & INSTALL:

ABOVE-GROUND SPLICE ENCLOSURE

CABINET

SEE NOTE 2

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

FIBER OPTIC CABLE 48-CT

NOTES:

1. EXISTING FIBER TO BE REMOVED BETWEEN ONE SET OF GATES AT A

TIME. DOWN TIME SHALL NOT EXCEED TWO HOURS.

2. SEE SPLICE/ PATCH PANEL DETAIL.

3. THIS AREA IS PROPERTY OF THE NATIONAL GUARD. PRIOR TO

BEGINNING WORK IN THIS AREA OR ACCESSING THIS AREA,

CONTRACTOR SHALL COORDINATE WITH THE AIRPORT AND THE

NATIONAL GUARD.

4. ALL EXISTING HAND HOLES WITHIN THE SCOPE OF THIS PROJECT

MAY NOT BE SHOWN IN THE PLANS. THE CONTRACTOR IS FULLY

RESPONSIBLE FOR LOCATING HAND HOLES.

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2" HDPE CONDUIT

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2" HDPE CONDUIT

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2" HDPE CONDUIT

FIBER OPTIC CABLE 48-CT

SCALE

0 400FT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

2" HDPE CONDUIT

FIBER OPTIC CABLE 48-CT

EXISTING:

2-1.5" HDPE CONDUITS

FIBER OPTIC CABLE 12-CT

REMOVE:

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

FIBER OPTIC CABLE 48-CT

PLOT SCALE : 1 IN:5 FT

ECOUNTY: DANE

H:\PROJECTS\12000\12598\CAD_BIM\SHEETSPLAN\AIRPORT\SPLICE-PATCH PANEL ENCLOSURE DETAIL.DWGFILE NAME : 1/25/2024 11:23 AMPLOT DATE : PLOT BY : BRENT BOKEMPER

PROJECT: DANE COUNTY REGIONAL AIRPORT

PLOT NAME :

SHEET FIBER SPLICE/PATCH PANEL ENCLOSURE DETAIL

LAYOUT NAME - Project Overview

NOTES:

1. WHERE POSSIBLE, THE CONTRACTOR SHALL ADD BRACKETS TO THE MOUNTING STRUCTURE.

CONTRACTOR SHALL MOUNT ENCLOSURE TO ADDED BRACKETS. IF THIS IS NOT FEASIBLE,

CONTRACTOR SHALL PROPOSE A DIFFERENT MOUNTING LOCATION AND RECIEVE APPROVAL FROM

THE ENGINEER.

2. SEE COMMUNICATION SCHEMATICS FOR SPLICING AND TERMINATION DETAILS.

3. CONTRACTOR SHALL CONNECT THE NEW CONDUIT BY CREATING NEW PENETRATION IN THE

BOTTOM OF THE EXISTING CABINET. CONTRACTOR SHALL SECURE CONDUIT TO THE CABINET AND

CREATE A WATERTIGHT SEAL. CONTRACTOR SHALL BE RESPONSIBLE FOR REPAIRING AND

REPLACING ANY INFRASTRUCTURE DAMAGED DURING THE CONDUIT INSTALLATION.

4. CONTRACTOR SHALL CONNECT CONDUIT TO ENCLOSURE AND UTILIZE A RUBBER GROMMET OR

OTHER METHOD APPROVED BY THE ENGINEER TO CREATE A WATERTIGHT CONNECTION.

5. THIS IS AN EXAMPLE OF SITE CONDITIONS THAT MAY BE ENCOUNTERED. SITES MAY DIFFER.

6. SITES WITH CCTV CABINET WILL UTILIZE EXISTING CONDUIT SYSTEM FOR FURNISH AND INSTALL

'GATOR' OR SIMILAR CABLE WITH INTEGRATED PATCH PANEL FOR CCTV. SEE COMMUNICATION

SCHEMATICS.

FURNISH & INSTALL:

1 - FIBER OPTIC

SPLICE/PATCH PANEL

ENCLOSURE

SEE NOTES 1 & 2.

SEE NOTE 1

SEE NOTE 3

SEE NOTE 4

FURNISH & INSTALL:

1 - 2" FLEXIBLE METAL CONDUIT

1 - GATOR OR SIMILAR INTEGRATED

PATCH CABLE

FURNISH & INSTALL:

1 - 2" HDPE CONDUIT

2 - FIBER OPTIC CABLE 48-CT

SCALE

0 5FT

REMOVE:

EXISTING FIBER OPTIC CABLE 12-CT

SEE NOTE 6

Sheets and Views
1 Title - General Notes - Plan Sheets - Title
2 Title - General Notes - Plan Sheets - General Notes
3 PO - Project Overview
4 Type V HH - CS
5 Type V HH - CS (2)
6 Type V HH - CS (3)
7 Type V HH - CS (4)
8 Type V HH - CS (5)
9 Type V HH - CS (6)
10 Type V HH - CS (7)
11 Type V HH - CS (8)
12 Construction Detail Plan Sheet - Construction Plans
OLE1
13 Construction Detail Plan Sheet - Construction Plans (2)
OLE1
14 Construction Detail Plan Sheet - Construction Plans (3)
OLE1
15 Construction Detail Plan Sheet - Construction Plans (4)
OLE1

16 Splice-Patch Panel Enclosure Detail - Project Overview

File details come from the government source that posted it. Updated .